LHC Insertions Upgrade Working Group (LIUWG) 20-03-2008 Space available in tunnel Y. Muttoni.

Slides:



Advertisements
Similar presentations
The HiLumi LHC Design Study (a sub-system of HL-LHC) is co-funded by the European Commission within the Framework Programme 7 Capacities Specific Programme,
Advertisements

Electrical wiring for piezo movers piezo power supply strain gauges readout temperature probes 1 Frédéric BOGARD – LAL/IN2P3/CNRS – Jan 25, 2013 Electrical.
19th – 20th of September 2007Cryogenic Expert Meeting at GSI, Jan Patrick Meier1/11 Cryogenic Experts Meeting at GSI, 2007 The SIS 100 Cryogenic Jumper.
A. Ballarino, 21/11/2014 Wrap up from WP6 A. Ballarino for the WP6 CERN, Geneva KEK, 21 st November th Hi-Lumi LHC Extended Steering Committee.
Cold Powering of the HL-LHC magnet system WP6 Motivation Work Package description Tasks Partners & resources Amalia Ballarino HL-LHC Design Study – 3 rd.
MODULE TRANSPORT CLIC Module Working Group 27 September 2010 Keith Kershaw CERN EN-HE.
MICE: Hall Infrastructure Chris Nelson CEng CM16 8 th Oct 2006.
13 March MERcury Intense Target (MERIT) Experiment Layout A.Fabich for CERN AB-ATB.
Crab Cavities in IR1 and IR5 Some considerations on tunnel integration What will be the situation in the tunnel after the LHC IR Phase-1 Upgrade. What.
HLTC 15 th April 2014 EDMS: Y. Muttoni EN-MEF-INT with the contribution of P. Fessia.
1 Presented at ColUSM by D. Ramos on behalf of the Cold Collimator Feasibility Study Working Group Longitudinal.
The HiLumi LHC Design Study (a sub-system of HL-LHC) is co-funded by the European Commission within the Framework Programme 7 Capacities Specific Programme,
Prospects of SC Quadrupole Production at IHEP-Protvino The 2nd Institutes Meeting on International Construction of the FAIR Accelerator Complex Protvino,
First Considerations on CLIC Cooling System Ch. Martel, J. Inigo-Golfin TS/CV.
June 2004 Andrea Gaddi, PH-CMI USC Installation Commissioning Task Force 1st Run Meeting, June 3rd, 2004.
The HiLumi LHC Design Study (a sub-system of HL-LHC) is co-funded by the European Commission within the Framework Programme 7 Capacities Specific Programme,
FP 420 Connection Cryostat Design and Integration Keith Potter, Jaak Lippmaa, Guido Ryckwaert, Benoit Florin, Thierry Renaglia, Thierry Colombet, Shrikant.
Magnetic Shielding Issues Roy Preece STFC - RAL. Overview Issues Items in harms way – Step IV Step IV mitigation plan –Racks –Compressors Current / Future.
David Nisbet – LIUWG 17 th July 2008 LIUWG – Options for Powering Phase I David Nisbet Summary of points from LIUWG 7 Existing topology Future topology.
The HiLumi LHC Design Study is included in the High Luminosity LHC project and is partly funded by the European Commission within the Framework Programme.
Workshop Chamonix XIV Shortcuts during installation and commissioning: risk and benefit H. Gruehagen, G. Riddone on behalf of the AT/ACR group 18 January.
July LEReC Review July 2014 Low Energy RHIC electron Cooling Al Pendzick LEReC Civil Construction.
The HiLumi LHC Design Study is included in the High Luminosity LHC project and is partly funded by the European Commission within the Framework Programme.
LIU – TCDI. INTEGRATION STATUS 1 ST APRIL 2015 Frédéric Galleazzi EN/MEF/INT Antoine Kosmicki EN/MEF/INT EDMS :
Big Magnet Design II: a) solenoid and cable concept b) short section test V.V. Kashikhin and A.V. Zlobin.
08/31/07Shutdown’07 Week 4 F.G. Garcia1 MTA beam line installation Weekly Report August 31, 2007 Period covered: August 24 th to August 31 st (Week 4)
1st LTEX 22 June 2009D.LACARRERE1 Protection of UX85 EDMS No IP8 Current Status & Plans  UX85 Expt Area  RB84 (8-7 sector)  RB86 (8-1 sector)
Experimental Sectors Ray Veness / AT-VAC With many thanks to G.Foffano + W.Cameron TS/MME Patrick Lepeule / AT-VAC.
EPPOG - LHC Machine LHC machine (and some outreach) Mike Lamont.
K. Foraz & Perrot A. L., EN/MEF - R2E Project LMC 25th May 2011 Thanks to EN/EL, EN/HE, EN/MEF, equipment owners the LHC integration team & the R2E team.
S. Claudet - 31st May 2007Power refrigeration for LHC Power refrigeration at 4.5K & 1.8K for the LHC S. Claudet, CERN AT-ACR.
AT-MEI-PE, RD, LIUWG 31-JUL R. Denz AT-MEI-PE LHC Luminosity Upgrade Protection of the Inner Triplet, D1, Correctors and Superconducting Links/Leads.
Activities related to Experiments during TS3 and YETS th November, 2015 M. Bernardini, M. Barberan With the support of S. Chemli and Experiments.
The HiLumi LHC Design Study (a sub-system of HL-LHC) is co-funded by the European Commission within the Framework Programme 7 Capacities Specific Programme,
HC review, A. Perin, 12-MAY DFB Project LHC hardware commissioning review May 2005 Hardware commissioning of the DFBs and DSLs and connection.
12th HL-LHC Parameter and Layout Committee meeting.
Integration studies – Part 1 Inner triplet Y. Muttoni TS-ICC-LI 31 July 2008.
Long shutdown 1 LHC Machine Status Report K. Foraz June 12 th, 2013.
March 22,  Overview of Asian Civil Design  Previous Case Study  Feature of Beam Tunnel  Tunnel Typical Cross Section  Beam Tunnel.
9/17/07IRENG071 Cryogenic System for the ILC IR Magnets QD0 and QF1 K. C. Wu - BNL.
Karl Williams Mechanical Engineer AD/MS Fluids Group Absorber RAW Cooling Systems.
1 Sector Test – Preparation Layout in LSS7 Jan Uythoven (AB/BT) Thanks to Mike Lamont and the other ‘sector testers’
Superconducting Technologies for the Next Generation of Accelerators CERN, Globe of Science and Innovation 4-5 December Superconducting Links for the Hi-Lumi.
The integration of 420 m detectors into the LHC
R. Ostojic, IRP1 CD Review, 31 July 2008 LHC IR Upgrade Phase I Goals and Constraints 1.Upgrade goals and milestones 2.Upgrade of IR systems: main constraints.
The HiLumi LHC Design Study is included in the High Luminosity LHC project and is partly funded by the European Commission within the Framework Programme.
R. van Weelderen and U. Wagner CERN
Teleconf ACS – FREIA 28th March 2017
Superconducting Links R2E and Avalilability Workshop
News and Introduction from CERN June 15th, 2005
CLIC Handling Engineering Update
HL-LHC IT STRING and Series test of SC link
Introduction and Meeting Objectives
IT-4189 Supply and installation of a cryogenic distribution system
MERcury Intense Experiment Experiment Layout
Equipment simplified model SMR UR safety
News from Integration WG
Helium spill in LHC tunnel
M. Alcaide Leon, Paolo Fessia
M. Alcaide Leon, Paolo Fessia
Hollow e- lens, Cryogenic aspects
Y. Muttoni - J.P. Corso TS Workshop Archamps
Status of Cryogenics Facilities Design
From Design to Installation courtesy R. Folch S. Atieh TS / MME
ATLAS ITk CO₂ Cooling pipe routing CO₂ Meeting, 28 June 2016
ATLAS ITk CO₂ Cooling pipe routing Common Mechanics meeting
Business opportunities related to CERN electrical network
Upgrade phase 1: Energy deposition in the triplet
LS3 Study & Readiness Meetings
Polarized 3He target installation
Presentation transcript:

LHC Insertions Upgrade Working Group (LIUWG) Space available in tunnel Y. Muttoni

LHC Insertions Upgrade Working Group (LIUWG) Overview Geographical location Study inputs and limitations Equipment in place UJ14 Study implantation new equipment UJ14 Equipment in place RZ54-USC55 Equipment in place UJ56 Conclusion

LHC Insertions Upgrade Working Group (LIUWG) Geographical location

LHC Insertions Upgrade Working Group (LIUWG) Geographical location USC55

LHC Insertions Upgrade Working Group (LIUWG) Equipment (compared to existing solution). Add energy extraction (DQR-DQS). Electrical feed box outside beam. Warm magnet or cold D1 magnet with surface powering assumed for current study. Limit Implantation studied around Pt1 in UJ14 (UJ16 symmetrical). Electrical feed box like DFBL used, DSL (Superconducting bus bar line) and QRLX (Cryogenic line extension) should be necessary. In future new DQR (not mechanical but semiconductor) should be studied (K. Dahlerup-Petersen/R. Denz). Implantation around Pt5 did not study but kept in mind. Study inputs and limitations

LHC Insertions Upgrade Working Group (LIUWG) Study inputs and limitations

LHC Insertions Upgrade Working Group (LIUWG) Point 1

LHC Insertions Upgrade Working Group (LIUWG) Equipment in place UJ14

LHC Insertions Upgrade Working Group (LIUWG) Equipment in place UJ14

LHC Insertions Upgrade Working Group (LIUWG) Equipment in place UJ14 Access control Removable Sector wire fencing removable

LHC Insertions Upgrade Working Group (LIUWG) Equipment in place UJ14

LHC Insertions Upgrade Working Group (LIUWG) Equipment in place UJ14 UL14 IP1 Access control Removable

LHC Insertions Upgrade Working Group (LIUWG) Equipment in place UJ14 UJ14 IP1 UJ13 Space reserved for transport

LHC Insertions Upgrade Working Group (LIUWG) Equipment in place UJ14 UJ14 1 st floor IP1 UJ13 UTA

LHC Insertions Upgrade Working Group (LIUWG) New equipment in UJ14

LHC Insertions Upgrade Working Group (LIUWG) New equipment in UJ14

LHC Insertions Upgrade Working Group (LIUWG) New equipment in UJ14 DFBL 2x13KA 6x600A 2x120A

LHC Insertions Upgrade Working Group (LIUWG) New equipment in UJ14 Cryogenic link Electrical link Routing link should be studied more in detail

LHC Insertions Upgrade Working Group (LIUWG) New equipment in UJ14 Holes through shielding wall

LHC Insertions Upgrade Working Group (LIUWG) New equipment in UJ14

LHC Insertions Upgrade Working Group (LIUWG) New equipment in UJ14

LHC Insertions Upgrade Working Group (LIUWG) New equipment in UJ14 D1 cold Cryogenic link Electrical link

LHC Insertions Upgrade Working Group (LIUWG) Point 5

LHC Insertions Upgrade Working Group (LIUWG) Equipment in place RZ54-USC55

LHC Insertions Upgrade Working Group (LIUWG) Equipment in place RZ54-USC55

LHC Insertions Upgrade Working Group (LIUWG) Typical cross section in R542

LHC Insertions Upgrade Working Group (LIUWG) Equipment in place UJ56

LHC Insertions Upgrade Working Group (LIUWG) Equipment in place UJ56

LHC Insertions Upgrade Working Group (LIUWG) Conclusion D1 cold: Increases the number of racks underground, necessary to find place for DFBL. Choice DFBM in main tunnel: More space in service cavern but in point 5 small tunnel to install DFBM. Not necessary to have cryogenic link and electrical link Not necessary to drill new hole in the shielding wall. New rack layout New cable routing required. New water pipe routing required. Audit of rack use required with all owners (optimize space?). New energy extraction Required for space constraints Checking metallic structure. Future integration studies More progress with P1 design (components and layout) before progressing with P5 studies