LS2 Other LHC Experiments Mike Lamont Thanks to: Michael Rijssenbeek (AFP) Joachim Baechler (TOTEM) Karl-Heinz Hiller (ALFA)

Slides:



Advertisements
Similar presentations
Beam commissioning strategy Global machine checkout Essential 450 GeV commissioning System/beam commissioning Machine protection commissioning.
Advertisements

Atlas SemiConductor Tracker Andrée Robichaud-Véronneau.
Saverio MINUTOLITIG meeting, 10 February Report on T1 installation activities and achievements made during this shutdown.
Experimental Area Meeting V. Bobillier1 Good connection to earth (in many points) of every metallic parts to be installed in the cavern is very.
The LHCf experiment Measurement of Photons and Neutral Pions in the Very Forward Region of LHC Letter Of Intent: May 2004 Technical report: September 2005.
Gueorgui ANTCHEVNEC’2013 – Varna, Bulgaria 1 The TOTEM Experiment Consolidation and Upgrade G. Antchev * On behalf of the TOTEM Collaboration * INRNE-BAS,
The First 1 ½ Years of TOTEM Roman Pot Operation at the LHC M. Deile, G. Antchev, I. Atanassov, V. Avati, J. Baechler, K. Eggert, J. Kašpar, F. Lucas Rodriguez,
TOF for ATLAS Forward Proton Upgrade AFP concept: adds new ATLAS sub-detectors at 220 and 420 m upstream and downstream of central detector to precisely.
FP420 Vacuum Ray Veness. Contents o What is FP420? o How would it be installed in the LHC? o What would it look like? o What are the issues/interest for.
Forward physics pertinent ECRs Mike Lamont, Samy Chemli.
V. Bobillier1 Long distance cable installation status Calorimeter commissioning meeting.
1 Tehniline ülevaade uusimast füüsikast CERN’is Endel Lippmaa 20. Detsember 2006, TTÜ.
Construction and Installation Readiness of TOTEM Roman Pots Detectors Federico Ravotti (PH/TOT) Gennaro Ruggiero (PH/TOT) LHCC minireview – 06 May 2009.
Experimental equipment interacting with beam operation D. Macina TS/LEA Many thanks to my colleagues both from the experiments and the machine for their.
Roman Pot Engineering Design Review CERN, 14 February 2006 M.Oriunno, CERN PH-TOT Installation, Commissioning and Schedule.
A MOVEMENT CONTROL SYSTEM FOR ROMAN POTS AT THE LHC Ben Farnham, Sylvain Ravat, Federico Ravotti, Mario Deile, Patrick Fassnacht, Odd Oyvind Andreassen,
ECRs and ES for the LHC Last presentation on the 26 th of August 2015 (LMC 232) S. Chemli for EN-MEF-DC LMC xxx.
AFP Introduction September 10th 2014 M. Bruschi, INFN Bologna (Italy) 1.
Outlook Production of the 12 DPs (220m Stations) Installation of the DPs in the LHC Tunnel Status of the RP Systems/Services Resources Production of DPs.
Improvements of the ALFA and TOTEM Roman Pot Movement System in TS1 Mario Deile with input from P. Fassnacht, S. Jakobsen, J. Kaspar, S. Ravat for the.
STATUS REPORT: ALIGNMENT OF COLLIMATORS P. BESTMANN /O. ABERLE Collimation Working Group 26/09/2011.
Experimental Sectors Ray Veness / AT-VAC With many thanks to G.Foffano + W.Cameron TS/MME Patrick Lepeule / AT-VAC.
LHCf: installation & commissioning Measurement of Photons and Neutral Pions in the Very Forward Region of LHC Oscar Adriani INFN Sezione di Firenze - Dipartimento.
The Stripping Foil Test Stand in the Linac4 Transfer Line
Status of and Installation Plan for DC Gas Control System and Target Work Scheduling Meeting 4 August 2006 PSI W. Molzon, Feng Xiao.
P. 1Mario Deile – Meeting on Experiment Protection from Beam Failures Protecting TOTEM Mario Deile PH-TOT
Activities related to Experiments during TS3 and YETS th November, 2015 M. Bernardini, M. Barberan With the support of S. Chemli and Experiments.
Design, integration and installation milestones Legend: 2015/Q1= 1 st quarter of 2015 (January-March) Phase 1 = proton & laser beams operation Phase 2.
ATLAS-ALFA as a beam instrument Sune Jakobsen (BE-BI-PM and PH-ADO) on behave of the ATLAS-ALFA community LS1 LBOC meeting
1 Sector Test – Preparation Layout in LSS7 Jan Uythoven (AB/BT) Thanks to Mike Lamont and the other ‘sector testers’
Walter Snoeys – CERN – PH – ESE – ME –TOTEM October 2009 TOTEM Electronics Status.
RRB scrutiny Report: Muons. Internal scrutiny group for RRB report Internal scrutiny group composition – J. Shank, G. Mikenberg, F. Taylor, H. Kroha,
AFP Trigger DAQ and DCS Krzysztof Korcyl Institute of Nuclear Physics - Cracow on behalf of TDAQ and DCS subsystems.
 Based on 2+2 Roman Pot Stations on each side of ATLAS at ~ 240 m from the Interaction Point  Aim in Run 2 at measuring the total cross section and.
Preamble Run 2 and Run 3 will see the continued exploitation of the forward physics potential of the LHC in the long straight sections (LSS) either side.
AFP – Technical Status 1.Cost estimates 2.Manpower estimates 3.First Actions AFP Kick-Off 03FEB Michael Rijssenbeek.
Low-x Meeting 2015 Sandomierz, 1-5 September 2015 Joao Varela, LIP/IST Lisbon (presented by K. Piotrzkowski) Physics Prospects with the CT-PPS Forward.
All Experimenters MeetingDmitri Denisov Week of July 22 to July 29 D0 Summary  Delivered luminosity and operating efficiency u Delivered: 3.1pb -1 u Live:
TE-CRG Activities D. Delikaris, TE-CRG.
Geoff HallLECC LHC detector upgrades Introductory comments on electronic issues Organisation of this short session.
1 Welcome to the mini-review of the Roman Pot mechanics for the ALFA project in ATLAS.
TOTEM Status Report F.Cafagna CERN & INFN-BA on behalf of TOTEM Collaboration.
Joint LHC Machine-Experiments Workshop on Very Forward Detectors - 25 January 2007 Beniamino Di Girolamo - CERN PH ATLAS Roman Pots status, commissioning.
D.Macina TS/LEATOTEM Meeting25/02/2004 Roman Pot test at the SPS Test of the Roman Pot prototype in the SPS proposed in December 2003 (CERN/LHCC ):
Mike AlbrowSept 8 th 2005Test Beam for FP420 Vacuum Chambers/Detectors 1 Things we need to test (and why) How we could, together with BTeV people, detectors,
ATLAS Forward Proton Detectors ATLAS Forward Proton Detectors Michael Rijssenbeek for the ATLAS Collaboration Physics summary: Physics withSingle and Double.
FORWARD ATLAS {major contributions from Per Grafstrom (CERN), Michael Rijssenbeek (Stonybrook), Brian Cox (Manchester} Andrew Brandt Luminosity measurement.
Diffraction at LHC (How to turn LHC into a 14 TeV Gluon Factory ?) stolen from Risto Orava University of Helsinki and Helsinki Institute of Physics Workshop.
Preparation & Commissioning of TOTEM for the Run-II of LHC S.Giani on behalf of the TOTEM Collaboration.
Integration of forward physics detectors into the LSS of the LHC D. Macina (TS/LEA) Technical Support 2004 Workshop.
The timing upgrade project of the TOTEM Roman Pot detectors
Status of the ATLAS Forward Proton Detectors Michael Rijssenbeek for the ATLAS AFP group 25FEB2016.
HPS: R&D issues Krzysztof Piotrzkowski (UCLouvain/CERN)
EYETS David Hay EN-OSS.
Introduction Status before the 2009 run Results from the 2009 run
First data from TOTEM experiment at LHC
Diffraction and Forward Physics in ATLAS: results and perspectives
AD consolidation activities in LS2
Injectors BLM system: PS Ring installation at EYETS
P.Fassnacht on behalf of ATLAS/ALFA
Status of the BI Work Package in the LIU-PSB frame
LS2 LHC forward experiments
(with R. Arcidiacono, A. Solano)
Tuesday 22nd January - morning
TOTEM experiment at the LHC
Equipment of experiments directly interfering with the beam operation
Status of CMS-PPS timing detectors
Thursday 22 September 2011.
Friday 14th September 03:15 Beta* at 1 km. Optics measurements, see yesterday. 07:00 Dump. 08:00 Refill with 3 nominal bunches for high beta. 11:15 Beams.
Status of the BI Work Package in the LIU-PSB frame
Presentation transcript:

LS2 Other LHC Experiments Mike Lamont Thanks to: Michael Rijssenbeek (AFP) Joachim Baechler (TOTEM) Karl-Heinz Hiller (ALFA)

TOTEM and CT-PPS

TOTEM Plan to progressively install the detector components in the Roman Pots Diamond Timing Detectors (vertical RPs of 220m near, sector 4-5 and 5-6) & associated components – start: TS > YETS – ECR - under preparation Pico-second clock distribution system (fibre based) – start: TS > YETS – ECR - under preparation

CT-PPS CMS-TOTEM Precision Proton Spectrometer Cerenkov Quartic timing detectors (cylindrical Roman Pots, 220m region, sector 4-5 and 5-6) & associated components – start: YETS 2015/2016 -> TS 2016 – ECR under preparation Pixel detector (horizontal RPs, 210m near/far, sector 4-5 and 5-6) & associated components – start: YETS 2015/2016 -> TS 2016 – ECR under preparation Clock distribution system - based on rigid RF cable to be laid from 220m region sector 4-5 via the bypass to 220m region of sector 5-6. – start: YETS 2015/2016 – ECR draft version already in EDMS (Finn Rebassoo) – First meeting with G. Canale (EN-MEF) took place last week > problems with the size of the cable drum -> not yet clear how to proceed.

TOTEM: LS2 Originally planned to have two cylindrical RPs per side and it could be possible, that we use LS2 to integrate such additional RP per side in the already existing mechanical frame. Furthermore, during LS1 we have not succeeded to create the two small excavations (radiation limiter) in the tunnel floor to locate radiation sensitive electronic timing components close to the detector. This might still be required, if the radiation level would limit the operation of the FPGA or other electronics This activity (if finally approved) during LS2 might require for safety reason the local removal of the beam pipe. no major upgrades planned for LS2 data taking in Run 3 with existing detectors no planned operation during HL-LHC

TOTEM: Run 3 The operation of the present TOTEM Roman Pots at high beta optics/special runs is officially foreseen until the max. possible energy of LHC has been reached, allowing to complete the approved scientific mission of TOTEM. Any future operation of the Roman Pots within the CT- PPS project at standard LHC optics will depend on the insertion limitations we find during the intensity ramps. The performance of the detector inserts in the Roman Pots under the specific radiation conditions (tracking and timing) will then determine the physics reach.

ALFA

ALFA: YETS Our major activity in LS1 was the protection against RF heating. – Full success. – If there are no future dramatic effects this ensures data taking until end of Run2. Enhanced UFO activity of one particular station – After some movement exercises the UFO level is unchanged. – Raise dump threshold by a factor 25, as done for TOTEM - should be sufficient for a safe LHC running

ALFA YETS 2015 activities On surface: – movement firmware update – prepare executables for PXI – commissioning of new movement & interlock – new firmware for ALFA_CTPIN trigger board – timing and commissioning of new triggers – adding a second DCS computer and splitting of the project In USA15 and tunnel: – install new crate for movement system to reduce noise – replace a noisy LVDT and electronics for A7L1L – upload new firmware for motherboards + PMFs – install new vacuum pumps & replace filters – exchange or modify a few radmons for higher intensity The team is small and load for people high!

ALFA – LS2 The long term plan for ALFA is to finish the physics program, total cross section and luminosity measurement, in Run2. No plans for LS2 But note AFP…

ATLAS Forward Proton (AFP) ATLAS Forward Proton detectors ~upgrade of ALFA Approved Physics: Single Diffraction, Double diffraction in special runs 2016 – 2018 To be approved: Exclusive Dijet, Exclusive WW (ZZ, γγ, …) p p forward jet (lost) central gluon jets forward jet (obsvd.) p g IP 205m217m SDDDCEDaQGC

AFP: Installation in YETS2015 Install ONE arm of AFP in C6R1 (Jura side of IP 1): – Cabling: 2×2 7/8” Ø Fast trigger cables, 2×1 optical data cable through SURVEY galleries on BOTH (!) sides of IP1 ~20 Service cables (LV, HV, monitoring, controls, … ) – Modify Exterior vacuum chamber between Q5 and Q6 2 VPI 2 BLM, 1-2 BPM – 2 Roman pot stations: 205 m, 217 m from Point 1 secondary vacuum air cooling – Tracking and (possibly) Time-of-Flight detectors PLUS: patch panels/crates/racks at 205 m, 217 m, and 212 m commissioning of motorization, interlocks, and detectors ~4 weeks ~3 weeks

AFP: Installation in EYETS2016 Install SECOND arm of AFP in C6L1 (GVA side of IP 1): – Cabling: ~20 Service cables (LV, HV, monitoring, controls, … ) – Modify Exterior vacuum chamber between Q5 and Q6 2 VPI 2 BLM, 1-2 BPM – 2 Roman pot stations: 205 m, 217 m from Point 1 secondary vacuum air cooling – Tracking and Time-of-Flight (ToF) detectors PLUS: patch panels/crates/racks at 205 m, 217 m, and 212 m commissioning of motorization, interlocks, and detectors Commissioning of new Trigger Electronics based on ToF ~3 weeks ~3 weeks

AFP: Plans for LS2 Possible AFP UPGRADES for Run 3: – Strongly dependent on pre-LS2 experience! – Modify Exterior vacuum chamber between Q5 and Q6 possibly add second BPM (after 205 m station) – Remove & refurbish ALFA vertical stations? – Tracking and Time-of-Flight (ToF) detectors: Update trackers if needed Update ToF if needed ~3 weeks ~5 weeks

MOU start date: 01/09/2014 End date > 01/09/2019

Conclusions TOTEM and CT-PPS – Detector upgrades ongoing for an ambitious data taking program in Run 2 and Run 3 ALFA – Aim to finish data taking in Run 2 AFP – New pots in YETS15, EYETS – Not so much in LS2 (but might refurbish ALFA)