RLSR 16/4/2015 UK Financial Plan & Risks. Content Finances – Cost to Completion Risks – Top level to completion – R9 working space – Summary 2 RLSR 24/11/2014.

Slides:



Advertisements
Similar presentations
1 UK Project Alan Grant, STFC. Finance How savings are made Update on stepIV position Milestones Critical Path - stepIV Concerns 2.
Advertisements

January 6. January 7 January 8 January 9 January 10.
Project Managers Update Roy Preece Particle Physics Department, STFC MICE Video Conference, 18 th September 2014.
Project Update for the Muon Ionization Cooling Experiment (RAL) Mark Palmer Fermilab December 15, 2014.
1 MICE PM Report General Update –Phase I civil engineering –R5.2 in June –Phase II design work –Phase II hardware –A few questions –Schedule, milestones.
March 2003 Paul Drumm MICE Collaboration Meeting, CERN 1 Beam Line & Installation Plans Paul Drumm CLRC Rutherford Appleton Laboratory.
Accelerator Systems Division FACET Project Management John Seeman for the FACET Study Group PPA Directorate Stanford Linear Accelerator Center DOE FACET.
11/26/2002Edgar L Black IIT MICE Video Conference November 27, 2002 Summary of safety implementation for proposal.
1 MICE PM Report Installations to date Future installation work Preparations for Phase Two Target status MICE Video Conference, 22nd May, 2008.
Electrical Installation CM39 Andy Gallagher & Ian Mullacrane.
Project Managers Report Video Conference 172 Roy Preece 11 th December 2014.
Linac Front-End R&D --- Systems Integration and Meson Lab Setup
Alan Grant OsC 30/4/ UK Project Finance & Schedule.
1 MICE - INFRASTRUCTURE MICO meeting 7 th February 2008 Tim Hayler.
UKNF/MICE PSAG, 3/5/11 Spectrometer solenoids: –Repair plan still ‘in approval’, already two months late –Workshop/mini review at LBNL 10 th /11 th May.
1 UK PM Report Costs & Schedule Alan Grant, STFC.
U.S. MICE Schedule, Cost, & Risks Peter H. Garbincius Mark Palmer, Alan Bross, Rich Krull Fermilab Presented at RAL – November 13, 2013.
RSLR mtg 28/3/2014 RLSR mtg Alan Grant. 2 RLSR mtg 28/3/ MICE Finances - Forward Look.
The status of the construction of MICE Step IV K. Long, on behalf of the MICE collaboration.
Executive Board Meeting Roy Preece 23rd May 2014
Electrical Integration CM38 Steve Griffiths & Ian Mullacrane.
Schedule and Work We are moving into a very intensive 4 months with a lot of work to be carried out Electrical services to the devices – after the South.
Magnetic Mitigation - Contents l Magnetic Mitigation General l West Wall Compressors l Rack Room 2 l Magnetic Shielding Yoke Jason Tarrant – Integration.
Andrew Moss ASTeC CM32 9t h February 2012 RAL MICE RF System.
Status of the MICE Project & Dashboard MICE Project Board 14 th November 2013 Roy Preece.
MICE Status & Plans MICE-UK paul drumm 15 th September 2004.
Report from MICE project teams Feedback from PPRP MICE funding: various scenarios Issues  Financial year 2003/04  iMICE common fund.
Project Managers Report CM40 Collaboration Board – Rome Roy Preece 28 th October 2014.
UK Update Package Managers Meeting 001 Roy Preece 13 th January 2014.
MICE Oversight Committee Meeting RAL, 24 April 2014 Paul Soler on behalf of the MICE Collaboration Status of MICE and Spectrometer Solenoids.
Paul Drumm, cm10, 27 Oct 2004 MICE Project Report Paul Drumm Collaboration Meeting 10 Rutherford Appleton Laboratory October 2004.
Christopher M. Quinn, MACC, CPA, CFE, CGFO, CGMA Finance Director Lina Williams Budget & Financial Analyst Tuesday, July 14 th 2015.
SunSatFriThursWedTuesMon January
OsC mtg 24/4/2014 OsC mtg Alan Grant. 2 OsC mtg 24/4/ MICE Finances - Forward Look.
1 UK PM Report Costs & Schedule Alan Grant, STFC.
MICE CM20 Alain Blondel 10 February The International Muon Ionization Cooling Experiment MICE CM20 Spokesmouse remarks.
Iouri Ivaniouchenkov RAL Specifying the needs for MICE July 8, RAL MICE Collaboration Meeting 1.
Status of the MICE Construction Project Resource Loaded Schedule Review 29 th April 2014 Roy Preece.
OsC mtg 15/10/2014 MICE Step IV Alan Grant. Content Step IV – Construction Status – Finances – Schedule – Risks – Summary 2.
Finance Roy Preece STFC RAL Oversight Committee Meeting 27 th November 2015.
MICE – UK Plan Roy Preece STFC RAL DOE Review of MAP Brookhaven National Laboratory 13 th August 2014.
1 UK Project Roy Preece – STFC Alan Grant, STFC. Finance Staffing Update on stepIV position Milestones Critical Path – stepIV Magnetic field mitigation.
Tuesday 9 th January Project Status Report Project Achievements Project Schedule Issues Finance Summary Risk Register Photos.
RLSR 16/4/2015 UK Financial Plan & Risks. Content Finances – FY 2014/15 – Cost to Completion Risks – Top level to completion – R9 working space – Summary.
PSAG mtg 20/03/2015 Finance Alan Grant. 2 PSAG mtg 20/03/2015 Finance Update FY14/15 – February Figures Additional capital funding in January of £63K.
UK Project Plan (Finance & Risk) Alan Grant STFC DL RLSR 5 th April 2016.
The MAP 3-Year Plan Mark Palmer Fermilab September 26, 2014.
US Construction Project: SSs, PRY, Cavities and test program 1.
Schedule to completion, Risk and Critical Interfaces Roy Preece STFC RAL RLSR 16 th April 2015.
Schedule and Milestones Roy Preece STFC RAL FAC 17 th April 2015.
1 UK Project Finance & Schedule. Overview Finance  Budget Setting 2013/14  June Finance  Forward look to complete stepVI Schedule  Overview 2.
EuCARD-2 is co-funded by the partners and the European Commission under Capacities 7th Framework Programme, Grant Agreement Ionisation Cooling Test.
Schedule and Milestones Colin Whyte STFC RAL Resource Loaded Schedule Review 5 th April 2016.
US Project Plan for MICE Peter H. Garbincius, Mark Palmer, Alan Bross, Rich Krull Fermilab April 16, 2015.
UK Project Plan Roy Preece STFC RAL RLSR 26 th October 2015.
Project Managers Report CM38 – Napa Roy Preece 24th February 2014.
Step IV Step IV extended through 2016 QP/QD – in progress at FNAL Target dates SSU ECE for Feb now only 20% probability – no-field Feb Remainder for April/March.
Reported by Ron Prwivo for Ian Robson. Overview Response to Recommendations from the RLSR of November 2014 – very good, RF staffing remains an issue Very.
Muon Ionisation Cooling Experiment Overview
Resource Loaded Schedule and Budget Profile
CBETA Technical Review
Status of the MICE Construction Project
UK Financial Plan & Risks
MICE CM31 Schedule summary
MICE Project in the US: Completion of Efforts
Renovation of the 45-year old PS magnets
Introduction Jason Tarrant – Integration Engineering Step IV Removal
East Hall under construction
Experimental equipment Edgar L. Black February 17, 2019
SNS-PPU upgrades the existing accelerator structure
Presentation transcript:

RLSR 16/4/2015 UK Financial Plan & Risks

Content Finances – Cost to Completion Risks – Top level to completion – R9 working space – Summary 2 RLSR 24/11/2014

Finance 3 RLSR 24/11/2014

Final Step UK Cost to completion Construction complete – March 2017 Commissioning complete – May 2017 Data taking complete – March 2018 Analysis and paper submissions timescales and associated resource costs TBA beyond 2016 Includes 3FTE of ISIS support staff each FY + MICE staff contributing to ISIS teams (T Stanley, M Tucker, J Govans) Additional maintenance/service costs in 2016/17 in O&A wp Ramping down of staff and non staff costs FY2017/18 Mitigation costs predominantly  Additional Helium costs for magnet training runs  Additional shielding  RF crowbar switch & spares  Electrical spares for system failures 4

Final Step UK Cost to completion 5  Allocation approved to FY 15/16  Required allocation for phase 3 - FY 16/17, & 17/18 £5,979k  Total UK spend for MICE £40,728k RLSR 24/11/2014

Risk Final Step 6 RLSR 24/11/2014

7 RLSR 16/4/2015 Top Level Risks

8 RLSR 16/4/2015 Top Level Risks

Working Space 9 Additional Experimental area ~170m 2 Current R9 experimental area ~200m 2 Moving out of this area

Working Space 10 Activity in the R9 Laboratory space Area for storage of essential equipment moved from the current Didcot storage facility - £20k/year  To end of project Clean lab  To end of project Target operational space  To end of project Waveguide layout and assembly  6 months during 2015/16 Storage of magnets and Partial Return Yoke materials during de-commissioning of Step IV (North sections)  Removal - June 2016  Installation - January 2017 Receiving area for RF cavities and chambers  Delivery June 2016  Installation June/Sept 2016 – for off line testing with RF Receiving area for Final Step additional Partial Return Yoke sections  Delivery April 2016  Installation November 2016 – February 2017 Forklift parking area  To end of project RLSR 16/4/2014

Risk Summary 11 No Second hydrogen system No Hydrogen absorber in final step Operational risk reduced from Step IV experience. Both Focus Coils performance sufficient for ionisation demonstration Additional space in R9 agreed ……….. work is progressing RF Power systems  Effort for build-up, testing and installation Longer commissioning times Changes in US budgets  Delivery of RF Cavities and Chambers late  PRY additional materials late RLSR 16/4/2014