Booster LV Electrical Distribution: Schedule and Quantities Aims: Modernisation of Booster electrical infrastucture To install necessary infrastructure.

Slides:



Advertisements
Similar presentations
Cisco 6500 E-Series Chassis Up-grade
Advertisements

Study report on the TDC2/TCC2 Cabling and Low Voltage activities Ivan Moya Martinez– EN/EL/CF – WP 31st Meeting
Long shutdown 2013: Electrical distribution activities 09/03/2012 IEFC 2012 Workshop F. Duval on Behalf of EN/EL group.
Nelson Hydro Downtown Conversion July 26, 2010 Project Overview.
DAQ&CM Infrastructure Paul Drumm. Issue Space is running out! Power supplies, RF system –Big kit, legislation dictates space requirements (not a clear.
RD51 Common Test Beam: Status RD51 collaboration week Kolymbari, June 2009 Yorgos Tsipolitis NTUA.
Gas systems for GIF++ 14/02/2015 Ernesto Regaño 1.
Fibres & copper Cabling activities LIU meeting 27/09/2013 F Duval 27/09/2013 F Duval Cabling acxtivities LIU 1.
EMMA Electrical Engineering July 06 EE & PS Group EE & PS Group – EMMA 06
The HiLumi LHC Design Study is included in the High Luminosity LHC project and is partly funded by the European Commission within the Framework Programme.
CV activities on LHC complex during the long shutdown Serge Deleval Thanks to M. Nonis, Y. Body, G. Peon, S. Moccia, M. Obrecht Chamonix 2011.
Machine Advisory Committee Review APS Upgrade Installation Plan and Schedule John Noonan November 15, 2006.
Status of handling studies for PSB-LIU Caterina Bertone EN-HE LIU-PSB 17/09/2015 Courtesy: A. Newborough EDMS
Site Construction & Installation Services
Active Safety Systems + EHN1: Draft EN/EL proposal for replacement of Nano PLC 1.Current situation 2.Requirements definition 3.Current solutions (Atlas/CMS)
LS1 : EL Upgrades & Consolidation Chamonix– February 8 th 2012 F. Duval on behalf of EN/EL The goal of LS1 is to implement everything needed for a safe.
Progress Completed Order/Fabricate SS Piping for HBD Purge gas from all detectors DAQ tests Prep. for Shutdown work (open doors, move carriages, etc. Pave.
Consolidation and Upgrade of the SPS Electrical Networks Current Status JP. Sferruzza, on behalf of EN/EL.
1 MICE Hall and Infrastructure - Progress since CM18 Chris Nelson MICE CM19 Oct 2007.
Power Plant Construction and QA/QC Section 4.4 – In-Plant Electrical Distribution Engineering Technology Division.
Injectors & LHC report K. Foraz on behalf of OSS members 14/06/2013LSC - K. Foraz1.
EN-CV interventions during YETS
Services in GIF++ A pictorial record of the work HV Cables LV cables DCS cables Signal Cables Ian Crotty 17 Dec 2014.
On behalf on EN-EL October 1 st, 2015 YETS Works EN-EL [ CF excluded ]
1 TT10 Remedial works What is happening. 2 Compression failure in crown (some cases) Tension/Shear failure in shoulders (typical) Compression Tension.
Consolidation needs for the Electrical Distribution, Control Cables and Optical Fibres Equipment F. Duval.
MTA Installation Meeting February 21, 2007 Agenda 1)Progress report (Fernanda+Carol) 2)Floor Plan layout (Fernanda+Larry) 3)AOB Key Red – critical Orange.
Vault Reconfiguration IT DMM January 23 rd 2002 Tony Cass —
EN-EL Activities for LS2 LIU, Consolidation, Maintenance, Operation Nicolas Bellegarde on behalf of EN-EL.
EHN1 – EN/EL Progress update J. Devine G. Gross 11/02/16.
Each converter 3 racks (fighting for 2?) Access from front and rear of each rack! 56 racks total + 6 racks Ethernet/control Existing RF equipment to be.
MICE Project Progress Update Power Converters Rack housing MQ1 to MQ3 magnet power converters –Marshalling for all other quadrupole & dipole units –Houses.
A new RF system for the PSB. LIU-PSB Working Group Meeting, 10th December 2015 M. Paoluzzi December 10 th Wide working group involved including.
September 30, 2008 Jim Van Dyke, Web:
Uninterruptible Power Supply Improves Reliability at The Australian Synchrotron Sean Murphy – ARW 2013 Melbourne.
Interventions on electrical distribution and racks’ infrastructure still to be done during LS1 and their impact W.Iwanski.
August 2007Andrea Gaddi, CERN Physics Dept. Detectors Infrastructures & Services Baseline to design detectors infrastructures. Tentative arrangement of.
Electrical Group Inputs for LIU-Ions J. Devine, on behalf of EN/EL.
Main MPE Activities during YETS/EYETS/LS2 and the Provision of Resources Andrzej Siemko Andrzej Siemko TE-MPE1.
YETS & LS2 Works EN-EL / Power distribution
Update on the Critical Path of the PS Booster Schedule for the EYETS
EYETS Works EN-EL [ FC excluded ]
Schedule CM SPS G.Vandoni.
YETS & LS2 Works EN-El on LHC / Power distribution
Identification of the unused cables
TE-MSC activities in SPS during LS2
EYETS David Hay EN-OSS.
BA6 – crab cavity activities in EYETS
Injector De-cabling Project
LIU–PLI report LIU PSB meeting.
EYETS16-17 ACTIVITIES EN-EL-CF
YETS & LS2 Reminder G. Girardot 20 juin 2017.
De-cabling strategy during YETS
LV Safe Powering from UPS to Clients
TE/EPC activities for YETS & LS2 LINAC 2-3, PSB, PS & TT2
TE/EPC activities for LINAC 2, PSB, PS & TT2 during EYETS
EN-HE SPS works during EYETS
PSB/PS/TT2/Linac2-3 YETS 2017–2018 & LS2 preparation meeting
SPS EN-CV Planning LS (initial draft)
SPS Planning for the EYETS Meeting 8 (07/12/2016)
SPS Planning for the EYETS Meeting 9 (14/12/2016)
SPS activities during LS2 TE-EPC (Power Converter Group)
Summary of ECRs for the YETS Booster, PS, ISOLDE and associated transfer lines (LIU + Consolidation) T. Birtwistle (EN-MEF-DC)
EN-CV interventions during EYETS for PS and PSB
YETS & LS2 Works EN-EL / Power distribution
Extension SR1 WP3 Electrical installations
TE-MSC activities in SPS during YETS
PS Booster Report from: David HAY, Cyrille BEDEL 12-Jan-2018
Experimental Areas – LS2 planning
Linac4 Connection Broken Line 07/08/19
Presentation transcript:

Booster LV Electrical Distribution: Schedule and Quantities Aims: Modernisation of Booster electrical infrastucture To install necessary infrastructure for transparent change-over of cabling Minimise impact on other work planned for the Booster (esp. cable removal campaign) Remove power cabling from false floor for easier installation + operation Phasing: Phase 1 – New containment installation + Switchboards - YETS 2015 Phase 2 – Cable & Busbar installation - >YETS 2015 (During run) Phase 3 – Change over - EYETS 2016? TBA with users Phase 4 – Cable removal – following change over, EYETS? Quantities for removal: 33 Cables to be removed (identified so far, however final number will be >> as no cablotheque exists for the majority) >1.6KM total cable length to be removed (identified so far) Quantities for installation: BRF2 new rack zone – Additional ~100m containment to install, notional duration 2 weeks Refurbishment BCER zone – Additional ~400m containment to install, notional duration 3 weeks Additional holes to be drilled for replacement of electrical supplies to distribution switchboards

Booster: LV Electrical Distribution Overview Power Converters RF General Services ESD Machine Racks General Services CV General Services Bat. 245 POPS-B Final circuit distribution within Bldg. 361 to be consolidated

Booster LV Electrical Distribution: Before & After inside Bldg. 361 Racks Structural Slab Existing service zone – Old cables + Power distribution No Access Before Racks Structural Slab Service zone dedicated for Control, DC cables and pipework After Electrical containment zone Racks supplies from above

Booster LV Electrical Distribution: Photos Front Typical configuration: New Fluorescent Lighting 2x300mm Cable trays (EL+CF) 1x100A Canalis Structure supported on racks (allowing for individual rack removal) or ceiling, to be determined. Similar systems used in Linac4 and CCC. Zone for EL installation False floor available for Control + DC cables