RECONSTRUCTION OF County Route 1, Golden Shores Pkwy & Oatman Highway Public Information Meeting Golden Shores Senior Center Tuesday, June 3, 2015
Agenda Purpose of Project Scope of Project Roadway Circulation Private Property Impacts Environmental & Right-of-Way Constraints Funding Schedule & Public Involvement Plan
Purpose of Meeting Inform you of the project No alternatives have been developed We have started to identify restraints and fatal flaws Obtain your feedback
Scope of Project How did the project come about … via a “safety study” Preliminary Design o 1) Study o 2) Scoping, with 2 PIM’s Final Design, with 1 PIM Construction
Project Overview Map County Route 1 / Golden Shores Pkwy / Oatman Hwy
Scope of Project Reconstruct “Six Points” Intersection Reconstruct Powell Lake Road & Oatman Highway Intersection Eliminate CR 1 between Powell Lake Road and Oatman Highway Cul-de-sac Golden Shores Pkwy
Roundabout Concept
Thru-about Concept
Conventional Intersection Concept
Scope of Project Maintain Business Access Maintain Bike & Pedestrian Circulation Right-of-Way may be Required Alternate Routes Possible Using Adjacent Streets
Roadway Circulation Roundabout, thru-about & conventional layouts (?? - show sample of each) Screening … o fatal flaws o Potential closures (roundabout most restrictive, conventional least restrictive, thru-about in between)
Private Property Impacts Access – note how alternatives may impact vehicular, bike and pedestrian access o Properties along Powell Lake Road, between County Route 1 & Oatman Highway o Station in the southwest corner of County Route 1 and Powell Lake Road
Environmental and ROW Constraints or Fatal Flaws Funding – alternative concepts must meet minimum benefit/cost ratios Environmental – certain activities include outside agency reviews whose time may not be completed in time … Right-of-Way – acquiring private lands may not be completed in time to use time sensitive funding
Funding … 100% funded with roundabout and possible the thru-about Design & construction Funding. –Design$827,841 –Construction$1,202,439
Schedule & Public Involvement Meeting PIM No. 1 6/3/15 PIM No. 2 7/1/15 Study to 7/10/15 PIM No. 3 Fall, 2015 Scoping (Eng. & Env.) to 2/19/16 Design to 6/10/16 Construction Fall 2016 or Spring 2017