Earned Value SOS section 3.7 1 541Sp8Jan24ev3. Earned Value Analysis One approach to measuring progress in a software project is to calculate how much.

Slides:



Advertisements
Similar presentations
Connoizor Enabling Performance for Businesses through Software Website: Contact:
Advertisements

 Costs are planned, measured, analyzed and controlled in terms of project activities.  Expenditure for any activity is incurred evenly over the duration.
1 SW Project Management (Planning & Tracking) Dr. Atef Z Ghalwash Faculty of Computers & Information Helwan University.
© The McGraw-Hill Companies, Software Project Management 4th Edition Monitoring and control Chapter 9.
1 Chapter 7 Project Scheduling and Tracking. 2 Write it Down! SoftwareProjectPlan Project Scope EstimatesRisksSchedule Control strategy.
These courseware materials are to be used in conjunction with Software Engineering: A Practitioner’s Approach, 6/e and are provided with permission by.
CSSE Oct.2008 Monitoring and reporting project status Chapter 10, pages
Microsoft Project 2002 Sessions 5-6. Entering Tasks During this first session we will enter a set of tasks that comprise building a shed – data sheet.
Chapter 10: Monitoring and Controlling Change
Monitoring and Controlling
Earned Value Project Management: a powerful tool for software projects
Project Monitoring and Control. Introduction Goal: ensuring that the project is on time and on budget and/or highlight any deviation from the plan Areas.
Earned Value Management
Chapter 10 Project Monitoring and Control
Earned Value Analysis by John Cornman. Introduction “Earned Value Analysis” is an industry standard way to measure a project’s progress, forecast its.
Project Management Methodology Project monitoring and control.
Controlling cost ( lecture + seminar ). Why control cost? To satisfy financial auditors and support data for the government (obligatory). To satisfy the.
1 ev14a Interactive Session 4 u Tuesday, July 17 7pm to 10pm u Build a sqa plan for the dental office software u Assume a 3-person, development team, a.
Construction Accounting & Financial Management, 3/e Steven Peterson © 2013 by Pearson Higher Education, Inc Upper Saddle River, New Jersey All Rights.
1. Earned Value Analysis (EVA) Earned value is a measure of progress enables us to assess the “percent of completeness” of a project using quantitative.
Earned Value JOEL VIRAY TOPICS What is Earned Value Management? –Why do I need it? –How do I do it? Earned Value Reporting Earned.
EARNED VALUE MANAGEMENT (EVM)
Controlling cost 2 ( seminar ). Budget preparation Data collection WBS Cost centres Indirect expenses & the use of hammocks –direct –overhead (indirect)
Earned Value Management System (EVMS). Given: –total budget of $100,000 –12 month effort –produce 20 units Status: –spent to date: $64,000 –time elapsed:
10/19/ :26 AM 1 Project Cost Control. 10/19/ :26 AM 2  Controlling involves making sure that the results achieved are in line with the planned.
1 Project Management – Unit 4 – Part 1 Cost Model ACWP: Actual cost of work performed: Actual costs in performing the work so far. BCWP: Budgeted cost.
Chapter 24 Software Project Scheduling - Introduction - Project scheduling - Task network - Timeline chart - Earned value analysis (Source: Pressman, R.
Project Scheduling 1. Why Are Projects Late? An unrealistic deadline established by someone outside the software development group Changing customer requirements.
Stage III: Project Execution and Control Earned Value Analysis B: Chapter 8: pages B: Chapter 12: the entire chapter.
Lecture 18: Chapter 27 Project Scheduling
Project Cost Con trol. 1.To identify those work types having excessive costs and to give an indication of how serious those overruns are. 2.To forecast.
1 These slides are designed to accompany Software Engineering: A Practitioner’s Approach, 7/e (McGraw-Hill 2009). Slides copyright 2009 by Roger Pressman.
Advanced Project Plan Tracking Lesson 15. Skills Matrix SkillsMatrix Skill Record actual start, finish, and duration values of tasks Enter actual start.
Presented by Tim Pyron Author: Que’s Special Edition Using Microsoft Project 2002 Que’s Special Edition Using Microsoft Project 2000 SAMS Teach Yourself.
UU Master Class Earned Value 17 July Earned Value Contents What is Earned Value / Earned Value Analysis Why and where is it used A brief history.
Ev3 1 In House Software Development:… Verner, etal IEEE Software, Jan?feb 2005.
Introduction To Earned Value November 14, Definition Earned Value is a method for measuring project performance. It compares the amount of work.
Earned Value Analysis Tracking Project Progress. Introduction | Components | Project Scenario | Values | Calculations | Forecasts | Summary l What Is.
Where Module 04 : Knowing Where the Project Is 1.
Project Management Information System What?? Objective: –Record & report relevant information and status of various components of project –Highlight the.
1 Earned value analysis Planned value (PV) or Budgeted cost of work scheduled (BCWS) – original estimate of the effort/cost to complete a task (compare.
Schedule Control (Earned Value)
Project Cost Con trol. 1.To identify those work types having excessive costs and to give an indication of how serious those overruns are. 2.To forecast.
Agenda ‒ Cost Management ‒ Cost Budgeting ‒ Cost Control Learning Goals 1.Cost Control 2.Earned Value Management.
Project Management 1 Project Control. Project Management 2 Topics Project Control Status Reporting Earned Value Analysis.
Earned Value Management
Measuring Progress HNC Project Management. Measuring Schedule Performance Break project tasks up into small work units. Work units that are too large.
Performance Measurement Baseline Contract Price (Project Price)
Earned Value Analysis by Miles M. Hamby, PhD Copyright©2014 Miles M
Project Monitoring
TOPIC-8B- PROJECT COST CONTROL
PROJECT MANAGEMENT AND CONTROL
CHAPTER:7 Project Cost Management
Earned Value Management
Chapter 34 Project Scheduling
Earned Value Management
Work Packages / Deliverables Completed
Progress and Performance Measurement and Evaluation
Earned Value - What is it
Earned Value Analysis It is a continuous comparison between the plan of the project data and the actual data. Budgeted and Committed Cost: Variance = Budgeted.
An Introduction to Earned Value Performance Measurement
Earned Value Measures Planned Value (PV) Earned Value (EV)
ENGINEERING MANAGEMENT (GE 404)
فرآيند كنترل پروژه.
Earned Value Management
Project Management Life Cycle
Monitoring and Controlling
Chapter 27 Project Scheduling
Chapter 34 Project Scheduling
Earned Value $$$.
Presentation transcript:

Earned Value SOS section Sp8Jan24ev3

Earned Value Analysis One approach to measuring progress in a software project is to calculate how much has been accomplished. This is called earned value analysis. It is basically the percentage of the estimated time that has been completed. Additional measures can be calculated. Although this is based on estimated effort, it could be based on any quantity that can be estimated and is related to progress Sp8Jan24ev3

Basic Measures - 1 Budgeted Cost of Work (BCW): the estimated effort for each work task. Budgeted Cost of Work Scheduled (BCWS): the sum of the estimated effort for each work task that was scheduled to be completed by the specified time. Budget at Completion (BAC): the total of the BCWS and thus the estimate of the total effort for the project 3 541Sp8Jan24ev3

Basic Measures - 2 Planned Value (PV): the percentage of the total estimated effort that is assigned to a particular work task. PV = BCW/BAC Budgeted Cost of Work Performed (BCWP): the sum of the estimated efforts for the work tasks that have been completed by the specified time. Actual Cost of Work Performed (ACWP): the sum of the actual efforts for the work tasks that have been completed 4 541Sp8Jan24ev3

Progress Measures Earned Value(EV)= BCWP/BAC the sum of the PV’s for all completed work tasks Schedule Performance Index (SPI) = BCWP/BCWS Schedule Variance (SV) = BCWP – BCWS Cost Performance Index (CPI) = BCWP/ACWP Cost Variance (CV) = BCWP – ACWP 5 541Sp8Jan24ev3

Example – as of 4/1/08 taskEst effort Actual effort Est Comp Date Actual Date Comp /25/082/1/ /15/ /15/ /15/084/1/ /1/ /01/08

For next Tuesday – 1 or 2 people u Use the data from slide 6. Assume that the rest of the tasks finish 1 month late. u Calculate EV, SPI, SV, CPI, and CV at half month intervals from Jan 1 through the finish of the project. u Plot the values as line graphs. Turn in hard copy of the spreadsheet and the graphs. u 25 points 7 541Sp8Jan24ev3

Tuesday, Jan 29 – post mortem u Read two articles –Anreas Birk,”Postmortem: Never Leave a Project without It” –June Vernier “In-House Software Development: What Project Management Practices Lead to Success” –Making Meaning for each – upload together on Monday 8 541Sp8Jan24ev3