Executive Session Director’s CD-1 Review of the Mu2e Project April 3, 2012 Elaine McCluskey.

Slides:



Advertisements
Similar presentations
PAINLESS PERIODIC REVIEW Cynthia Steinhoff Anne Arundel Community College Arnold, Maryland.
Advertisements

OFFICE OF SCIENCE Kurt W. Fisher Review Committee Chair Office of Science, U.S. Department of Energy 1 Closeout Report.
The Value of a Project Management Office Copyright: Kathy J. Lang, 2004.
The Re-Start Meeting Warren County School Strategic Planning Process Action Team Leaders September 25, 2013.
Executive Session Director’s CD-1 Follow-Up Review of the APUL Project November 2-3, 2009 Dean A. Hoffer.
Managing Evaluations for Consistently High Quality American Evaluation Association Annual Conference Molly Hageboeck.
1 Orientation For Reviews of Initial Credentialing Proposals Ron Briel, Program Manager Licensure Unit Division of Public Health Department of Health &
OFFICE OF SCIENCE 1 Closeout Presentation and Final Report Procedures.
Chapter 2 The Analyst As Project Manager In Managing Information Systems 2.3.
©2007 by the McGraw-Hill Companies, Inc. All rights reserved. 2/e PPTPPT.
Mu2e WGM 2/22/2011 R. Ray Mu2e Project manager. CD-1 Our sole focus is on CD-1 and in particular, the Director’s Review scheduled for April 3-5. To be.
Jan 28, 2009CFS-GBL meeting 1 PM report Jan 28, 2009: Reviews –AAP –PAC (May 9 and 10, 2009) Meetings –TILC09 FALC –Madrid, Jan 19, 2009.
OFFICE OF SCIENCE Kin Chao, Chairperson DOE/SC Review Committee Office of Science, U.S. Department of Energy Review Committee.
How Your Application Is Reviewed Vonda Smith, Ph.D. Scientific Review Officer (SRO)
First Executive Session Fermilab Director’s/DOE Fermi Site Office's Performance Management System Review of the NOvA Project June 19-20, 2007 Frank Gines.
1 Dissertation & Comprehensive Exam Process Dissertation Process Comprehensive Exam.
L. Greiner 1IPHC meeting – September 5-6, 2011 STAR HFT Plans for the next year A short report on review results and plans for TPC – Time Projection.
1 Dissertation Process 4 process overview 4 specifics –dates, policies, etc.
NuMI Offaxis Costs and Whither Next Stanley Wojcicki Stanford University Cambridge Offaxis workshop January 12, 2004.
GLAST LAT Offline SoftwareWorkshop - SLAC, Jan , 2001 R.Dubois Lehman Review Feb Joint NASA/DoE review My understanding: –“The purpose of the.
Chapter 11: Follow-up Reviews and Audit Evaluation ACCT620 Internal Auditing Otto Chang Professor of Accounting.
A MEMBER OF THE RUSSELL GROUP PGR PERIODIC REVIEW Sara Crowley
Project Lifecycle Section 6 - Closeout. Project Manager’s Role During Project Close-Out  Ensure that all project deliverables have been completed and.
MAC Committee Update Robert Kondziolka, MAC Chair.
What If I Must Go Beyond a Preliminary Assessment? (the example of a USAID EA under Reg. 216) [DATE][SPEAKERS NAMES]
PTCS Service Provider Review 0 Background RTF assumed responsibility for maintaining PTCS specifications in March 2003  Developed PTCS Service Provider.
Market Meeting Support Susan Munson ERCOT Retail Market Liaison Commercial Operations Subcommittee (COPS) June 10, 2008.
OFFICE OF SCIENCE 1 Closeout Presentation and Final Report Procedures.
Preparing for the Launch Mohammed El- Affendi. Launch Major Tasks  The Launch is performed according to script “LAU1”, table 3.1 in the book (page 39),
OFFICE OF SCIENCE 1 Closeout Presentation and Final Report Procedures.
7/26/2006 Wyatt Merritt 1 DECam Preparations for Critical Decision 2/3a Preparations for CD2 Preparations for CD3a DECam MOUs.
Executive Session Director’s CD-3b Review of the MicroBooNE Project January 18, 2012 Dean Hoffer.
National Commission for Academic Accreditation & Assessment Developmental Reviews at King Saud University and King Faisal University.
July 2008 CPS2 Waiver SDT Technical Workshop for Draft BAL-001-TRE-01 Judith A. James Reliability Standards Manager TRE.
SPS policy – Information Presentation Presentation to ROS June 16, 2004.
The Steps Involved Select a Company who has internationalised or is intending to Age of Internationalisation event Check existing papers about this coy.
Mu2e WGM R. Ray Mu2e Project Manager Sept. 14, 2012.
LBNE Working Group Meeting December 20, :00– 5:00 PM Snake Pit.
Executive Session Director’s CD-1 Review of the LBNE Project September 25, 2012 Jim Yeck.
Executive Session Director’s Progress Review of the NOvA Project August 4-5, 2010 Dean A. Hoffer.
Implementation Strategy July 2002 STANDARDS DEVELOPMENT LIFECYCLE PROCESS ORP Publishes & Maintains 8 Standing Committee Recommends Approval / Disapproval.
1 Accredited Standards Committee C63 ® - EMC Subcommittee 1: Techniques and Developments Zhong Chen SC1 Chair
Mu2e WGM 11/16/2011 R. Ray Mu2e Project manager. Review of the past few months In September it became apparent that the cost of Mu2e was well in excess.
OFFICE OF SCIENCE 1 Closeout Presentation and Final Report Procedures.
1 Identify Preferred Alternative and Finalize Plan Planning Steps 7 & 8.
OFFICE OF SCIENCE 1 Closeout Presentation and Final Report Procedures.
DOE Stanford Site Office Office of Science U.S. Department of Energy 1 U.S. Department of Energy’s Office of Science Office of Science Review of the LCLS.
DUSEL Beamline Working Group Meeting March 09, :00 AM – Snake Pit (WH2NE) By Dean Hoffer - OPMO.
Report of the Technical Subcommittee Mario Bergeron, Technical Subcommittee Chair/NGEC Vice Chair.
Management February 20, Annual Review of the Muon Accelerator Program (MAP) Subcommittee members: Ron Prwivo, Ron Lutha, and Jim Kerby.
AGS RSVP Weekly Meeting P. Pile 6 Jan 2005 AGS RSVP Weekly Meeting 6 Jan 2005 Useful Links: RSVP Project : C-AD.
Project X Working Group Meeting January 15, :00 PM Snake Pit.
“Inspiring our students to reach their full potential.”
Module 7- Evaluation: Quality and Standards. 17/02/20162 Overview of the Module How the evaluation will be done Questions and criteria Methods and techniques.
Closeout Report on the Review Committee (CD-1) for the Long Baseline Neutrino Experiment (LBNE) Project at Fermi National Accelerator Laboratory October.
W. Smith, U. Wisconsin, Upgrade MB, Sept. 9, 2011 Proposal Reviews - 1 Upgrade Peer Review Report Wesley H. Smith U. Wisconsin CMS Upgrade Peer Review.
Adaptive Software Development Process Framework. Version / 21 / 2001Page Project Initiation 2.0 Adaptive Cycle Planning 5.0 Final Q/A and.
Executive Session Director’s Conceptual Design Review of Mu2e Project May 3-5, 2011 Jim Yeck.
Executive Session Director’s Conceptual Design Review of Muon g-2 Project June 5-7, 2013 Jon Kotcher.
OFFICE OF SCIENCE DOE/SC CD-2/3b Review of the Muon to Electron Conversion Experiment (Mu2e) Project Fermi National Accelerator Laboratory February 4,
OFFICE OF SCIENCE DOE/SC CD-3c Review of the Muon to Electron Conversion Experiment (Mu2e) Project Fermi National Accelerator Laboratory June 14-16, 2016.
Director’s Progress Review Closeout Meeting
Updating the Regulation for the JINR Programme Advisory Committees
Implementation Strategy July 2002
Expert Panel on Diversion Planning and Implementation: Meeting #3
Director’s Progress Review Closeout Meeting
JEFFERSON LAB LCLSII CRYOPLANT INSTALLATION PACKAGE DIRECTOR’S PROGRESS REVIEW Welcome and Introduction Stuart Henderson June 1, 2017.
TECHNOLOGY ASSESSMENT
Fort Valley State University
ESHAC #8 Safety Readiness Review Thomas Hansson, ESH
Presentation transcript:

Executive Session Director’s CD-1 Review of the Mu2e Project April 3, 2012 Elaine McCluskey

03-Apr-2012Director's CD-1 Review of the Mu2e Project 2 Agenda for Exec Session Charge to Reviewers DOE O 413.3B Critical Decision Table Subcommittee Agenda Assignments/Write-ups Discussion

Charge Excerpts The Committee is to conduct a Director’s CD-1 Review of the Muon to Electron Conversion Experiment (Mu2e) Project to assess if the project meets the Critical Decision 1 (CD-1) “Approve Alternative Selection & Cost Range” CD-1 requirements as specified in DOE O 413.3B. Additionally this review is a preparation for a planned DOE Independent Project Review/Independent Cost Review (IPR/ICR) scheduled for June 5-7, Apr-2012Director's CD-1 Review of the Mu2e Project 3

Charge Excerpts (Continued) As a cost cutting measure there have been significant changes to the scope of the accelerator and solenoid subsystems and modest changes to the conventional facilities subsystem. The scheme for delivering beam to Mu2e has been significantly simplified and now requires fewer machines and fewer beam manipulations, but the delivered beam power is 1/3 of the original 25 kW. The solenoids have also been simplified. The magnet iron surrounding the Production and Detector Solenoids has been removed, the peak field in the Production Solenoid has been reduced and the coil configuration in the downstream section of the Detector Solenoid has been simplified. The Accelerator and Solenoid subcommittees are asked to evaluate the technical aspects of these subsystems to ensure that they are feasible and still satisfy the performance requirements. In addition to the committee reviewing the changes to the project’s design since the Director’s Impendent Conceptual Design Review conducted on May 03-05, 2011, they are to assess the project’s progress on addressing the relative recommendations from that review. 03-Apr-2012Director's CD-1 Review of the Mu2e Project 4

Charge Excerpts (Continued) The main focus of this review is to look at the project’s cost, schedule, management, and ES&H. The project will present a Cost Range that the review committee is to assess and determine if it is appropriate based … Furthermore, the committee is asked to review and assess the quality of and comment on the additional formal project management documentation required for CD-1 approval. 03-Apr-2012Director's CD-1 Review of the Mu2e Project 5

Charge Excerpts (Continued) Director's CD-1 Review of the Mu2e Project 03-Apr-20126

Charge Excerpts (Continued) Director's CD-1 Review of the Mu2e Project 03-Apr-20127

DOE O 413.3B - Summary of Major Requirements Table 03-Apr-2012Director's CD-1 Review of the Mu2e Project 8

DOE O 413.3B – CD-1 Requirements Table 03-Apr-2012Director's CD-1 Review of the Mu2e Project 9

Subcommittee Reviewer Assignments 03-Apr-2012Director's CD-1 Review of the Mu2e Project 10 Chair: Elaine McCluskey

Agenda Director's CD-1 Review of the Mu2e Project 03-Apr

Agenda (continued) Director's CD-1 Review of the Mu2e Project 03-Apr

Agenda (continued) Director's CD-1 Review of the Mu2e Project 03-Apr

Agenda (continued) Director's CD-1 Review of the Mu2e Project 03-Apr

Executive Session (Subcommittee and Full) Subcommittee and full committee Executive Sessions at the end of each of the first two days. Subcommittee sessions to discuss and formulate potential issues and plan for the next day. At full committee executive session, each subcommittee will report on results of their discussions. Will collect questions at end of day 1 to give to give to the project, which they will respond to the questions after lunch on Wednesday. 03-Apr-2012Director's CD-1 Review of the Mu2e Project 15

Report Outline and Writing Assignments Outline and writing assignments document Rev/2012/04_03/ReportOutlineReviewerAssignments_Mu 2e_CD-1_DR.pdf Rev/2012/04_03/ReportOutlineReviewerAssignments_Mu 2e_CD-1_DR.pdf Writing assignments can be adjusted within subcommittee’s area. Same outline used in Word template to document results of review to present at the closeout. 03-Apr-2012Director's CD-1 Review of the Mu2e Project 16

Reporting Structure Results of the review are to be documented as findings, comments, and recommendations. Answer the charge questions. Answers should be short and precise. Any additional actions required to be completed by the project team to acceptably address the review charge are to be documented as Recommendations Answers to the questions and any recommendations should be presented in writing at a closeout with Mu2e’s and Fermilab’s management. 03-Apr-2012Director's CD-1 Review of the Mu2e Project 17

Findings, Comments, and Recommendations 03-Apr-2012Director's CD-1 Review of the Mu2e Project 18 Findings Comments Recommendations Findings are statements of fact that summarize noteworthy information presented during the review. Comments are judgment statements about the facts presented during the review. The reviewers' comments are based on their experiences and expertise. The comments are to be evaluated by the project team and actions taken as deemed appropriate. Recommendations are statements of actions that should be addressed by the project team. A response to the recommendation is expected and that the actions taken would be reported on during future reviews.

Write-up Write-up template (Review Closeout Presentation Format) is posted on Director’s Review Webpage. 4_03/Template-Closeout_Presentation_Mu2e_2012_04_03.docx 4_03/Template-Closeout_Presentation_Mu2e_2012_04_03.docx There is to be one consolidated write-up for each subcommittee. Answers to Charge question will be consolidated and submitted in whole Write-ups are to be sent to Mary Ellen Tolian at by no later than 9:45 AM on Thursday. Closeout Dry Run to start at 11:00 AM. A final report is to be issued within 2 weeks after the closeout. Director's CD-1 Review of the Mu2e Project 03-Apr

Discussion 03-Apr-2012Director's CD-1 Review of the Mu2e Project 20 Questions and Answers