Summary of Si Strip Group QA Preparation & Schedule and Costs Abhay Deshpande Stony Brook University PHENIX VTX Detector Readiness Review Brookhaven National.

Slides:



Advertisements
Similar presentations
8-3-05Jens Jørgen Gaardhøje. NBI. ALICE-CR5 1 ALICE Forward Detectors Technical Design Report Editorial team: I.G. Bearden (NBI) H. Bøggild (NBI) C.Holm.
Advertisements

Silicon Preshower for the CMS: BARC Participation
128 September, 2005 Silicon Sensor for the CMS Tracker The Silicon Sensors for the Inner Tracker of CMS CMS Tracker and it‘s Silicon Strip Sensors Radiation.
October 7, 2003 US Silicon Tracker group Sergey Korjenevski University of Rochester 1 Quality Assurance Test Stand University of Rochester oQTC at Rochester,
Sensor overview Ulrich Heintz Brown University, Providence, RI 6/18/2015U. Heintz - Sensor Overview 1.
Linac Front-End R&D --- Systems Integration and Meson Lab Setup
Institute of Physics ASCR, Prague Strip Sensors R&D for SCT and ITk Marcela Mikeštíková.
8/22/01Marina Artuso - Pixel Sensor Meeting - Aug Sensor R&D at Syracuse University Marina Artuso Chaouki Boulahouache Brian Gantz Paul Gelling.
Jon S Kapustinsky 11/17/2010 Jon S Kapustinsky FVTX Commissioning Plan 1.71 Jon S Kapustinsky 1.
Christina Hägemann,UNM Sensor Testing at University of New Mexico C. Hägemann, M. Hoeferkamp, D. Fields, A. Zimmerman, M. Malik VTX Meeting 03 June 2005.
HIE-ISOLDE contribution packages M. Pasini BE/RF.
Temperature dependence of sensor leakage current Contents Introduction Measurement Result Summary Junkichi Asai (RIKEN BNL Research Center) (Hiroki kanoh.
David M. Lee Forward Vertex Detector Cost, Schedule, and Management Plan Participating Institutions Organizational plan Cost Basis R&D Costs.
Slide 1 6-Nov-98PHOBOS Review: Cost & Schedule Cost & Schedule S. Steadman, MIT PHOBOS Cost & Schedule Review Technical Advisory Committee BNL November.
Anna Macchiolo, Status of Process Qualification Centers, Sensor Meeting, 31st Oct 2001 Status of Process Qualification Centers Florence, Strasbourg, Vienna.
Silicon Inner Layer Sensor PRR, 8 August G. Ginther Update on the D0 Run IIb Silicon Upgrade for the Inner Layer Sensor PRR 8 August 03 George Ginther.
2004/09/07 Junkichi Asai (RBRC) (Kieran Boyle (SBU))
Concluding Summary WBS1.1.2 SCT Subsystem A. Seiden BNL March 2001.
Silicon Meeting July 10, 2003 Module and Stave Production Status James Fast Fermilab.
The Bigbite second GEM tracker. SBS GEM Trackers Front Tracker Geometry x6 18 modules In Italy  50 cm x 40 cm Modules are assembled to form larger chambers.
U.S. Deliverables Cost and Schedule Summary M. G. D. Gilchriese U.S. ATLAS Review Revised Version November 29, 2000.
Guido_Tonelli / CMS_TSC / 5 February Time stability of ST sensors The problem The sensors re-measuring campaign Failure analysis Conclusions.
Testing Site Qualification Purpose: –Perform detailed scans of the silicon microstrips to make sure they all work. –Check HPK. Candidates for Certification:
Muon trigger upgrades, missing since not aimed towards DOE funding PHENIX upgrades: view presented to DOE R&D $3.5M Construction $16.6M Au-Au p-p 200 Si-Si.
M. Gilchriese Sectors, Rings, Frame Assembly and Installation July 18.
DOE Rev of Run IIb Sep 24-26, Silicon sensors procurement and quality assurance WBS Regina Demina Kansas State University Frank Lehner University.
Fermilab PMG - Results from module testing - April 9, 2004 – E.Chabalina (UIC) 1 Results from module testing E.Chabalina University of Illinois (Chicago)
8 July 1999A. Peisert, N. Zamiatin1 Silicon Detectors Status Anna Peisert, Cern Nikolai Zamiatin, JINR Plan Design R&D results Specifications Status of.
David Lee, FVTX Review Nov Cost and Schedule WBS 1.0 David M. Lee Los Alamos National Lab Deputy Project Leader.
CMS Si Tracker Project - US CMS Meeting at Riverside – May 19, US CMS Tracker Outer Barrel (TOB) Silicon Project Tim Bolton (for Regina Demina)
Silicon Strips for PHENIX SVTX Status and Plans for Silicon Strips in PHENIX SVTX Abhay Deshpande Recent development: Possibility of the second Si Pixel.
1 Silicon Testing at KSU Sergey Korjenevski Kansas State University 06/18/2002 (11 slides total)
FVTX Wedge Assembly WBS , , , , , David Winter Columbia University FVTX Wedge Manager.
RD50 Michael Moll – PH-TA1-SDMeeting February 25, Three R&D strategies:  Material engineering - Defect engineering of silicon (oxygenation, dimers,
Brenna Flaugher Sept. 24 th Lehman Review1 Run IIB Silicon Upgrade: Cost and Schedule Lehman Review Sept. 24, 2002 Brenna Flaugher Run IIB Silicon Project.
Forward Vertex Detector Cost, Schedule, and Management Plan Participating Institutions Organizational plan Cost Basis R&D Costs Cost Schedule.
1 FVTX Monthly/Quarterly Report January 2009 Cost Summary Schedule Summary Current technical status of each WBS item.
Phase 2 Production Discussion We would like to review the conclusions reached at Caltech on US involvement in the phase 2 outer tracker This will be presented.
D. M. Lee, LANL 1 07/10/07 Forward Vertex Detector Overview Technical Design Overview Design status.
1 HBD: Update and Schedule Itzhak Tserruya DC Meeting, BNL, April 13, 2005 Outline:  Full scale prototype status  Light source test  Construction Schedule.
Maria Rita Coluccia Simon Kwan Fermi National Accelerator Laboratory
GLAST LAT ProjectMarch 24, B Tracker Peer Review, WBS GLAST Large Area Telescope: Tracker Subsystem WBS B: Silicon Strip Detector.
Status Report for E391a (Continuation of the previous PAC on April) G.Y.Lim IPNS, KEK Group Meeting at the JINR 26 th – 29 th July 2003 Dzhelepov Laboratory.
PHENIX Vertex Detector with Conventional Strip Sensors Abhay Deshpande Stony Brook University.
August DESY-HH VFCAL Report W. Lohmann, DESY Infrastructure for sensor diagnostics FE Electronics Development Sensor test facilities Laser Alignment.
Production Database Apollo Go, NCU Taiwan Preshower Silicon PRR July 5, 2001.
Plans to Test HBD Prototype in Run 6 Craig Woody BNL DC Meeting March 8, 2006.
March 25, FVTX Monthly/Quarterly Report June, 2009 Technical Status, Cost & Schedule Melynda Brooks, LANL.
David M. Lee Forward Vertex Detector Cost, Schedule, and Management Plan Participating Institutions Organizational plan Cost Basis R&D Costs.
September 7, 2004Si VTX Strip Overview1 Overview of VTX Strip Group Activities Abhay Deshpande SUNY-SB For Si Strip Group.
EDM Fast Start Presentation WBS 11 – Assembly and Commissioning Vince Cianciolo, Paul Huffman May 23, 2006.
Status of the Planar Edgeless Silicon Detectors Gennaro Ruggiero TOTEM Collaboration Meeting 09/11/2005.
1 HBD: Responsibilities, Cost and Schedule Itzhak Tserruya EC/DC Meeting, BNL, March 9, 2005.
Procurement Readiness Review : Detector Fabrication, Qualification & Assembly at India M D Ghodgaonkar Electronics Division, BARC, India.
Silicon strip detector R&D issues –readout chip decision –interface with PHENIX –ladder Technical options –SVX4 or MVD-TGV+AMU/ADC recut –other sensors.
Preparations to Install the HBD for Run 6 Craig Woody BNL PHENIX Weekly Meeting January 26, 2006.
Upgrade with Silicon Vertex Tracker Rachid Nouicer Brookhaven National Laboratory (BNL) For the PHENIX Collaboration Stripixel VTX Review October 1, 2008.
Preparation for silicon sensor arrival sensor delivery schedule aggressive expect 130 L2-L5 sensors each in July and August sensor lot/batch will likely.
Eija Tuominen, coordinatorHIP/UH Detector Laboratory, October 2010 DETECTOR DEVELOPMENT at HELSINKI DETECTOR LABORATORY Detector Laboratory is a joint.
ADC values Number of hits Silicon detectors1196  6.2 × 6.2 cm  4.2 × 6.2 cm  2.2 × 6.2 cm 2 52 sectors/modules896 ladders~100 r/o channels1.835.
Preshower PRR July NCSR DEMOKRITOS Production Center : Institute of Microelectronics (IMEL) Regional Center : Institute of Nuclear Physics (INP)
QA Tests Tests for each sensor Tests for each strip Tests for structures Process stability tests Irradiation tests Bonding & Module assembly Si detectors1272.
Si Sensors for Additional Tracker
Karlsruhe probe equipment and QA proposals/expertise
Status Caltech meeting – discussions of assembly centers, US responsibilities We will try to organize a PS module assembly workshop at Brown April 30 –
EENP2 Silicon Detectors.
Pradeep Ghosh for the CBM Collaboration Goethe-Universität, Frankfurt
Hybrid & Module Electrical Testing
HIE-ISOLDE contribution packages
HL-LHC upgrade at IPHC news
Presentation transcript:

Summary of Si Strip Group QA Preparation & Schedule and Costs Abhay Deshpande Stony Brook University PHENIX VTX Detector Readiness Review Brookhaven National Laboratory January 19, 2005

Overview You heard about the –Strip Sensor from J. Tojo (RIKEN) –Front End Electronics from V. Cianciolo (ORNL) This talk will cover –Plans for Q/A for Si Strip Sensors Status of Three facilities: BNL, UNM and SBU –Plans for assembly and tests for ladders onwards Collaboration: RIKEN, SBU, BNL-Chemistry Schedule & Costs Manpower for Q/A

January 19, QA & Assembly Plan Sensor QA –Preproduction of Hamamatsu/SINTEF wafers: Resistance, doping tests, diced in to Sensors –400 sensors start arriving BNL/RBRC Mid 2005 Registration, visual inspection Divide them up in to three sets SBU, UNM, RBRC/BNL 1 or 2 wafers/day/site –Current, Capacitance at full depletion Voltage –Inter-strip current & capacitance (x-x, u-u, and a few x-u) Assembly of ladders and QA –ROC+Sensor (SBU/RIKEN) Glue (6-8 hrs) + wire-bond (2 hrs) + test (1 hr) –Ladder (5 ot 6 ROC+Sensors) (SBU/RIKEN) Glue + wire-bond (1 hrs) + test (1 hr) First one taken for bench & beam test, next only bench tests Construction of the barrel: BNL Chemistry/PHENIX

January 19, Laboratory Setups and Status RBRC/BNL –Laboratory setup in the last three months –Semi-Automatic probe station moved from instrumentation division and added equipment peripherals –Activity started, fully functional facility Stony Brook University –Stony Brook high energy physics facility for D0 to be given to PHENIX for 2-3 years starting Jan/Feb 2005 –Fully functional with clean room, semi-automatic probe station and peripheral; plans to add bonding machine with off project funds University of New Mexico –UNM high energy physics CDF facility to be used for PHENIX SVTX QA, fully equipped, software being installed and tested. Fully functional in the next few days/weeks

January 19, New RBRC/BNL Laboratory Setup

January 19, What is where in this lab? New clean room at BNL The new clean room was setup at RBRC lab. room in BNL in this October. Fitting room Wafer in the desiccators Semi-automatic probe station in the dark box PC for DAQ PC for Analysis N2 gas for desiccators Keithley 7002 switching system HP 4263B LCR meter Keithley 6487 HV/Ammeter The condition in the dark box is almost; temp: 25[oC] hum : 15[%]

January 19, Semi-Automatic Probe Station Ribbon Cable GPIB Cable Probe station HV/Ammeter Keithley 6487 Switch system Keithley 7002 LCR Meter Agilent 4263B Windows LabView Windows LabView controlled All device through GPIB cable. Dark Box Microscope Movable stage chuck Probe positioner for Guard Ring Probe card sensor Probe stage

January 19, SINTEF measurements at RBRC/BNL Good x strip Bad u strip Good u strip

January 19, QA guidelines & criteria Mechanical properties: dimensions, thickness, widths, edge chipping, alignment of various components including metallization points etc. –UNM,SBU already have facilities that do this Electrical properties: CV, IV curves, leakage current on strips, inter-strip resistance, inter strip capacitance) –Key tests (every sensor, every ladder) –Subset tests (defined fraction of sensors and ladders) Laser/source and observe basic response, CV/IV 1 u/x per active area (4 per sensor) –Diagnostic tests: to be performed on sensor/ladders tagged for some abnormality All data to be stored in a dedicated database presently being produced by P. Steinberg et al (BNL/Chemistry) –Extensive experience from PHOBOS will be preserved!

January 19, Strip Sensor Presently [here] ==> Jan-Mar’05 QA of preproduction ==> Decision ==>Production Sensors Arrive (7/19/05) ==> divide 400 in to 3 sets and ship to QA sites. ==> Three months for QA (130 wafers : 2 wafers/day = 65 days ~25 days contingency (38%) but that too is an under estimate since we need only 246 wafers as against 400 assumed in this calculation and real start date may be much earlier than the presumed (1/2/06).

January 19, Strip Sensor Budget Most of the work performed by students/post docs so no manpower cost to project. Assume $2500/month for materials costs in laboratories, times 3 months + BNL overhead + 50% DOE contingency = TPC DOE

January 19, Strip System Tests Presently [here] ==> next year for ROC+Sensor “module” development ==> start assembly of ladders for testing Oct’05 and continue until Oct.’06

January 19, Strip System Test Budget TPC DOE = (Man-hour estimates + Material costs + BNL overhead) + 50% DOE contingency. Most work will be done by the post docs and students (see list later) Man-hour cost estimate: depends on technician help or engineering help Material cost $1500/ month times number of months

January 19, Strip Ladder Assembly

January 19, Strip Ladder Assembly Budget 9 months of a technician assumed 5k/month Material costs: setting up of jigs, and later test equipment: engineering estimate TPC DOE = (Manpower + material cost + BNL overhead) + 50% DOE Contingency

January 19, Summary: FTEs, Cost & Contingencies All FTE-weeks calculated with 30-45% time contingencies Slide 10 ==> 60 FTE-weeks Slide 12 ==> 84 FTE-weeks Slide 14 ==> 224 FTE-weeks Total FTE-weeks for this part of the project: 368 Most of this work will be done by Physicists (students/post docs) DOE Total Project Costs for this part of the project = BNL overhead + (additional overhead if applicable) + 50% DOE contingencies Total Project Cost (TPC) for this part of the project is: $343,478 = $88,750 (manpower) + $141,322 (material + overhead) + $113,406 (~50% contingency)

January 19, Person-power: QA, assembly & tests Stony Brook University –Grad Students: K. Boyle, R. Bennett, S. Campbell, A. Dion, M. Nguyen, H. Themann, and more expected in future –Post Doc to be appointed + J. Franz –Technical/Electrical/Electronics: R. Hutter, C. Pancake, E. Shafto –Faculty: A. Deshpande, A. Drees, V. Pantuyev RIKEN-BNL Research Center at BNL –Post Doc: J. Asai –Scientist: J. Tojo, Y. Goto, A. Taketani, Y. Akiba BNL Chemistry –Scientsts: R. Noucier, R. Pak, P. Steinberg, M. Baker, B. Holzman, A. Sukhanov –Post Doc: Z.W. Chai University of New Mexico –Graduate students: R. Hobbs + future students –Technical: M. Hoeferkamp –Faculty: D. Fields