1 De-cabling strategy during YETS 2017-2018
PSB/PS/TT2/Linac2-3 YETS 2017–2018 & LS2 preparation meetings Thursday, 28st September 2017 Gérard CUMER on behalf project team

2 Injectors de-cabling Project De-cabling Project : status August 2017
Master Schedule, Dashboard Decabling interventions during YETS (PS Center Ring) Identification campaign TT2 during YETS 17-18 PSB/PS/TT2/Linac2-3 YETS 17–18 & LS2 - Gerard Cumer & Lucia Maricalva - 28th September 2017

3 De-cabling project : Master schedule (August 2017)
PSB/PS/TT2/Linac2-3 YETS 17–18 & LS2 - Gerard Cumer & Lucia Maricalva - 28th September 2017

4 Dashboard (August 2017) PSB/PS/TT2/Linac2-3 YETS 17–18 & LS2 - Gerard Cumer & Lucia Maricalva - 28th September 2017

5 Injectors de-cabling Project De-cabling Project : status August 2017
Master Schedule, Dashboard Decabling interventions during YETS ( PS Center Ring ) Identification campaign TT2 during YETS 17-18 PSB/PS/TT2/Linac2-3 YETS 17–18 & LS2 - Gerard Cumer & Lucia Maricalva - 28th September 2017

6 De-cabling interventions during YETS 17-18 (PS Center Ring)
PSB/PS/TT2/Linac2-3 YETS 17–18 & LS2 - Gerard Cumer & Lucia Maricalva - 28th September 2017

7 PS False Floor consolidation
Buildings –367: no stability issues due to false floor  requested consolidation due to and accident on 18th May 2017 (A2_ EDMS ). This works are not required for the de-cabling project of PSCR and SMB can carry them out independently. Building 368: False floor will be reinforced with the same tripod type already installed in PSB in order to assure a permanent stability. PSB/PS/TT2/Linac2-3 YETS 17–18 & LS2 - Gerard Cumer & Lucia Maricalva - 28th September 2017

8 Works classification and Responsible Unit
The works for the removal of obsolete cables have been classified as electrical nature in application of the Norm NF (EDMS Memorandum: ) Complying with GSI-WS-1, EN-EL is the responsible unit for: All the VIC’s must be organized by EN-EL The necessary lock outs for this works must be requested by EN-EL The removal of the obsolete cables will be carried out by the COMSA company from EN-EL, with electrician professionals authorised H1-B1 + a work supervisor certified H2-B2 PSB/PS/TT2/Linac2-3 YETS 17–18 & LS2 - Gerard Cumer & Lucia Maricalva - 28th September 2017

9 Lock-out organization
The Project Team has proposed and approved the equipment that necessarily needs to be kept powered in order to assure the safety of workers The works for the cable removal require: The Lock-out Standard and systematic of PS (EPC-ABT) The supplementary and specific lock-out (racks, power RF, Tablx BT, UPS…) The temporary power supply for the basic needs (vide, star-points…) The works for the cables’ removal are framed by 2 VICs, one at the beginning and one at the end of the work. Signatures and formal exchanges of forms for lock-out certificates (first or second stage) during the VICs. The group leaders (owners of each installation/equipment), previously notified through the Memorandum EDMS , are named lock-out responsible for their equipment. PSB/PS/TT2/Linac2-3 YETS 17–18 & LS2 - Gerard Cumer & Lucia Maricalva - 28th September 2017

10 Organization of the project & Safety
Project Group Link Person and Lock out responsible Updating process from the groups in progress PSB/PS/TT2/Linac2-3 YETS 17–18 & LS2 - Gerard Cumer & Lucia Maricalva - 28th September 2017

11 De-cabling during YETS 17-18 (PS Center Ring)
Duration Planning 3 days for Lockout and False floor consolidation (20,21 & 22/12/2017) Surface + galleries (without Ovoid 8) 30 working days needed Ovoid 8 (in parallel with surface): working days needed Pulling 30 cables LIU: 5 working days needed (intervention period TBD) Specific lock-out for decabling project from 20/01  15/02 First Draft The calculations are based on the gained experience in PSB (works in 2 shifts). PSB/PS/TT2/Linac2-3 YETS 17–18 & LS2 - Gerard Cumer & Lucia Maricalva - 28th September 2017

12 De-cabling during YETS 17-18 (PS Center Ring)
Test Génératrice PS PSB/PS/TT2/Linac2-3 YETS 17–18 & LS2 - Gerard Cumer & Lucia Maricalva - 28th September 2017

13 Injectors de-cabling Project De-cabling Project : status August 2017
Master Schedule, Dashboard Decabling interventions during YETS ( PS Center Ring ) Identification campaign TT2 during YETS 17-18 PSB/PS/TT2/Linac2-3 YETS 17–18 & LS2 - Gerard Cumer & Lucia Maricalva - 28th September 2017

14 Organization of the project & Safety
Procédure identification câbles obsolètes Similar procedure draft for the TT2 PSB/PS/TT2/Linac2-3 YETS 17–18 & LS2 - Gerard Cumer & Lucia Maricalva - 28th September 2017

15 Identification process TT2
YETS GROUPES + EL + ACE : Recherches, identifications sur site Déconnections, repérages violet tests Renseignements dans SharePoint EN/ACE Réaffectation de câbles entre les groupes Réaffectation de câbles dans autres Zones du PS autres zones du PS TT2 (EN/ACE) Stockage des fichiers dans SharePoint Futures campagnes de dé-câblages CES (en service) Importation des câbles en service dans la BD GESMAR DOV (à déposer) Déposés pendant ce YETS DEC’s Autres câbles trouvés coupés ou déconnectés avec ou sans numéro PT (pas trouvés – déjà déposés dans le passé depuis 1960… ) 2017 Cablothèque GESMAR Papier V1 Papier V2 Cablothèques numérisées en Excel importées Cablothèques après 1989 sous format Excel – DEC avant 1989 macro Analyse par les Groupes MASTER FILE sous Share-point Identification, repérages, déconnexions Renseignements BD par les groupes Identification process TT2 Transmis aux groupes Analyse en cours PSB/PS/TT2/Linac2-3 YETS 17–18 & LS2 - Gerard Cumer & Lucia Maricalva - 28th September 2017

16 TT2 & Building 269Y PSB/PS/TT2/Linac2-3 YETS 17–18 & LS2 - Gerard Cumer & Lucia Maricalva - 28th September 2017

17 Summary Procedures and methodologies are similar to the previously applied during EYETS 16-17 De-cabling works at the PS Centre Ring is not linked to the false floor consolidation (contrary to PSB) Standard Lock-out for the PS machine and supplementary lock-outs required for de-cabling works: lock-out responsible (chargé de consignation) for the 14 groups involved. Decabling works at PS Centre Ring are classified ALARA 1 Building 359: Identified coactivity with maintenance works (TE-ABT and EN-CV) and false floor consolidation works (SMB) The TT2 identification campaign will entail cable investigation out of TT2 and Building 269 such as AD, nTOF and SPS. The cable analysis from the cablotheque has already started PSB/PS/TT2/Linac2-3 YETS 17–18 & LS2 - Gerard Cumer & Lucia Maricalva - 28th September 2017

18 …..Questions? Thanks for your attention
PSB/PS/TT2/Linac2-3 YETS 17–18 & LS2 - Gerard Cumer & Lucia Maricalva - 28th September 2017