Concluding Summary WBS1.1.2 SCT Subsystem A. Seiden BNL March 2001.

Slides:



Advertisements
Similar presentations
23-Aug-2005 VELO Production UCD VELO Module Production at Liverpool T. Bowcock.
Advertisements

M. Gilchriese US ATLAS Pixel Meeting July 18-19, 2002 UC Santa Cruz.
US CMS DOE/NSF Review: May 8-10, US CMS Cost & Schedule Mark Reichanadter US CMS Project Engineer DOE/NSF Review 8 May 2001.
L. Greiner 1HFT PXL LBNL F2F – March 14, 2012 STAR HFT The STAR-PXL sensor and electronics Progress report for F2F.
Milestones and Schedule of SVD Construction Markus Friedl (HEPHY Vienna) on behalf of the Belle II SVD Collaboration BPAC October 2012.
US CMS Silicon Tracker : Schedule J. Incandela University of California Santa Barbara US CMS Silicon Tracker Project Manager Fermilab PMG April 9, 2004.
DCal Meeting
US Module and Rod Production Overview and Plan For the US CMS Tracker Group.
Stephen Milton Undulator System 20 April, 2006 LCLS Undulator System Update S. Milton, ANL FAC, April 20 th, 2006.
Slide 1Rod Production presented by Jim Lamb (UCSB)April 9, 2004 Rod Production Rod Production, April , presented by Jim Lamb (UCSB)
Project Management Session 7
Brenna Flaugher Oct. 31 th CDF Meeting1 RunIIb Silicon Project Successful Lehman Review Sept Workshop at LBL 10/23-10/25: Wednesday-Thursday  hybrids.
Effective Methods for Software and Systems Integration
March 20, 2001M. Garcia-Sciveres - US ATLAS DOE/NSF Review1 M. Garcia-Sciveres LBNL & Module Assembly & Module Assembly WBS Hybrids Hybrids WBS.
Common PDR Problems ACES Presentation T. Gregory Guzik March 6, 2003.
DOE/NSF Review of U.S. ATLAS /March 2001 WBS 1.1 Silicon Subsystem M. G. D. Gilchriese Lawrence Berkeley Laboratory.
HFT project Overview and Status October 14, 2010 F.Videbaek BNL.
David M. Lee Forward Vertex Detector Cost, Schedule, and Management Plan Participating Institutions Organizational plan Cost Basis R&D Costs.
ATLAS Endcap Muon System WBS 3.5 Frank Taylor MIT M&O Request FY06 Toronto August 3, 2005 V1.1.
DOE/NSF Review of the U.S. ATLAS Construction Project June 3-4, 2002 WBS 1.1 Silicon Subsystem Abe Seiden UC Santa Cruz.
Slide 1 6-Nov-98PHOBOS Review: Cost & Schedule Cost & Schedule S. Steadman, MIT PHOBOS Cost & Schedule Review Technical Advisory Committee BNL November.
Silicon Inner Layer Sensor PRR, 8 August G. Ginther Update on the D0 Run IIb Silicon Upgrade for the Inner Layer Sensor PRR 8 August 03 George Ginther.
L. Greiner 1IPHC meeting – May 7, 2012 STAR HFT Plans for the next year A short report on HFT/PXL plans for post May 2012 TPC – Time Projection Chamber.
Evaporative Heater Design, qualification and planning M.Olcese PRR SCT off-detector cooling PRR SCT off-detector cooling March March 2005.
HFT face-2-face F.Videbaek Brookhaven National Lab.
Roberto Tenchini CMS FB December 2004 CMS Tracker The Tracker Cost Review - November 2004.
Silicon Meeting July 10, 2003 Module and Stave Production Status James Fast Fermilab.
U.S. Deliverables Cost and Schedule Summary M. G. D. Gilchriese U.S. ATLAS Review Revised Version November 29, 2000.
Abe Seiden December 2003 SCT Week S USA SCT Barrel Module Assembly SCT Week CERN December 2003 Presented by Abe Seiden U.C. Santa Cruz.
Muon trigger upgrades, missing since not aimed towards DOE funding PHENIX upgrades: view presented to DOE R&D $3.5M Construction $16.6M Au-Au p-p 200 Si-Si.
M. Gilchriese Sectors, Rings, Frame Assembly and Installation July 18.
G. Carboni – Muon Meeting – April 2002 Muon Meeting LHC schedule is now official (Council Committee) First protons (Pilot run) delayed to
U.S. Deliverables Cost and Schedule Summary M. G. D. Gilchriese Revised Version December 18, 2000.
ATLAS PIXEL SYSTEM OVERVIEW M. Gilchriese Lawrence Berkeley National Laboratory March 11, 1999.
CMS Si Tracker Project - US CMS Meeting at Riverside – May 19, US CMS Tracker Outer Barrel (TOB) Silicon Project Tim Bolton (for Regina Demina)
L. Greiner 1IPHC meeting – May 7, 2012 STAR HFT Plans for the next year A short report on HFT/PXL plans for post May 2012 TPC – Time Projection Chamber.
1 US Cost & Schedule Summary W. R. Edwards US Project Manager CD-2/3a Review January 8, 2008 BNL.
UCSC August 12, 2008 U.S. Upgrade R&D Meeting: Strip Detector  Seiden.
1 ME1/1 ODMB Production Readiness Review: Schedule and Budget Darien Wood Northeastern University For the ME1/1 Electronics Project.
TOF Preliminary Design and Safety Review Project Management Controls R. L. Brown.
P. Shanahan Nov 15, 2003 Page 1 MINOS WBS 2.3: Electronics, DAQ and Database Status Accomplishments since May review Near Detector Electronics production.
DoE Review June 6, 2000 Cost Estimate  New Cost Estimate u Manpower Costs (Op. SWF) u Equipment Costs (Eq. M&S) u Contingency  Conclusions Mike Tuts.
Brenna Flaugher Sept. 24 th Lehman Review1 Run IIB Silicon Upgrade: Cost and Schedule Lehman Review Sept. 24, 2002 Brenna Flaugher Run IIB Silicon Project.
G. Carboni - Muon Meeting – Muon Meeting 12/ Agenda IntroductionGiovanni (30’) GEM and TDR AddendumWalter (20’) Update on M1 ratesAlessia.
DOE/NSF Review of U.S. ATLAS May 21-23, 2003 CSC Mechanics and Electronics Paul O’Connor Tom Muller BNL May 22, 2003.
US Project Plan for MICE Mark Palmer Peter Garbincius, Alan Bross, Rich Krull Fermilab November 24, 2014.
1 FVTX Monthly/Quarterly Report January 2009 Cost Summary Schedule Summary Current technical status of each WBS item.
Pixel power R&D in Spain F. Arteche Phase II days Phase 2 pixel electronics meeting CERN - May 2015.
ATLAS Pixel Detector September 2002 N. Hartman LBNL 1 Pixel Support Tube: Cost and Production Schedule September 2002.
Strykowsky 1Project Review November 2, 2005 NCSX Project Review November 2, 2005 Cost and Schedule Ron Strykowsky.
M. TYNDEL 1 LHCC Interactions May 2003 ATLAS SCT SCT Production Status ‘Snap-shot’ of the status of the SCT production (May 2003) 1. Barrel Modules 2.
March 25, FVTX Monthly/Quarterly Report June, 2009 Technical Status, Cost & Schedule Melynda Brooks, LANL.
EDM Fast Start Presentation WBS 11 – Assembly and Commissioning Vince Cianciolo, Paul Huffman May 23, 2006.
Executive Committee, Toronto August 3, 2005 TRT Barrel WBS 1.2/3.2 Harold Ogren Indiana University.
Brenna Flaugher, PMG, April 6, 2007 DECam Funding Need Profile (Dec 06) (then yr $, Overhead included) This gave a technically driven schedule resulting.
1 HBD: Responsibilities, Cost and Schedule Itzhak Tserruya EC/DC Meeting, BNL, March 9, 2005.
U.S. ATLAS Project Manager’s Review with the Project Advisory Panel March 21-22, BNL Introduction Howard Gordon.
OsC mtg 15/10/2014 MICE Step IV Alan Grant. Content Step IV – Construction Status – Finances – Schedule – Risks – Summary 2.
Technical Board Summary Alan Bross MICE CM17 CERN February 25, 2007.
Steinar Stapnes, LHCC June The ATLAS inner detector TRT endcap A+B TRT endcap C TRT barrel SCT barrel SCT endcap Pixels uWhole ID sits inside bore.
NCSX Strykowsky 1Independent Project Review (IPR) June 8-9, 2004 NCSX Project Review June 8-9, 2004 Cost, Schedule, and Project Controls Ron Strykowsky.
SVD Status Markus Friedl (HEPHY Vienna) SVD-PXD Göttingen, 25 September 2012.
1 FVTX Quarterly/Monthly Report July 2008 Melynda Brooks, Dave Lee.
CBETA Project ALD’s Cost and Schedule Review February 6, 2017
Jim Fast Pacific Northwest National Laboratory
WBS 1.03 Readout Systems Scope, Cost and Schedule
MicroMegas Mechanical Meeting --- Cern April 2014
CMS Goal of the experiment
TSF Upgrade Project Overview Resources Plans and Timetable
East Hall under construction
Presentation transcript:

Concluding Summary WBS1.1.2 SCT Subsystem A. Seiden BNL March 2001

Conclusions From Last Year 1. Rest of this Fiscal Year: very important to establish that the technical design of the SCT detector is sound through building and simultaneous operation of a of a number of modules. 2. The first 9 months of Fiscal Year 01 will focus on pre-production to establish and quantify our ability to do testing and construction. 3. Starting summer 2001 go into full production. How are we doing on these goals? 2

Verification of Technical Design: Have irradiated and tested six modules, also have run six modules in system test. Will culminate in system test with: 18 barrel modules 6 new modules for PS irradiation These are the target goals prior to hybrid/module FDR in May, followed by integrated circuit PRR in July. 3

Readiness for Testing and Construction Readiness for chip testing: Need to complete wafer tester. This is nearly done. Crucial to reduce test time from 22 hrs/wafer (original CERN tester) to about 5 hours/wafer, our target. Expect to meet target. Will have common wafers tested at all three test locations and with CERN tester to verify that test results are robust. Readiness for module construction: Status, now completing mechanics. Plan is to then construct 20 dummy modules. This will be in 2 groups of 10, using successively more realistic parts. Active modules will also be constructed in parallel. 4

WBS Description PreviousForecast Production June 15July 4 Electronics DesignReadiness Review Complete Pre-production Feb 28March 30 Electronics ProductionFab Hybrid/Module Final April 16May 25 Hybrid DesignDesign Review Pre-production Hybrids June 4Sept 1 Hybrid ProductionAvailable Final Design Review April 16May 25 Module Design Complete Assembly March 5May 1 Module DevelopmentProto Modules Complete Pre-production July 30Oct 30 Module ProductionModule Assembly Short Term Schedule (2001) 5

Some Key Dates: 5/23/01 Complete IC Pre-production Design Verification Needed for hybrid/module FDR May /6/01 Start Full Electronics Production Follows PRR for Front-end Chips 11/23/01 First IC Lots Delivered 12/16/02 Production Testing of Chips Complete 1/7/02 Start Module Production Will Ship 670 Modules 10/13/03 Complete Shipment of Production Modules Details Shown in Line of Balance Plan 6

7

8

ETC01vs ETC00 Comparison Electronics Increase in cost of engineering and materials for IC test system+system test support. Decrease in cost of ICs, more favorable $/Euro rate. Decrease in systems engineering costs. Correction of accounting errors and revised inflation estimate based on new schedule Hybrids Correction of accounting errors and revised inflation estimate based on new schedule Modules Correction of accounting errors and revised inflation estimate based on new schedule. 9

Contingency Management Contingency in original SCT Plan was $988k, all in IC production costs. Cash Contingency left for IC Electronics is about $1M. Cash contingency left for Hybrids and Modules is about $400k. Total Cash contingency appears more than adequate to cover risks for baseline scope. 10

Risk Analysis Items: Parts supplied by other groups (Kapton Hybrids and Baseboards), chips, rate of chip testing and hybrid and module construction. 1. Hybrid (without front-end chips) and baseboard schedules are projected to be well ahead of other construction items. 2. Some possible risk scenarios involving chips and modules: a) FE IC yield is roughly 1/2 that expected and Atmel delivers extra wafers to meet the contractual guarantee of minimum yield or we have a 6 month delay in starting production. Doubling the number of wafers to test or late start should be handled by a modest increase in manpower costs (doubling the manpower would add about $0.1M), there is already an additional probe station (if needed) in the budget and having multiple test systems (ie, various electronics boards) at each site is already in the budget. b) There are additional losses of ICs during handling and assembly and about 15% more wafers have to be procured and tested. Procuring an additional 15% wafers would be about $0.3M. c) We have to roughly double the steady-state rate of module assembly/test, resulting from unexpected delays in delivery of components. Our conclusion is that the current cash contingency for hybrid and module assembly/test (about $0.4M) is probably too low by about $0.1M for this scenario. 11

Baseline Deliverables: 45% of front-end chips, 670 modules. Goal with management contingency allocated is to provide 65% of front-end chips. Rest of SCT has significant cost over-runs in items such as cables and power supplies, which we can’t help with. Therefore important to try to supply the full 65% of the chips. We believe there is a good chance that we can do this (and cover risks) within the current cash contingency for the Silicon Strips. 12