1 Developing Scope of Work, Budgets and Schedules for the OTIA III State Bridge Delivery Program Raymond Mabey, Deputy Program Manager, ODOT Lynn Iaquinta,

Slides:



Advertisements
Similar presentations
Project Cycle Management
Advertisements

Metro Muncipal Agreement Program
Project Development Process (PDP) Structures. PDP – Three Project Levels Major Project ~ 14 Steps Major Project ~ 14 Steps Minor Project ~ 10 Steps Minor.
DISTRICT FIVE CONSTRUCTION CONTRACT ADMINISTRATION UPDATE TRAINING Submission of Working Schedule Specification SP A.
ODOT’s Public Involvement Process PI and the Project Development Process Minimum PI Requirements.
CMGC Contracting at UDOT Program, Projects & Lessons Learned
State of Indiana Business One Stop (BOS) Program Roadmap Updated June 6, 2013 RFI ATTACHMENT D.
Managing Evaluations for Consistently High Quality American Evaluation Association Annual Conference Molly Hageboeck.
Phases of Plan Development – Leading to High Quality Plans ACEC/ODOT Conference April 15, 2008 Steve Cooley, PE, PLS ODOT Region 2 Technical Center Manager.
1 C E T A S Range of Alternatives Presentation Date Project Name Project location (city, county) ODOT Key Number:
Project Prospectus and Design Acceptance Package ( and a little more) Alan Lively Project Delivery Specialist January 30, 2009.
Procurement and Tendering Presentation to [NAME OF CLIENT] [YOUR NAME] [DATE]
LANE CLOSURE CHARTS CHART DEVELOPMENT AND DELAY DAMAGES (District 3) OBJECTIVE To become familiar with the lane closure chart development process.
Federal Transit Administration New Starts Project Development Process
Delivery Methodology.
10.5 Report Performance The process of collecting and distributing performance information, including status reports, progress measurements and forecasts.
1 ®  Overview Benefits of a Good Construction Schedule Baseline Schedule Development Schedule Updating and Maintenance Managing Project Changes USACE.
Lecture(3) Instructor : Dr. Abed Al-Majed Nassar
Pre-Project Planning Lessons from the Construction Industry Institute Construction Industry Institute Michael Davis, P. Eng, PMP Ontario Power Generation.
The R&M Task Group mandate is to: Develop specific recommendations on how social housing project reporting and monitoring could be improved and made more.
Project Delivery Overview June 2015 Final PD Training FMD WUSM 6/15/15 1.
Project Management: Madness or Mayhem
Public Works Contracting Marsha Reilly Office of Program Research House of Representatives recommended.
Intersection & Interchange Geometrics (IIG) Innovative Design Considerations for All Users Module 8 Intersection- Interchange Evaluation Process.
IDM Chapter 104 Utility Coordination Joe Gundersen Senior Utility Engineer, INDOT August 21, 2014.
26-FEB Project Controls Requirement ABP Update Through January 19, 2010 the MassDOT Accelerated Bridge Program has advertised 73 construction projects.
Commissioning of Fire Protection and Life Safety Systems Presented by: Charles Kilfoil Bechtel National Waste Treatment Plant Richland WA.
Capital Improvement Program. During the Annual Strategic Action Plan (SAP) evaluation, long-term needs and priorities are identified by City Council Capital.
Water Supply Planning Initiative State Water Commission November 22, 2004.
A New Paradigm for Utility Coordination Kenny Franklin INDOT Director of Utilities and Railroads.
HIGHWAY/UTILITY PROGRAM OVERVIEW ROADWAY CONFERENCE APRIL 20, 2009.
Project Scoping Fundamentals Alan Lively Project Delivery Specialist Local Government Section April 6, 2010.
PROJECT SCOPING FOR LOCAL AGENCY FEDERAL AID PROJECTS.
SacProNet An Overview of Project Management Techniques.
Presentation Topics Oregon Transportation Investment Acts (OTIA) Goals of Statewide Traffic Mobility Program Focus of ODOT’s Mobility Approaches Results.
Local Government Section Welcome Marty Andersen ODOT Local Government Section 355 Capitol Street NE, Rm. 326 Salem, Oregon Ph:
OREGON DEPARTMENT OF TRANSPORTATION Practical Design Decision Matrix.
Enosburg BRO 1448(40) Bridge 48 on TH 2 Over the Tyler Branch Public Information Meeting.
Develop Project Charter
Implementation Strategy July 2002 STANDARDS DEVELOPMENT LIFECYCLE PROCESS ORP Publishes & Maintains 8 Standing Committee Recommends Approval / Disapproval.
METROPOLITAN TRANSPORTATION COMMISSION Key Steps to Delivering Project 1.Lead agency submits final project scope, budget and schedule to MTC 2.MTC.
Texas Department of Transportation Corpus Christi District Harbor Bridge Project U.S. 181 (Harbor Bridge)/SH 286 (Crosstown Expressway) Citizens Advisory.
University of Minnesota Internal\External Sales “The Internal Sales Review Process” An Overview of What Happens During the Review.
Contractor Alternate Design Serving the Public’s Best Interest.
Project Development Process. ODOT’ PDP A project management and transportation decision-making tool. Developing the detail to the level necessary to make.
Public Involvement. Why? Who Cares? –What we do matters to the public –Effective PI enables proactive input and enhances the decision- making process.
Proposition 1 Workshop: the Grant Application Process July 2015.
SOLUTION What kind of plan do we need? How will we know if the work is on track to be done? How quickly can we get this done? How long will this work take.
Module 5 Session 5.2 Visual 1 Module 5 Refining Objectives, Scope, and Other Project Parameters Session 5.2 Reviewing the PAR and refining key project.
Project Management Basics
1 Waste Discharge Authorization Application - British Columbia WG6 Application Process WG Document Review presented by Helga Harlander October x, 2008.
Project Management Processes for a Project
OTC Pres Project Del P5 12/08 Page 1 Project Delivery Performance Improvement Report to the Oregon Transportation Commission Jeff Gower, State Construction.
OTC Pres: Bid & Award Phase 4 12/08 Page 1 Project Delivery Performance Improvement Report to the Oregon Transportation Commission Eryca McCartin, Office.
Project Delivery Performance Improvement Report to the Oregon Transportation Commission Hal Gard, Technical Services, Geo-Environmental Dee Jones, Technical.
BSBPMG501A Manage Project Integrative Processes Manage Project Integrative Processes Project Integration Processes – Part 2 Diploma of Project Management.
Office of Major Project Development (OMPD) Overview November 2015.
Collaborating for Quality Quality Assurance (QA) & Quality Control (QC) in the Accelerator Project (ACCSYS) Matthew Conlon ACCSYS QA/QC
Dave Adamson Design Network launched 2 years ago Had many good ideas Discipline tracks Activity ownership Milestone meetings Promised “Not Static”
SCHEDULE MANAGEMENT MODULE 8. Required by Specification City/Caltrans Level 1 schedule – simple Less than $1 million, less than 100 working days Advanced.
4.4 Monitor and Control Project Work
Construction Oversight
FOR LOCAL AGENCY FEDERAL AID PROJECTS
FOR LOCAL AGENCY FEDERAL AID PROJECTS
Project Development Quality Program QA/QC – What does ODOT need?
CBP Biennial Strategy Review System
CIS12-3 IT Project Management
Managing Project Work, Scope, Schedules, and Cost
Construction Management Services April 16, 2018
TOTAL COST CONTROL ON CONSTRUCTION PROJECTS
Presentation transcript:

1 Developing Scope of Work, Budgets and Schedules for the OTIA III State Bridge Delivery Program Raymond Mabey, Deputy Program Manager, ODOT Lynn Iaquinta, Engineering Manager, OBDP

2 Summary of Process Developing Program Scope, Budget and Schedules Determining Project Level Details including Project Development Process Reporting Progress Monitoring and Maintaining Communications and Issue Resolution

3 Purpose of the Funding Program Goals and Objectives –Fulfill the Goals of the budget note  Stimulate the economy  Employ efficient and cost-effective delivery practices  Maintain freight mobility / keep traffic moving  Build projects sensitive to their communities and landscape  Capitalize on funding opportunities

4 How the Program Scope, Budget and Schedule were developed EBOR developed list of affected bridges and strategy Took programmatic approach to environmental and data gathering with Baseline Reports Use of all available information to determine recommended scope Projects bundled to maximize participation of Oregon firms and contractors

5 Bridge Background Information Environmental Baseline Reports –I.D. Natural / Cultural Resources –Established API –Hazmat Survey –Local Permitting –Environmental Justice Engineering Baseline Reports –Cost Estimate –Drawings / Site Photos –Foundation Report –Inspection Report –Recommended Scope

6 Current Scope for Bridges Data gathering for re-scoping of program –Region input and site visit –Engineering and Environmental baselines –Inspection reports –Load ratings –As-constructed drawings Revised cost estimates –For revised scopes –Refined other estimates

7 Current Scope for Bridges Resolve scope issues prior to DAP Assessed special issues and agreements –Widening for future traffic needs –Allowance for future widening of facility crossed –Rail retrofits –Seismic retrofits –Mobility and temporary traffic control –Programmatic permitting –Vertical clearance issues No added scope without BOC approval

8 Justification of Scope Justification of Scope Policy on addition of work or capacity improvements to the OTIA III Bridge Program Bundles For future lane accommodation, traffic analysis and projectio ns needed Interchange modifications must be in long-term plan for ODOT or MPO Schedule must be considered in decision to add work

9 Budget Original budget approximately $1 billion in construction for 365 bridges Bridge Oversight Committee (BOC) responsible for budget decisions Revised programming level estimates based on rescoping and updated costs Project specific estimates at DAP, Progress, Advanced and Final PS&E Change management process in place

10 Development of Schedule Roughly follows the program stages in the Economic and Bridge Options Report (EBOR) Developed to maximize mobility of the traveling public Laid out to graphically to spread out bidding to maximize bidders and receive favorable bid prices Aggressive project development and construction timelines Acceleration through the use of innovative techniques

11 Current Schedule Available on website and in OTIA III Monthly Report – Master Schedule with 13 steps for each DBB project Revised to incorporate changes resulting from re- scoping and delivery methods of Stages 4 and 5

12 Change….It Happens……. How do we handle change? Change Management Process through OBDP to the BOC Operational Notices available on the OBDP website –Sample letter –Timelines –Contact names –Submission information

13 Operational Notice No. 1 Preparation of Change Management Letter for BOT –Prepared by your Project Manager/Leader –Estimate budget in-line with cost estimating processes (bridge level) –Submit letter to OBDP prior to BOT meeting date Use standard template If you have questions call: Doug Kirkpatrick, OBDP

14 Operational Notice No. 2 Green, yellow, red definitions for OTIA III program Definitions for monitoring of project progress –Scope –Budget –Schedule Reported monthly in OTIA III Monthly Report Yellow or Red means corrective action is necessary

15 Development of Process Flow Reviewed ODOT scope and work flow Development of work flow specific to a bridge program Partnering sessions with Regions to review process Partnering with ODOT Technical Services to review process

16 Design Bid Build Process Flow Steps 1.Bundle/project Development 2.Scope Refinement with Region 3.Assignment of design bundle 4.Project kick-off meeting at project site 5.Design Acceptance 6.Progress Plans 7.Advanced Plans 8.Final Plans, Specifications, and Estimate (PS&E) 9.Pre-let period 10.Pre-construction meeting 11.Construction start 12.Construction progress 13.Project closeout

17 Bundling Projects for Delivery Total of 67 project bundles Coordinated with ODOT regions and stakeholders Multidisciplined approach Five point bundling strategy –Location & context –Type of work –Maintain mobility & minimize traffic impacts –Contract size appropriate for Oregon firms –Critical issues (potential impact on scope, schedule, or budget)

18 Bundling Projects for Delivery Data Gathering –Determine Repair vs. Replace –Approx. construction cost –STIP projects incorporated for efficiency –Other adjacent projects in STIP or Local Map all projects on worksheet Use multi-disciplined team to graphically assess with bundling strategy Evaluate distribution of size and complexity Adjustments throughout the execution

19 Scope Refinement with Region OBDP creates Bridge Scoping Report Review with Region to gather input –Technical –Maintenance –Political –Operational –Other projects Issues log captures and responds to Region comments Scope is presented in Request for Services (RFS) to project team

20 Assignment of Design Bundle to Project Team Selection process Development of project team Development of scope of work Negotiation of scope and fee Development of contract documents Negotiation with Bridge Delivery Unit (BDU) Notice to Proceed (NTP)

21 Scope Template Standard Scope of Work –Menu of services –Use only what is necessary –Provide detail to match anticipated work effort –Use A&E Consultant’s Guide for reference –Site visit prior to developing scope –Use professional judgment –Consider feasible structural solutions –Incorporate CS 3 objectives

22 Level of Effort and Cost Negotiation Fee Estimating Spreadsheet Template (FEST) consistent with the scope template –Provides consistency in estimating project to project –Tool for improvement of data gathering Negotiation includes hours, rates, profit, direct costs, and technology charges Back up to cost development required $

23 Project Kick-off Meeting Meet at the Region to assemble project team Site visit with the stakeholders Continue to gather background information

24 Design Process Flow Activities – Data collection – Field reconnaissance – Kick-off meeting Submissions – Design Quality Plan (DQP) – Project Schedule – Technical Memoranda – CS 3 plan – Monthly reports – Draft DAP submission

25 DAP Activities & Submissions Design Acceptance Package includes: – RR & utility coordination – Public open house mtg. minutes – ROW plan – CS 3 Alternative Analysis Matrix – Level 1 Environmental Preconstruction Assessment (PCA) – Foundation Report & Hydraulics Report – Traffic Management Plan – Bridge TS&L reports & drawings – Construction phasing

26 Design Exceptions Identify any Design Exceptions or Design Concurrences early in the process Minimize need for exceptions or concurrences

27 Progress Plans –60% design progress plans for review –Validation of scope, schedule and budget Advance Plans –Full plans, specifications and estimates for review by the Agency –Validation of scope, schedule and budget Final Design Steps

28 Submission –Complete OPL checklist –Incorporate comments from Advanced Plan Submission Final PS&E biddable, buildable drawing set including environ. specs and plans –Final calculation books –Construction specifications & special provisions –Engineer’s estimate Final PS&E Submission

29 Monitoring and Maintaining Scope: Critical to prevent scope creep during execution of project –Changes must be approved by BOC Budget: Must design a project that fits the budget for the location –Can add additional items that are funded by region or local if schedule is maintained –Estimates at each submission to monitor budget status Schedule: Monthly monitoring –Plan to recover if falling behind

30 Quality Control Key to maintaining budget and schedule (prevent rework and delays) Important part of the execution of the design process Interdisciplinary plan and specification review is critical to reduce construction change orders QC includes resolution of comments or issues Quality control processes apply to work performed during construction

31 Monthly Project Updates Region Operations Committee Meetings (ROC) Monthly reporting of the status of the project you are delivering –Standard format for sheet –Contact information –Status of expenditure –Progress completed on work –Description of major issues Information is published in the OTIA III State Bridge Delivery Program Monthly Report posted to the public.

32 Monthly Reporting Monthly Reports Consultants provide OBDP with: –Project summary and status –Activities and accomplishments –Notes of interest –Issues being worked –Budget information –Percent complete –CS 3 notes –Schedule information –Contact information

33 Communications and Issue Resolution Solve problems at lowest level in organization possible Track issues and document their resolution to the whole team via Electronic Data Management System Defined escalation process to prevent schedule delays –OBDP Design Coordinator/Technical Lead –BDU CPM/ OBDP Design Management –Region Area Manager/ BDU Area Manager

34 Communications and Issue Resolution Utilizing a team approach throughout project development minimizes project rework We all need each other for the transportation program in Oregon to be successful HOW we do the work is important Program success means appreciative public and legislators leading to greater funding for future programs

35 ONE TEAM with a Common Goal ODOT OBDP A&E