Collaboration Mtg Cotober 11, 2000 Installation Status Opening Remarks Overview, logistics Recent events, status Outlook, concerns Conclusions Jon Kotcher.

Slides:



Advertisements
Similar presentations
H1 SILICON DETECTORS PRESENT STATUS By Wolfgang Lange, DESY Zeuthen.
Advertisements

MICE Collaboration MTG IIT – Feb 2002 The Fiber Tracker Option for MICE Spectrometers The D0 Central Fiber Tracker – Experience and Implications for MICE.
DoE Review June 6-7, 2000 Current Detector Configuration June 6, 2000  Solenoid, Central Preshower installed in central bore  A-layer MDTs installed.
Status of Eric Kajfasz CPPM/Fermilab GDR-Susy, Lyon - 26 novembre 2001.
1 MICE PM Report General Update –Phase I civil engineering –R5.2 in June –Phase II design work –Phase II hardware –A few questions –Schedule, milestones.
All DØ Meeting December 1, 2000 Uncle DØ Needs you!!! Commissioning Status & Plans Jae Yu All DØ Meeting Dec. 1, 2000 What have we been doing? What is.
Atlas SemiConductor Tracker Andrée Robichaud-Véronneau.
1 MICE PM Report Installations to date Future installation work Preparations for Phase Two Target status MICE Video Conference, 22nd May, 2008.
Experimental hall in Japanese mountain site Y. Sugimoto ILD MDI/Integration 1.
SSD Operations Manual March 2014 SSD: 4 th layer of vertex detector Heavy Flavor Tracker Silicon Strip Detector – Operations Manual PXL Inserted from this.
Global Design Effort Detector concept Plenary introductory talk IRENG07 Kurt Krempetz September 17, 2007.
13 January All Experimenters’ MeetingAlan L. Stone - Louisiana Tech University1 Data Taking Statistics Week of 2003 January 6-12 We had to sacrifice.
CMS FPIX Reinstallation/Commissioning Lorenzo Uplegger 4/20/091.
MICE: overview K. Long, 18 March, Contents ► Introduction ► Beam line ► Infrastructure ► MICE steps ► Phase II (comment) ► Conclusions.
CM26 March 2010Slide 1 EMR Status o Intro o Construction o Magnetic shielding o Electronics o Prototype Cosmics test o Schedule Jean-Sebastien Graulich,
Silicon Inner Layer Sensor PRR, 8 August G. Ginther Update on the D0 Run IIb Silicon Upgrade for the Inner Layer Sensor PRR 8 August 03 George Ginther.
Schedule and Work We are moving into a very intensive 4 months with a lot of work to be carried out Electrical services to the devices – after the South.
Director’s Review Dec 1999 Tracker Integration and Installation W. E. Cooper 6 December 1999.
Magnetic Mitigation - Contents l Magnetic Mitigation General l West Wall Compressors l Rack Room 2 l Magnetic Shielding Yoke Jason Tarrant – Integration.
10-25 years of DØ FranceE. Kajfasz1 -France RunII RunIITracking Hard/Soft-ware with.
Ronald Lipton PMG June Layer 0 Status 48 modules, 96 SVX4 readout chips 6-fold symmetry 8 module types different in sensor and analog cable length.
M&O status and program for ATLAS LAr calorimeter R Stroynowski (on vacations)
Status of the MICE Project & Dashboard MICE Project Board 14 th November 2013 Roy Preece.
Dmitri Denisov D0 Weekly Summary: August 18 to August 24  Delivered Luminosity and operating efficiency u Delivered 6.9pb -1 u Recorded 6.0pb -1 (87%)
Santa Cruz Meeting August 12 th 2008 Layout options & Schedule Issues David Lissauer 8/12/2008 1David Lissuaer, Santa Cruz Meeting.
D0 Collab Mtg Feb 7, 2001 D0 Detector: Status for Run 2 Wistful reminiscences Near term: Roll in, detector status, next few weeks Latest from Beams Division.
1 MICE Hall and Infrastructure - Progress since CM18 Chris Nelson MICE CM19 Oct 2007.
Run 12: STAR Status and Schedule Update RHIC Coordination Meeting October 18, 2011 Bill Christie BNL Outline Status update Schedule update and issues Summary.
Fermilab PMG Jan 20, 2000 Reconsideration of the Installation at D0  Overview  Major constraints  Basics of old, new schemes  Some details on each.
Forward Muon Installation and Commissioning Dmitri Denisov Fermilab Director’s review 7/12/1999 Plan Forward muon detectors Mini-drift tubes installation.
L0 Technical Readiness Review-Electronics Installation Linda Bagby L0 Electronics Installation  System Electronics Overview u Low Voltage s Filter.
PMG Meeting February 2000 A Split Central Silicon Tracker W. E. Cooper on Behalf of the D0 Silicon Group 3 February 2000.
D0 Status: 01/14-01/28 u Integrated luminosity s delivered luminosity –week of 01/ pb-1 –week of 01/ pb-1 –luminosity to tape: 40% s major.
All Experimenters MeetingDmitri Denisov Week of July 7 to July 15 Summary  Delivered luminosity and operating efficiency u Delivered: 1.4pb -1 u Recorded:
18 March 2002 All Experimenters’ Meeting Alan L. Stone Louisiana Tech University 1 DØ Status: 03/11 – 03/18 Week integrated luminosity –1.1 pb -1 delivered.
D0 PMG 6/15/00 PMG Agenda June 15, 2000  Overview (Tuts) u Detector status u Reportable milestones u Financial status u Summary  Response to DOE review.
D0 Status: 04/01-04/08 u Week integrated luminosity –1.7pb -1 delivered –1.5pb -1 utilized (88%) –1.1pb -1 global runs u Data collection s global data.
MINERvA Status Report Deborah Harris, Gabe Perdue, Kevin McFarland, Jorge Morfin October 15, 2009.
MICE Project Report Alan Bross (for Paul Drumm). Project Issues ● Key dates: – ISIS Synchrotron start-up scheduled for 1st August ● Shielded area around.
Kurt Krempetz (Director's Review - Dec. 7, 99) 1 Mechanical Infrastructure Kurt Krempetz Introduction Existing Systems New Systems Schedule Manpower Conclusions.
FNAL All Experimenters Meeting January 7, Leslie Groer Columbia UniversityDØ Status 1 DØ Status and Progress Dec 17, 2001 – Jan 7, 2002  Reasonably.
All Experimenters MeetingDmitri Denisov Week of September 9 to September 16 D0 Summary  Delivered luminosity and operating efficiency u Delivered: 4.0pb.
All Experimenters MeetingDmitri Denisov Week of September 2 to September 8 D0 Summary  Delivered luminosity and operating efficiency u Delivered: 3.9pb.
OsC mtg 24/4/2014 OsC mtg Alan Grant. 2 OsC mtg 24/4/ MICE Finances - Forward Look.
FPD STATUS Carlos Avila Uniandes/UTA 1. FPD overview 2. Roman pot and detector status 3. FPD readout integration status 4. Software status 5. Stand-alone.
D. Lincoln Run II MTG May 12, Y2K What will it take to get data out of the CFT?* Don Lincoln CFT Commissioning Czar Fermilab Run II Meeting May 12, Y2K.
DoE Review June 6-7, 2000 Installation and Commissioning of the D0 Detector Overview since last review Organization Current status Installation sequence,
Michel RAYMOND – July 1 st, 2013 Technical Support Activities in PH-ADO-PO Summary of 2013 activities.
D0 PMG February 15, 2001 PMG Agenda February 15, 2001  Overview (Weerts) u Detector status u Reportable milestones u Summary  Operations Organization.
D0 PMG 2/3/00 PMG Agenda Feb 3, 2000  Overview u Project Manager’s Report – Tuts u Fallback options – Weerts  Silicon Support Cylinder Modifications.
Upgrade PO M. Tyndel, MIWG Review plans p1 Nov 1 st, CERN Module integration Review – Decision process  Information will be gathered for each concept.
6 September 2007VELOEddy Jans 0 VELO-installation++ activities September 6, 2007 General items Detector installation plans.
1 Project Infrastructure for steps I-III Tim Hayler, STFC – RAL MICE Collaboration Meeting, RAL, nd October 2008.
Director’s Review Dec 1999 DO Timeline Old Version J F M A M J J A S O N D J F M D Install silicon front-end ICD FPS Lum (L0) CFT install/hookup.
Collaboration Mtg April 14, 2000 DO Timeline J F M A M J J A S O N D J F M D Install silicon front-end ICD FPS Lum (L0) CFT install/hookup 1/2.
D0 PMG 4/19/01 Completed Reportable Milestones MilestoneBaselineActualVar. H Half-Wedge Fabrication 20% Complete 10/15/99 0 w 3 Chip Ladder Fabrication.
All Experimenters MeetingDmitri Denisov Week of July 22 to July 29 D0 Summary  Delivered luminosity and operating efficiency u Delivered: 3.1pb -1 u Live:
ATLAS LAr Forward Calorimeters C. Zeitnitz (Universität Wuppertal) for the ATLAS LAr Community.
OsC mtg 15/10/2014 MICE Step IV Alan Grant. Content Step IV – Construction Status – Finances – Schedule – Risks – Summary 2.
ATLAS Forward Project (AFP) Technical review outcome Review done on (morning) September 2013, see agenda
TDAQ and L1Calo and Chamonix (Personal Impressions) 3 Mar2010 Norman Gee.
Nikhef Scientific Meeting 2000Onne Peters D0 Muon Spectrometer December 14-15, Amsterdam Onne Peters Nikhef Jamboree 2000.
Aras Papadelis, NIKHEF Jaarvergadering 19/12/06 1 Fresh results from the LHCb Vertex Locator test beam Aras Papadelis Ann Van Lysebetten, Anne Keune, Eddy.
Arnd Meyer (RWTH Aachen) Sep 8, 2003Page 1 Integrated Luminosity Total data sample on tape with complete detector > 200pb -1.
21 Mar 2007ALICE - Paul Dauncey1 ALICE CR07: Installation and Commissioning Paul Dauncey Material from: L. Leistam: “ALICE Status” W. Riegler: “Commissioning.
Overview B A B AR L1 DCT Upgrade FDR Masahiro Morii Harvard University Scope of the Project Current Status Schedule  Commissioning.
ELENA installation progress F. Butin / ELENA collaboration.
Vertex Detector Mechanical R&D Design Questions and Issues
Integration and IR Hall
UK CMS Oversight Committee Mtg
Presentation transcript:

Collaboration Mtg Cotober 11, 2000 Installation Status Opening Remarks Overview, logistics Recent events, status Outlook, concerns Conclusions Jon Kotcher Collaboration Meeting October 11, 2000

Collaboration Mtg Cotober 11, 2000 Opening Remarks  Installation/detector evolving very nicely u Huge progress on many fronts s Detectors delivered/mounted s Critical electrical & mechanical infrastructure installed – necessary ingredients s Cabling of all flavors (delicate, tricky) s Electronics (deliveries will remain problem) s Commissioning! (J. Yu) u Focus of hardware upgrade almost completely at DAB (SMT finishing up) s Tight organization, working well together u We are all indebted to excellent support staff s Buy them a cigar, cognac sometime…  Much left to do in time allotted u Some of it detailed work that can only go so quickly without unacceptable amount of risk u Not without concerns for March 1 startup s Will discuss later in talk  Two major “innovations” have opened up our ability to progress rapidly: u Split silicon into two halves u Put large pieces in place on final installation “runways” as early as possible s EF irons on platform, EMC trusses brought down to pit s (Awaited delivery of CFT)

Collaboration Mtg Cotober 11, 2000 Since NIU Workshop  Fiber Tracker installed Thu/Fri, June u Transport from Lab 3, light-tighting in Hi Bay, insertion into bore, transfer to final mounts u Went very smoothly s Used 2 days of the 2 wks we’d allotted u Surveyed into position s CFT well-centered on solenoid, axially and transversely s Solenoid ~ 5/8” south –Critical area, need clearance for CFT/CPS/CFT waveguides –Sophisticated “putty test” in inter-cryostat gap demonstrated ample space – quite definitive u Kudos to D0 Mechanical Group, CFT Group s Completion, installation represents major technical achievement u Starting gun for motion of large pieces back into position…  ECS on center beam Tues, July 11 u Surveyed, repositioned, resurveyed, … s Positioning constraints much tighter for Run 2 (beam pipe, silicon) s Some outstanding issues remain u Cryogenic hookup, recabling of ECS, beryllium beam pipe placed in CFT Barrel 1 s Bubble wrap, PVC, foam, purge

Collaboration Mtg Cotober 11, 2000 Since NIU Workshop  After ECS, platform moved west, end irons picked up, returned 8/4 (one week – faster than anticipated)  Trusses brought down immediately thereafter, completed 8/15  VLPC cryostats installed 8/7, commissioned 8/17 u Working very reliably, without incident u Copper ground straps installed for electronic noise u Handful of production VLPC cassettes installed to do waveguide checkout s Data looks great – another important milestone  Waveguide installation ran into some snags u Spatial constraints btwn calorimeters at outer radius not properly accounted for u 4:1 model made of entire face, incl silicon cable runs u Waveguide running on south face completed this week s A necessary prerequisite for SMT-S installation s Actually will be ahead of schedule u Detailed modeling demonstrated need for more room for waveguides/silicon cables & services s Two inner H-disks will be moved 1.75” away from interaction point u Waveguide checkout continues, much progress s Using kludged stereo boards for front end

Collaboration Mtg Cotober 11, 2000 Since NIU Workshop  All Forward Muon detectors complete (Sep) u Congratulations Dmitri, et al.  Forward Muon A-layer pixels and MDTs mounted u Manipulation, alignment of large pieces – manpower, effort u Mounting of full A-layer major accomplishment s Has typically required iteration – a worry for completion of full system s Final articulating drawbridges not yet in place  C-layer north MDTs installed, being surveyed into position u Lead time for turnaround of survey information can be painful  C-layer north pixel plane assembled on shield wall u Quite impressive (go see it) u Being surveyed, then “hung” into place on truss after rear C-layer MDTs positioned  Expect north truss ready to roll in to Collision Hall mid Oct, south truss mid Nov u Truss installation to Collision Hall begins Nov 13  Accelerator shutdown, warm up, low  retraction  System is progressing, but engineering is proving to be a significant bottleneck  4.5 months ain’t much time…

Collaboration Mtg Cotober 11, 2000 Since NIU Workshop  Calorimeter electronics arriving u Almost 2 full quadrants of upgraded electronics available u Vendors an issue, as always  Purity of liquid argon in dewar 0.4 ppm   test cell, stand-alone test cryostat   measurements being taken now u Ready to be used to fill cryostats s Thanks to G. Sajot & Co.! u Considering filling prior to roll in s Purity monitoring & thermometry (C. Zeitnitz, Mainz), HV, electronics s Manpower, amount of activity an issue s Will be discussed in Yu’s commissioning mtg this week  Beam loss monitors, radiation sensors, Run 1 luminosity counters installed in Collision Hall (NIKHEF, Brown, others) u Readout, feedback to accelerator  Silicon is doing very well u Cabling of SMT-S finishing at SiDet within next two weeks u Expect SMT-S installed early November, SMT-N around Xmas u Noise, error rates on 70k channels at 10% test looks quite good u Talks by Zdrazil, Lehner on Friday

Collaboration Mtg Cotober 11, 2000 Outlook, Concerns  Hardware: u Both SMT half-barrels should be in before roll in s Won’t be necessary to do in Collision Hall u B-layer pixels are in jeopardy s Design of mounting hardware not quite complete s If late, will likely require roll out to complete (crane) s Would be a blow (detectors complete) - pushing very hard u Alignment, positioning accuracy of detector elements far more stringent for Run 2 s Beryllium beam pipe + bellows, silicon, calorimeters… s Difficult problem - much thought, survey u Amount of work in limited space, time  Arrival of electronics for tracking & other systems is very, very late u Interface cards for silicon: start arriving mid-Nov u Adapter cards: partials Nov? u Power supplies for CFT AFE: Feb 12 (partials?) u 8-chip AFE boards for CFT: end Dec (RH), mid- Jan (LH) s 3-4 in hand til then, no partials s 12-chip AFE (stereo, preshowers): Spring u Completion of CAL BLS motherboards: mid-Feb u Level 2 trigger commissioned: 25 April s Alpha boards – smoke hasn’t settled here… u Vendors a canonical problem – much work focusing on expediting these orders, but… u Robust economy is not helping us

Collaboration Mtg Cotober 11, 2000 Outlook, Concerns  Impossible to overstate delicacy of silicon hookup u Final connection of low mass cable must be made one and only one time s Full checkout upstream of adapter card prior to hookup of detector s Detectors damaged, fried with little effort – has been proven in the field by other exp’ts u Electronics will be trickling in u Dressing of inner cables very delicate, convoluted u Properly functioning interlocks an integral part of process (complex system) u Extreme care essential here u Parallel activities a worry s Locked gate at intercryostat gap! u Beginnings of commissioning team in place, needs coalescing u Si hookup will take a while – no corners can be cut s Need access to intercryostat gap, cathedral  Time allotted for detector commissioning time prior to roll in has all but disappeared u Replaced by electronics installation & hookup:  Being synched to accelerator downtimes for electronics installation & hookup in a system of this complexity will severely hamper our readiness for acquiring physics-quality data u Detector, front end, DAQ, online, trigger experts will be absolutely crucial

Collaboration Mtg Cotober 11, 2000 Conclusions  D0 is doing extremely well, an excellent year for the hardware portion of upgrade u Si, CFT, Muon, Cal, infrastructure, online, commissioning  Systems are coming up, behaving as hoped in most cases  Serious, dedicated young people have been, and continue to be, instrumental in getting us there  Much remaining to do, activity in hall escalating organically – OK for moment, but approaching saturation u Spatial/temporal constraints may mean some things cannot get done prior to roll in  Pressure rapidly mounting u Danger now is breaking something, hurting somebody u Taking appropriate care more important than speed!

Collaboration Mtg Cotober 11, 2000

Collaboration Mtg Cotober 11, 2000 Data Taking Position  Clamshells closed, shielding mid-piece extended, EF & calorimeters closed

Collaboration Mtg Cotober 11, 2000 Calorimeter Access  Retraction of shielding mid-piece & EF travel allow access to region between calorimeters u FPS, ICD, LUM, SMT installation & cabling u CFT cabling on face of CC u Collision Hall access – servicing, repairs, etc. EF travel only 42/47” for Run 2

Collaboration Mtg Cotober 11, 2000 Access to B/C layers  Requires scaffolding supported off Collision Hall floor (not shown) u Small (~ 7”) footprint