1 of 24 Earned Value Management.

Slides:



Advertisements
Similar presentations
Project Cost Management
Advertisements

Connoizor Enabling Performance for Businesses through Software Website: Contact:
©2003 Rolls-Royce plc The information in this document is the property of Rolls-Royce plc and may not be copied or communicated to a third party, or used.
Budget Management. 57 Budget Management Budget Development Good scheduling skills and abilities Understanding of the project scope Well developed WBS.
1 SW Project Management (Planning & Tracking) Dr. Atef Z Ghalwash Faculty of Computers & Information Helwan University.
© The McGraw-Hill Companies, Software Project Management 4th Edition Monitoring and control Chapter 9.
Monitoring and Control Earned Value Management (EVM)
Project Cost Management Sections of this presentation were adapted from A Guide to the Project Management Body of Knowledge 4 th Edition, Project Management.
CSSE Oct.2008 Monitoring and reporting project status Chapter 10, pages
Irwin/McGraw-Hill ©The McGraw-Hill Companies, 2000 Chapter 13 Progress and Performance Measurement and Evaluation.
Chapter 10: Monitoring and Controlling Change
Section 4.0 Project Implementation. Factors that Ensure Success  Update the project plan  Stay within scope  Authorized change implementation  Providing.
Software Project Management
Project Monitoring and Control. Introduction Goal: ensuring that the project is on time and on budget and/or highlight any deviation from the plan Areas.
Project Cost Management J.-S. Chou, P.E., Ph.D.. 2 Learning Objectives  Explain basic project cost management principles, concepts, and terms.  Discuss.
Where We Are Now. Where We Are Now Structure of a Project Monitoring Information System Creating a project monitoring system involves determining:
Project Cost Management
Using Earned Value Management System (EVMS) Briefing for ATC Engineering & Test Division (ACT-200) Managers and Leads.
Project Management Process Project Description Team Mission/ Assignment Major Milestones Boundaries Team Identification Measures of Success Roles & Responsibilities.
Earned Value Management
Progress and Performance Measurement and Evaluation CHAPTER THIRTEEN Student Version Copyright © 2011 by The McGraw-Hill Companies, Inc. All rights reserved.
Chapter 10 Project Monitoring and Control
Project Management 6e..
EARNED VALUE MANAGEMENT SYSTEM A Project Performance Tool
This work is licensed under a Creative Commons Attribution 3.0 Unported LicenseCreative Commons Attribution 3.0 Unported License (CC-BY). Project Management.
PowerPoint Presentation by Charlie Cook THE MANAGERIAL PROCESS Clifford F. Gray Eric W. Larson Progress and Performance Measurement and Evaluation Chapter.
Project Monitoring and Control. Monitoring – collecting, recording, and reporting information concerning project performance that project manger and others.
Project Management Methodology Project monitoring and control.
Progress and Performance Measurement and Evaluation CHAPTER THIRTEEN Student Version Copyright © 2011 by The McGraw-Hill Companies, Inc. All rights reserved.
Chapter 13: Progress and Performance Measurement and Evaluation
PPMT CE-408T Engr. Faisal ur Rehman CED N-W.F.P UET P.
PowerPoint Presentation by Charlie Cook Copyright © 2006 The McGraw-Hill Companies. All rights reserved. THE MANAGERIAL PROCESS Clifford F. Gray Eric W.
Software Project Management Lecture # 7. What are we studying today? Chapter 24 - Project Scheduling  Effort distribution  Defining task set for the.
Software Project Management (SPM)
Microsoft Project Association Building an EV System using MS Project (and Excel) Kirsty C. McLean, MBA, PMP Project Controller, Photonics Division General.
9-1 Project Management from Simple to Complex. 9-2 This work is licensed under the Creative Commons Attribution-Noncommercial-Share Alike 3.0 Unported.
EARNED VALUE MANAGEMENT (EVM)
Project Management Part 6 Project Control. Part 6 - Project Control2 Topic Outline: Project Control Project control steps Measuring and monitoring system.
1 Project Management – Unit 4 – Part 1 Cost Model ACWP: Actual cost of work performed: Actual costs in performing the work so far. BCWP: Budgeted cost.
Project Cost Management
PowerPoint Presentation by Charlie Cook Copyright © 2006 The McGraw-Hill Companies. All rights reserved. THE MANAGERIAL PROCESS Clifford F. Gray Eric W.
Project Management 6e..
UU Master Class Earned Value 17 July Earned Value Contents What is Earned Value / Earned Value Analysis Why and where is it used A brief history.
Evaluating EVM January 13, EVM Issues and Opportunities ▪ EVM Basics ▪ EVM Issues ▪ EVM ETC and EAC Calculations ▪ EVM Cost and Schedule Value Calculations.
Report Performance Monitor & Control Risk Administer Procurement MONITORING & CONTROLLING PROCESS.
Introduction To Earned Value November 14, Definition Earned Value is a method for measuring project performance. It compares the amount of work.
Earned Value Analysis Tracking Project Progress. Introduction | Components | Project Scenario | Values | Calculations | Forecasts | Summary l What Is.
Where Module 04 : Knowing Where the Project Is 1.
EVM – Do You Really Know What the Numbers Mean? Booz | Allen |Hamilton Seth Huckabee EVP, PMP, PMI-SP.
1 Understanding Earned Value in Under an Hour Breakout Session # A11 Name: Wayne Brantley, MS Ed, PMP, ITIL Senior Director of Professional Education.
0 Earned Value Management. 1  What is it?  Where did it come from?  What’s so special about it?  How do you do it?  What is an EVMS?
Information Technology Project Management, Seventh Edition Note: See the text itself for full citations.
Agenda ‒ Cost Management ‒ Cost Budgeting ‒ Cost Control Learning Goals 1.Cost Control 2.Earned Value Management.
Project Management 1 Project Control. Project Management 2 Topics Project Control Status Reporting Earned Value Analysis.
Project Cost Management
“PMP® Exam Prep” Earned Value Management
Project Communication, Tracking, and Reporting
5. Cost resources & PLAN DURATION
Earned Value Management
Earned Value Management
Earned Value - What is it
Project Scope Management
Implementing EV in IT A Three Step Approach John Chapman Touchstone Ltd
Earned Value Measures Planned Value (PV) Earned Value (EV)
Earned Value Management
5. Cost resources & PLAN DURATION
5. Project PLAN & cost estimation
Project Cost Management
Managing Project Work, Scope, Schedules, and Cost
Where We Are Now. Where We Are Now Structure of a Project Monitoring Information System Creating a project monitoring system involves determining:
Presentation transcript:

1 of 24 Earned Value Management

2 of 24 Earned Value Management (EVM) originated at the US DoD in 1967 with their ‘instruction ’, mandating an early form of EVM for larger contracts. This was to prevent projects going so far before serious problems were apparent that too much had already been spent to contemplate cancelation. “EVM is a project control process based on a structured approach to planning, cost collection and performance measurement. EVM facilitates the integration of project scope, time and cost objectives and the establishment of a baseline plan for performance measurement.” APM Competence Framework EVM uses the Planned Value, the Actual Cost and the Earned Value to track performance – and show what has been achieved for the money spent to date What is Earned Value Management?

3 of 24 Why Use EVM? Improves the predictability of projects An early indicator of problems A structured approach to planning and the data to enable performance management Objectively ties delivered value to spend, comparing that with what was planned Forecasts the impact of corrective actions

4 of 24 US Standard ANSI EIA 748-C [ ] Earned Value Management Systems  Australian Standard  AS 4817 [2006] Project Performance Using Earned Value   Association for Project Management Earned Value Management Handbook [ ]   Earned Value Management APM Guidelines, 2 nd edition [2008]   Interfacing Risk and Earned Value Management [2008]   The Earned Value Management Compass [2010 ]   Project Management Institute Practice Standard for Earned Value Management [2011]   UK Government Ministry of Defence Acquisition System Guidance: Earned Value Management [v3.2.16] US Government Department of Defence: Earned Value Management Implementation Guide [2006]   NASA EVM Implementation Handbook [ ]   and EVM Reference Card   Earned Value Management Best Practice

5 of 24 Project Tracking using only Actual Cost Before EVM, projects were tracked by looking at actual spend and comparing with planned spend Compare Actual Cost (40) with Planned Cost (80) at time Now (4); what is the project status? – Is the project under-spent? Or over-spent? – Is the project on schedule? Or behind schedule? Status depends on how much of the planned work is complete for the money spent – If all the work planned to time now is complete Status: on schedule but 50% under-spent – If half the work planned to time now is complete Status: on budget but 100% behind schedule – If a quarter of the work planned to time now is complete Status: 200% over-spent and 400% behind schedule – If all the work planned is complete Status: 80% under-spent and 60% ahead of schedule Status cannot be known using Actual Cost alone Now 40 80

6 of 24 EVM Process Define What work needs to be done and who will do it, defined in the Statement of Work (SoW) Product Breakdown Structure > Work Breakdown Structure > Work Packages > Tasks or PBS > WBS > WP > Tasks Use EVM at the WBS level, sometimes at the WP level, hardly ever at the task level minimise the overhead whilst maximising the value of using EVM Each WBS element, made up of a number of WPs, is a Control Account Each Control Account has a Control Account Manager - on smaller projects the PM or a Team Leader Plan How and when the work will be done, at what cost A PERT or Gantt chart with estimates for the cost per task as hours x hourly rate Resource level so the resources do not exceed those available at any given time The sum cost of all the work will give us the Planned Value, or baseline for the project Monitor & Control Manage delivery performance during the project, against the baseline At any point in time:how much have we delivered? (the Earned Value) how much had we planned to deliver? (the Planned Value) what are the variances? are any corrective actions indicated? DefinePlan Monitor & Control

7 of 24 Choose an Appropriate Measure of Progress x/y: 0/100, 50/50, User Defined Percentage (10/90, 20/80…) The EV is x% at the start of the WP and a further y% at the end when the WP is complete. If the work falls within a single reporting period, 0/100 may be appropriate. If the work spans two reporting periods, 50/50 or a user defined percentage may be appropriate. Milestones Setup milestones at the start of the project. Assign each milestone a proportion of the budget. As milestones are completed, the EV is that part of the budget assigned to them. If the work spans multiple reporting periods, this method may be appropriate. Percent Complete EV depends on the percentage completion of the WP. It can be difficult to agree an objective measure of percent complete… Equivalent Units EV = WP budget x the number of tasks completed / by the number of tasks to be done. Level of Effort EV is set such that 1 hour effort = 1 hour EV. Appropriate where there is no specific deliverable result, e.g. administration. Apportioned Effort EV is equal to the EV on another directly related WP, e.g. if a Technical Authority works on two Control Accounts and one CA has 50% EV, the other CA is also considered to have 50% EV. Individual Judgement Expert judgement may have to be used for complex work where no other method is applicable.

8 of 24 EVM Terms and Formulae Basic Measures Planned Value (PV), Planned Cost, Budget, Budgeted Cost of the Work Scheduled (BCWS) The sum of all budgets for the planned work, to a point in time. Budget At Completion (BAC) The total budget for completing the project. Note that contingency is usually excluded. Planned Duration The planned duration of the project. Actual Cost (AC), Actual Cost of the Work Performed (ACWP) The sum of cost incurred in completing the work to a point in time. Earned Value (EV), Budgeted Cost of the Work Performed (BCWP) The sum of all budgets that were planned to complete the work that has actually been completed, at a point in time, or what the completed work should have cost. Variances (good: positive values, possibly bad: negative values) Schedule Variance (SV) = BCWP-BCWS or EV-PV The difference between planned achievement and actual achievement, at a point in time. Can be measured in both cost and time. Cost Variance (CV) = BCWP-ACWP or EV-AC The difference between planned achievement and actual spend to achieve this, at a point in time.

9 of 24 EVM Terms and Formulae II

10 of 24 EVM Chart Budget At Completion BAC Cost Variance CV Schedule Variance SV Schedule Variance (time) Now Planned Value PV Earned Value EV Actual Cost AC Planned Duration Time Now Estimate At Completion EAC Forecast Schedule Variance (time) Estimated Duration ED

11 of 24 EVM Example Status at Time Now (4) Basic Measures BAC = 200, Planned Duration = 10 PV = 80, AC = 80, EV = 80 Variances SV = 0, CV = 0 Performance Indices SPI = 1.0, CPI = 1.0, TCPI (BAC) = 1.0 Calculated Estimates EAC = 200, ETC = 120, Estimated Duration = 10 Summary On schedule, on budget Now 80 On Time On Budget On BAC

12 of 24 EVM Example II Status at Time Now (4) Basic Measures BAC = 200, Planned Duration = 10 PV = 80, AC = 40, EV = 40 Variances SV = -40, CV = 0 Performance Indices SPI = 0.5, CPI = 1.0, TCPI (BAC) = 1.0 Calculated Estimates EAC = 200, ETC = 160, Estimated Duration = 20 Summary Behind schedule, on budget Now Now 0.5 Late On Budget On BAC SV = EV - PV = = -40, i.e. Late Forecast Schedule Slip = 10

13 of 24 EVM Example III Status at Time Now (4) Basic Measures BAC = 200, Planned Duration = 10 PV = 80, AC = 114, EV = 114 Variances SV = 34, CV = 0 Performance Indices SPI = 1.4, CPI = 1.0, TCPI (BAC) = 1.0 Calculated Estimates EAC = 200, ETC = 86, Estimated Duration = 7 Summary Ahead of schedule, on budget Now Now Early On Budget On BAC Forecast Schedule Gain = 3 SV = EV - PV = = 34, i.e. Early

14 of 24 EVM Example IV Status at Time Now (4) Basic Measures BAC = 200, Planned Duration = 10 PV = 80, AC = 100, EV = 80 Variances SV = 0, CV = -20 Performance Indices SPI = 1.0, CPI = 0.8, TCPI (BAC) = 1.2 Calculated Estimates EAC = 250, ETC = 150, Estimated Duration = 10 Summary On schedule, over budget Now Now On Time Over Budget Above BAC Forecast Over Spend = 50 CV = EV - AC = = -20, i.e. Over Spent

15 of 24 EVM Example V Status at Time Now (4) Basic Measures BAC = 200, Planned Duration = 10 PV = 80, AC = 40, EV = 80 Variances SV = 0, CV = 40 Performance Indices SPI = 1.0, CPI = 2.0, TCPI (BAC) = 0.75 Calculated Estimates EAC = 100, ETC = 60, Estimated Duration = 10 Summary On schedule, under budget Now Now On Time Under Budget Below BAC Forecast Under Spend = 100 CV = EV - AC = = 40, i.e. Under Spent

16 of 24 EVM Example VI Status at Time Now (4) Basic Measures BAC = 200, Planned Duration = 10 PV = 80, AC = 80, EV = 40 Variances SV = -40, CV = -40 Performance Indices SPI = 0.5, CPI = 0.5, TCPI (BAC) = 1.3 Calculated Estimates EAC = 400, ETC = 320, Estimated Duration = 20 Summary Behind schedule, over budget Now Now Late Over Budget Above BAC Forecast Schedule Slip = 10 Forecast Over Spend = 200 CV = EV - AC = = -40, i.e. Over Spent SV = EV - PV = = -40, i.e. Late

17 of 24 EVM Example VII Status at Time Now (4) Basic Measures BAC = 200, Planned Duration = 10 PV = 80, AC = 80, EV = 120 Variances SV = 40, CV = 40 Performance Indices SPI = 1.5, CPI = 1.5, TCPI (BAC) = 0.67 Calculated Estimates EAC = 133, ETC = 53, Estimated Duration = 6.7 Summary Ahead of schedule, under budget Now Now Early Under Budget Below BAC Forecast Schedule Gain = 3.3 Forecast Under Spend = 67 SV = EV - PV = = 40, i.e. Early CV = EV - AC = = 40, i.e. Under Spent

18 of 24 Corrective Actions Resource Problems – Not enough resources? – Wrong or insufficiently skilled resources? Training needed? Replacement needed? Work Problems – More difficult than anticipated? – More rework than anticipated? Need technical help? Assumption or Dependency Problems – Incorrect assumption(s)? – Missing in-feeds? Data Problems – Correct & consistent data? e.g. are Actuals for the same time as Planned – Appropriate method of objectively assessing EV?

19 of 24 EVM Bulls Eye Chart To make reporting easier, variance thresholds can be agreed at the start of a project. Variances within these thresholds can then be logged but with no explanation needed. Variances might be presented using a Bulls Eye Chart. CPI and SPI are plotted each reporting period (weekly, monthly or quarterly). CPI < 1, SPI < 1 Over Spent, Late CPI 1 Over Spent, Early CPI > 1, SPI < 1 Under Spent, Late CPI > 1, SPI > 1 Under Spent, Early

20 of 24 Risk Management & Change Control At the start of a project, the Planned Value does not include all the risk contingency as risk events are uncertain (i.e. have a probability less than 100%) Risk mitigation and enhancement tasks will be included in the PV As the project progresses it will likely be necessary to add or modify tasks – either adding further risk mitigations or enhancements, or because of scope change – These should update the baseline PV – in order to maintain the validity of the EVM data – This can be done within standard planning tools with care; or specialist tools are available

21 of 24 Earned Schedule EVM Example II (slide 12) using SPI (time) in place of SPI First proposed by Walt Lipke in 2003 Now Late On Budget On BAC 0.69

22 of 24 Cautions & Tips SPI > 1 does not always mean the project is ahead of schedule. Schedule performance should be assessed looking at the project plan, in particular the critical path. If more non-critical path work is done than planned at a given point, this could lead to SPI > 1, but this will not shorten the critical path! Take care that materials and expenses don’t incorrectly skew EVM. Use EVM to trigger appropriate action. Setting hares running on seeing CPI, SPI less than 1 may be neither necessary or helpful. EVM will not help a project with inadequate requirements, WBS or change control, i.e. EVM is not a substitute for general project management best practice. Remember that all measures of project progress are estimates.

23 of 24 Summary Earned Value Management offers an objective way of visualising project performance, providing early indication of problems as well as a view on the impact of corrective actions. It is an indispensable project management tool for all but the smallest projects. EVM is not complex to implement. Like any tool, EVM is open to misuse in the wrong hands. In the competent hands EVM is the most efficient means of assessing project progress, providing a narrative for progress reporting and is highly recommended.

24 of 24 In my board role I led a team of 22 professional Project Managers and 5 Quality Engineers, and ensured Roke’s £79M project portfolio delivered better than budget profit. I ran a virtual PMO and created the Roke Engineering Process, REP, also managing the engineering tools to support it. I created a project management competency framework, the PM Excellence Programme, which achieved APM corporate accreditation, scoring 24 out of a possible 25 points in the APM assessment.APM corporate accreditation I chaired a quarterly PM forum which shared best practice and built a supportive PM community – seven of the project managers I coached achieved APM RPP, five gained PQ, and all passed APMP. Together, these investments in PM professionalism led to a turn-around and annual improvement in project results across a typical portfolio of 400 projects a year and delivered an above budget performance in five consecutive years with profits totalling £7.9M above budget. I am a passionate advocate of PM professionalism, a Fellow of the APM and the IET, and author of articles published in Project and PM Today. After 4 years as an electronics engineer for Siemens, achieving Chartered Engineer, I moved into project management for 14 years, at Siemens and Roke Manor Research. At Roke, my ability to successfully deliver the most challenging whole lifecycle product development projects on time and under budget led to a role as Projects Director and board member for 6 years. In 2013 I went back to hands-on project management, taking a Programme Director role at Cambridge Consultants, in the Cambridge Science Park. Author Profile