TPC Collaboration Meeting 2-3.9.02Peter Glassel 1 Reminder on Installation Schedule (ALICE Forum June 2002)  Install Muon magnet directly into experimental.

Similar presentations


Presentation on theme: "TPC Collaboration Meeting 2-3.9.02Peter Glassel 1 Reminder on Installation Schedule (ALICE Forum June 2002)  Install Muon magnet directly into experimental."— Presentation transcript:

1 TPC Collaboration Meeting 2-3.9.02Peter Glassel 1 Reminder on Installation Schedule (ALICE Forum June 2002)  Install Muon magnet directly into experimental hall in temporary position No pre-installation of magnet, absorber, Muon filter, Muon chambers in SXL2  Assembly of absorber at Point 2 Assembly line in SX2 – if agreement with Sarov  No displacement of TPC and clean-room Keep clean room in SXL2  Installation of TPC / ITS / Vacuum chamber This installation has a duration of 6 months and is regarded as a block We assume that no other activity can proceed in parallel  TDR / TOF / PHOS have two installation periods Period 1: Before TPC/ITS/Va Period 2: After the installation of TPC/ITS/Va (Vacuum chamber in place)

2 TPC Collaboration Meeting 2-3.9.02Peter Glassel 2 Installation Phases  Phase 1 now – 01.06.2005 Large structures for Muon arm  Phase 201.06.2005 – 01.05.2006 TRD/TOF/PHOS/HMPID  Phase 301.05.2006 – 01.11.2006 TPC/ITS/Vacuum  Phase 401.11.2006 – 01.04.2007 Commissioning PMD and FMD, V0, T0, Si3 on RB24 side Last TOF modules Shielding / machine interface / close L3 magnet etc

3 TPC Collaboration Meeting 2-3.9.02Peter Glassel 3 Installation of detectors into space-frame  Installation shaft 7 x 15 m2  Working position outside the magnet  Installation in the space-frame 1 st Period; outside / inside the L3 magnet 2 nd Period; after TPC/ITS/Va installation

4 TPC Collaboration Meeting 2-3.9.02Peter Glassel 4 Installation mile stones  Close L3 magnet back door Best guess to-day is beginning of 2004  Installation of space-frame In the new planning the space-frame is moved from SXL2 and installed in the experimental area in June 2005 I.e. pre-installation testing in SXL2, involving the space-frame, must end at this date