LHCC referee meeting L.Rossi - INFN / Genova CERN - March 19 - 2001 1 Status of insertable pixel  Layout in 2000 (Dubna layout)  Reasons for the change.

Slides:



Advertisements
Similar presentations
Track Trigger Designs for Phase II Ulrich Heintz (Brown University) for U.H., M. Narain (Brown U) M. Johnson, R. Lipton (Fermilab) E. Hazen, S.X. Wu, (Boston.
Advertisements

HFT PXL Mechanical WBS 1.2 March 2010 Howard Wieman LBNL 1.
LHCf: a LHC Detector for Astroparticle Physics LHCf: a LHC Detector for Astroparticle Physics Lorenzo Bonechi on behalf of the LHCf Collaboration * University.
Striplet option of Super Belle Silicon Vertex Detector Talk at Joint Super B factory workshop, Honolulu 20 April 2005 T.Tsuboyama.
Consolidation and Upgrade of the LHC Experimental Vacuum Sectors
Performance of the DZero Layer 0 Detector Marvin Johnson For the DZero Silicon Group.
HFT & PXL geometry F.Videbæk Brookhaven National Laboratory 13/9/12.
ATLAS Pixel Detector July 2003 ETC ‘04 E. Anderssen LBNL BPSS and Service Panels Santa Cruz, CA E Anderssen LBNL.
March 20, 2001M. Garcia-Sciveres - US ATLAS DOE/NSF Review1 M. Garcia-Sciveres LBNL & Module Assembly & Module Assembly WBS Hybrids Hybrids WBS.
Engineering Division 1 Mechanical and Integration CD0 Walkthru, 19-Dec, 2007 Eric Anderssen, LBNL.
Pixel Support Tube Requirements and Interfaces M.Olcese PST CDR: CERN Oct. 17th 2001.
SLHC Pixel Layout Studies S. Dardin, M. Garcia-Sciveres, M. Gilchriese, N. Hartman LBNL November 4, 2008.
18 November 2010 Immanuel Gfall (HEPHY Vienna) SVD Mechanics IDM.
ATLAS Upgrade ID Barrel: Services around ‘outer cylinder’ TJF updated According to the drawing ‘Preparation outer cylinder volume reservation’
HEP GROUP MEETING work on the ATLAS UPGRADE T.J.Fraser.
Ron Madaras, LBL U.S. Pixel Meeting, SCIPP, July 9-10, 2003 Patch Panel 1 (PP1) Brief Review Cost and Effort Estimate.
Saverio Minutoli INFN Genova 1 1 T1 Electronic status Electronics Cards involved: Anode Front End Card Cathode Front End Card Read-Out Control card VFAT.
Aug/16/05 Su DongSiD Vertexing: Snowmass 05 SiD trk+vtx1 SiD VXD Geometry Update Su Dong SLAC.
09/03/2010 ADO-PO section meeting Beam Pipe Extraction/Insertion R. Vuillermet.
U.S. Deliverables Cost and Schedule Summary M. G. D. Gilchriese U.S. ATLAS Review Revised Version November 29, 2000.
1 Jim Thomas - LBL HFT Issues that may Bear on the Fate of the SSD & SVT presented by Jim Thomas 07/07/2006.
Ronald Lipton PMG June Layer 0 Status 48 modules, 96 SVX4 readout chips 6-fold symmetry 8 module types different in sensor and analog cable length.
ATLAS Pixel Detector February 2002 Cooling Services Connections N. Hartman LBNL Cooling Connections Status Report: LBNL Effort February, 2002 N. Hartman,
Santa Cruz Meeting August 12 th 2008 Layout options & Schedule Issues David Lissauer 8/12/2008 1David Lissuaer, Santa Cruz Meeting.
U.S. Deliverables Cost and Schedule Summary M. G. D. Gilchriese Revised Version December 18, 2000.
ATLAS Pixel Detector September 2003 Services E. Anderssen LBNL Service Connectivity from Module to PP1b Eric Anderssen LBNL Pixel Services Meeting, CERN.
B-layer integration with beam-pipe and services ATLAS B-layer upgrade E. Anderssen A. Catinaccio.
M. Gilchriese U.S. Pixel Mechanics Overview M. G. D. Gilchriese Lawrence Berkeley National Laboratory April 2000.
Tevatron II: the world’s highest energy collider What’s new?  Data will be collected from 5 to 15 fb -1 at  s=1.96 TeV  Instantaneous luminosity will.
Tilt angles reloaded, and status of some other things.
1 Outer Barrel, Phase 2 Mech Review 26 Aug 2013, indico: Antti Onnela, CERN Tracker Phase 2 Mechanics Review, 26 August 2013 Status of the Outer.
DOE/NSF Review of U.S. ATLAS /March 2001 WBS Pixel Overview and WBS Pixel Mechanics M. G. D. Gilchriese Lawrence Berkeley Laboratory.
ATLAS 1 Beam Pipe Support Structure (BPSS) Interface and Assembly Final Design Review, April 2003 E. Anderssen, N. Hartman LBNL.
ATLAS 1 Beam Pipe Support Structure (BPSS) Services Interface and Assembly Final Design Review, April 2003 E. Anderssen, N. Hartman, A Smith, LBNL S. Coelli,
End-of-stave region. 2 Space Z-dimension is critical –Keep gap small (might help getting rid of stubs) Edge of last barrel silicon (at corner) is 1277.
Simon Kwan - FermilabCMS Tracker Upgrade Workshop – June 3, Update on the Phase 1 FPIX Half Disk Design Simon Kwan Fermilab on behalf of the USCMS.
Alpine pixel layout Integration progress Teddy Todorov For the ATLAS-LAPP group AUW Integration meeting 20/11/2012.
ATLAS Pixel Detector Pixel Support Tube and Related November 9, 2001 Pixel Day E. Anderssen, LBNL.
J-C Brient-DESY meeting -Jan/ The 2 detector options today …. SiD vs TDR [ * ] [ * ] J.Jaros at ALCPG-SLAC04 ECAL ECAL tungsten-silicon both optionsHCAL.
Local Supports to IDR Discussion ATLAS Upgrade Week November 2014.
TC Straw man for ATLAS ID for SLHC This layout is a result of the discussions in the GENOA ID upgrade workshop. Aim is to evolve this to include list of.
SiD Vertex Detector Mechanical R&D (May Apply to Other Concepts) Bill Cooper Fermilab.
SiD Collaboration Meeting Highlights Tom Markiewicz/SLAC ILC BDS Meeting 08 May 2007.
Andrei Nomerotski, University of Oxford ILC VD Workshop, Menaggio 22 April 2008 SiD Vertex Detector.
M. Gilchriese - September 2000 Pixel Insertable Layouts September 2000.
ATLAS Pixel Detector Pixel Support Tube Interfaces Pixel Support Tube PRR CERN, Geneve E. Anderssen, LBNL.
A2-A5: The drawing has been revised (minor changes), the bid has been approved by INFN management and the invitation letter to the companies will be sent.
SiD MDI Issues Tom Markiewicz/SLAC Beijing ACFA/GDE Meeting 05 February 2007.
Leonardo Rossi INFN Genova - UTOPIA #12 0 What we have learned from UTOPIA so far? Defined a set of gauge histos to compare layouts Exercised on barrel-part.
Comments on Engineering talk by A. Catinaccio at Inner Tracker Engineering Meeting CERN ) Fixed length barrel layout drawing by C. Bault (Strawman.
Brief Status of LHC Experimental Vacuum Project Ray Veness CERN TE/VSC.
Leonardo Rossi – EB 68 – Oct 5, Pixel status and schedule Rad-hard electronics (has always been) on the critical path for the construction of the.
Steinar Stapnes, LHCC June The ATLAS inner detector TRT endcap A+B TRT endcap C TRT barrel SCT barrel SCT endcap Pixels uWhole ID sits inside bore.
USCMS Pixel PMG, Nov 29, Mechanics Status Disks, ½ Service Cylinders Installation USCMS FPIX FNAL PMG Joe Howell Bruno Gobbi Nov. 29, 2006.
DCal-ALICE integration and installation plan and status A. Tauro.
ATLAS 1 Beam Pipe Support SCT TRT Side CSide A Services and Beampipe Support Frame Services and Beampipe Support Frame Pixel Detector Composite support.
ATLAS ID Services Mock Up - Proposal Presented by Ian Wilmut at DESY, update from John Hill 4th May, 20101ATLAS Upgrade - RAL.
EC: 7 DISK concept Preliminary considerations
Straw man layout for ATLAS ID for SLHC
Ferrara MECHANICAL SUPPORT for forward tracking detectors Federico Evangelisti INFN - Ferrara GSI – 2-6 march 2009.
Alpine, very forward, EOS…
- STT LAYOUT - SECTOR F SECTOR A SECTOR B SECTOR E SECTOR D SECTOR C
Introduction Status before the 2009 run Results from the 2009 run
A.Rozanov CPPM Highlights of b-layer upgrade workshop
Additional muon stations for the Upgrade of the Elevator Regions in the ATLAS Muon Spectrometer. Integration issues Denis Diyakov, Alexander Seletskiy,
IHEP group Shashlyk activity towards TDR
Sub-Detector Assembly Area Summary of discussion at ALCW2015
Silvan Steuli Roland Horisberger Stefan König CMS Upgrade Workshop
BCM Overview Placement such that system is sensitive to all types of beam accidents. => 2 independent subsystems Halo losses inside the Pixel volume ie.
Inner DET. Integration Inner detector envelope Radial clearances.
Presentation transcript:

LHCC referee meeting L.Rossi - INFN / Genova CERN - March Status of insertable pixel  Layout in 2000 (Dubna layout)  Reasons for the change (and boundary conditions)  Design of insertable pixel  layout  insertion method  service routing and patch panels  Simulation results  coverage and resolution  material  Road to ECR

LHCC referee meeting L.Rossi - INFN / Genova CERN - March Dubna layout  3 barrel layers (R b = 5cm,R 1 =9.3cm,R 2 =12.7cm ) and 10 disks (6 with 11 sectors and 4 with 9 sectors).  Services at high R, except for b_layer running at R~8cm to allow for independent insertion of b_layer.

LHCC referee meeting L.Rossi - INFN / Genova CERN - March Reasons for change  Rad-hard submissions to DMILL (tested in detail in 2000) revealed unexpected problems for our FE design. After some trials with DMILL, migration to DSM technology was judged necessary. This has generated a schedule delay of at least 15 months and made impossible (or very risky) to install the pixel inside the barrel ID on the SR building (on 4/2004).  Installing pixel separately from ID gives also more freedom in case of production problems (more likely for a novel detector) and allows easier upgrade & repair (all vertex detectors undergo upgrade sooner or later).

LHCC referee meeting L.Rossi - INFN / Genova CERN - March Layout update  Why we did not propose it before?  mechanics more difficult (and a lot of redesign if half-shelled)  more material (services at lower radius, more massive mechanics)  conflicts with SCT (inner bore + alignment)  A solution was found to keep the present design approach (shell and disks) and install pixel in absence of the beam pipe section just outside the barrel, i.e.  break vacuum (as in long shutdown scenario), remove section of b_pipe, and  install pixel during ~2 months (<< long shutdown timescale)  The layout redesign implies some shrinkage after envelope agreement with SCT [smaller radii by ~5mm (R 1 =8.7cm,R 2 =12.2cm) and less and smaller disks (3+3, 8 sectors each)]  less modules to build (2094  1744; i.e. – 17%)  less robust PR at large .  some (~2%) acceptance losses for 3-hit coverage.  Further optimization difficult without loosing one hit  shrunk from outside (SCT bore) and inside (beam pipe) and in-the-middle (requirement of b_layer independently extractable  rails)

LHCC referee meeting L.Rossi - INFN / Genova CERN - March Insertable layout  All services go at low radius up to the barrel end  b_layer services all out on one side  keep independent b_layer insertion/extraction 1400m m  =2  =2.5

LHCC referee meeting L.Rossi - INFN / Genova CERN - March  Barrel design also updated to slightly increase clearance between staves  safer mount/dismount and pigtail routing (clearances~1.5mm (1 for b_layer))  Flex -hybrid module (as opposed to MCMD) adopted also for b_layer

LHCC referee meeting L.Rossi - INFN / Genova CERN - March Design of insertable pixel  A permanent CF tube is installed with ID  this allows to slide in pixel+services sliding in through the beam pipe flange SCT TRT 3450mm 3400mm (end-plug face) PP0 Overlap region Z=[750,1070] PP1 In End-Plug Z=3400 Length of service panel Pixel + Pigtails 795mm (Barrel Tube half length) Pixel Frame is 1400mm long Without pigtails Side CSide A

LHCC referee meeting L.Rossi - INFN / Genova CERN - March  The insertion process is done when the Forward Calorimeter is retracted and the relative beam pipe section is out.  First the far services and the pixel frame are inserted Far Services Pixel Frame Beam pipe support Inner Detector Bore Beam pipe Far Services in Quadrants 2.65m Services need to extend beyond end of Beam pipe support frame to allow termination of overlapping pigtails Z=3450 (this bears some investigation) 500mm (comfortable Human-width) 2270mm To end of Pigtails

LHCC referee meeting L.Rossi - INFN / Genova CERN - March  Far services terminated, pixel detector inserted Far Services Terminate Far Services 2270mm To end of Pigtails for Cantilevered support 2770mm Over mechanical support Z=3450 Far side barrel pigtails need to fold back over frame to give access to PP0 Z=6220mm Z=5720 Cantilever structure necessary to support beampipe during installation— same as for ID forward installation

LHCC referee meeting L.Rossi - INFN / Genova CERN - March  Then the near services are connected and slided in Far Services Near Services 3400 (end of support tube) Support wire at 3450 re-attached Frame end just inside tube (Frame end to PP0 gap is 50mm) (2.65m + 50mm) 2.7m 6.1m Far Services Termination to B-Layer services occurs inbound of Support wire

LHCC referee meeting L.Rossi - INFN / Genova CERN - March  Assembly order require connections at different locations (PP0 and PP1) but simplifies PP2 Pigtail PP1 “Type I” 2.7m “Type II” 3.2m to PPB2 PPB1 Pixel Volume Patch PPF1 To PP3 PP0 Location PPB2 No Longer Used Voltage drop on low mass cables becomes more challenging. Timed well with DSM change (everything changes)

LHCC referee meeting L.Rossi - INFN / Genova CERN - March  The b_layer must be clam-shelled as it does not pass through the beam pipe flange without opening.  the b_layer can (in principle) be inserted without breaking the vacuum. Far Services 1.2m Far Services TOP View Vertical Support Halves are inserted around wire--required tooling is not shown Halves are closed and fixed together B-layer is inserted into Pixel Frame using same rails in pixels as for baseline

LHCC referee meeting L.Rossi - INFN / Genova CERN - March  Cartoon of b_layer insertion Preliminary design of tooling structures is consistent with space available now. Length of 1.2m required Halves are held together by longitudinal actuation

LHCC referee meeting L.Rossi - INFN / Genova CERN - March  Finish of b_layer installation Far Services To terminate the services to the B-layer, and the rest of the detector, the detector must be withdrawn to gain access B-layer services are terminated first as they will be obscured by the rest of the pixel services The B-Layer is then pushed into the frame into its final position. Depending on the length of the Pigtails on the B-layer, this step may be avoided B-layer Services

LHCC referee meeting L.Rossi - INFN / Genova CERN - March A 6A 8A 2A 4A 1A 5A 3A 6C 7C 5C 3C 1C 4C 8C 2C 4CBL 2CBL 3CBL 1 1CBL Needs update for new stave count (90) Services routing (octants)

LHCC referee meeting L.Rossi - INFN / Genova CERN - March PP0   Radius of PP0 is approximately 180mm   Starts at Z=750 and goes to Z=1070 (50mm gap between PP0 and Frame) Z_400.7 Z_ R_190 R_90 100mm 205mm 260mm 50mm 120mm Z_ mm 50mm 30mm 160mm Bi-Stave Assy 6X7X 370mm End of Pixels+Pigtails Z_1070 End of Pixel Frame

LHCC referee meeting L.Rossi - INFN / Genova CERN - March Rail system on support tube Vee and Flat rails were chosen to provide pseudo-kinematic support for the detector during delivery to the support points Rails are used only for delivery, not support

LHCC referee meeting L.Rossi - INFN / Genova CERN - March Support tube mock-up   Sufficient space acquired in old Bevatron Generator Room   Enough space to simulate entire assembly sequence   Mockup in three pieces to simulate independent parts of tube   Goal is for full length of entire tube to simulate all installation scenarios   Detector rails are removable, should modification be necessary

LHCC referee meeting L.Rossi - INFN / Genova CERN - March Scope of tube mock-up  Mass and Envelope Geometry of final detector Frame  Attempting for similar friction as well  At least two full quadrants of “dummy” service panels  Initially 1-quadrant, both sides, eventually half of all services  At least two octants (both sides) of mechanically accurate connection  Needed for installation simulation  At least one octant of electrically active service connections  This is to provide verification that terminations stay terminated through procedure  Might prove useful for thermal mockup  Provision for Dummy B-Layer installation  Requires also mechanical connections for installation simulation Expected to be ready (tube + services) by end of March

LHCC referee meeting L.Rossi - INFN / Genova CERN - March Simulation results  Coverage  first disk cannot come too close to barrel end (service routing) Barrel-to-disk two hit hole Assume all tracks coming from (0.0.0)

LHCC referee meeting L.Rossi - INFN / Genova CERN - March  Geometric hit losses (not including electronics , dead channels) Vertex smearing included

LHCC referee meeting L.Rossi - INFN / Genova CERN - March GeV   Resolution does not change appreciably  e.g. in b_layer

LHCC referee meeting L.Rossi - INFN / Genova CERN - March GeV   Transverse impact parameter slightly improves  MCMD --> flex (51.5 to 50  m pixel size), smaller radii of layers 1&2 and larger stave tilt angle  Longitudinal i.p. worsens at high   less disks and algorithm not yet tuned for long clusters in b_layer

LHCC referee meeting L.Rossi - INFN / Genova CERN - March GeV   No change of i.p. resolution vs Dubna layout, sensible change vs physics TDR layout mostly due to increase of the b_layer radius (4 -> 5cm)  beam pipe X 0 (1mm Be -->1.6mm Be) and radius (24 -->38mm) increase not yet included in simulation (new beam pipe not yet released).

LHCC referee meeting L.Rossi - INFN / Genova CERN - March Material  increase mostly due to support tube + services at low radius  mean increase up to  ~2 is ~0.6%X 0

LHCC referee meeting L.Rossi - INFN / Genova CERN - March Material with less layers  We will likely start-up with 2 layers

LHCC referee meeting L.Rossi - INFN / Genova CERN - March Low-energy tails in EM calorimeter spectra   Study of effects on EMC and on b_tagging just started Tails  event fraction with E rec < 0.92 E true Layout Tails  =0.3 Tails  =2.4 Physics TDR 9.5  0.6% 3.6  0.6% Insertable 11.3  0.7% 9.6  0.9% Vertex spread included Events over full  and  =0.025 (1 cell) Electrons E T =10 GeV  = 2.4 Normalised to same number of events

LHCC referee meeting L.Rossi - INFN / Genova CERN - March Steps to ECR  On design/mock-up  April: put together mock-up support tube and dummy services  June 18: Comprehensive Design Review of global supports + insertion tube  June-Aug: electrically active tests and thermal simulation of mock-up  October: mechanical testing of assembly procedure  On simulation  compare reconstruction efficiency and b_tagging with TDR  study effect of material increase on tracking and EM calorimetry (and reduce material whenever possible).  Time-scale for ECR: Summer 01.