Electrical Distribution Training

Slides:



Advertisements
Similar presentations
Seminar on Circuit Breaker
Advertisements

Variable Frequency Drives Bypass Options
CL100D series DSP controlled Uninterruptible power supplies.
Square D Electrical Protection And Monitoring
Modeling Electrical Systems With EMTP-RV
Submitted by: Name:Rajendra Kumar Choudhury Branch:Electrical Engg.
Setup/Installation/Operation of an Environmental Control Unit (ECU)
EMC in Electrical Power Systems Frithiof Jensen Power System Engineer November 12, 2013.
HYDRAULICS & PNEUMATICS
NERC Lessons Learned Summary December NERC lessons learned published in December 2014 Three NERC lessons learned (LL) were published in December.
555 Timer ©Paul Godin Updated February Oscillators ◊We have looked at simple oscillator designs using an inverter, and had a brief look at crystal.
GENERATOR PROTECTION.
SYMAP-BC SYMAP-BC.
Elec467 Power Machines & Transformers
Direct Current Circuits
Slide 1 / 35 P&T - GPS - Training PhB - 01_TECH_TeSys_U_controller_ en 06/2004 Presentation of the range Composition of the controller  Control base 
Generator Protection. Amount of Protection Rated power of the generator Ratio of its capacity to the total capacity of the system Configuration of the.
Chapter 7 SYSTEM PROTECTION
Department of Mechanical Engineering HumilityEntrepreneurshipTeamwork LearningSocial ResponsibilityRespect for Individual Deliver The Promise BS&H, GMR.
IC Voltage Regulator.
Electro-Pneumatics Module 1
Industrial Machine Control
Electrical Installation 2
Understand the concept to improve parameter setting
SFT 2841 IN CONNECTED MODE Prepare setting files.
Prepared By :.  Introduction  Techniques Used  Case Study  Advantages  Application  Conclusion OUTLINE.
Electrical Distribution Training
Current operation (black keys) Descriptions Parameter / protection setting (blue keys) Main points to remember A B C D ? SEPAM UMIs SEPAM UMI OPERATION.
LAFA Food Distribution
Frankfurt (Germany), 6-9 June 2011 Smart Grid Protection in China Wu Guopei Guangzhou Power Supply Bureau Guangdong Power Grid, China.
Electrical Distribution Training Logic Equation Editor.
SFT2841 disconnected Prepare setting files Experts: L.GIGLI
Protection & Switchgear
SmartMQn Motor Horner APG, LLC September 9, 2008.
1 Distributed Generation and Power Quality-Continued.
Introduction to switchgears
ABOC/ATC days Electrical Network: Selectivity and Protection Plan José Carlos GASCON TS–EL Group 22 January 2007.
PRESENTATION ON THE TOPIC By: Rahul agarwal. INTRODUCTION  Overload protection circuit are required in inverters and uninterrupted power supplies to.
SmartMQn Motor Protective Functions Ken Jannotta Jr. Horner APG, LLC.
A SEMINAR ON 400 KV GSS(RRVPNL) BIKANER.
Self Switching Power Supply. Introduction Self Switching Power Supply  Embedded system requires a regulated power supply.
Presentation Topic: Circuit Breakers Represented to: Dr. M. Riaz Khan Represented by: M. Mujahid.
Control Engineering. Introduction What we will discuss in this introduction: – What is control engineering? – What are the main types of control systems?
MCB Connor, Sunny, Kia. What does it do? A circuit breaker is an automatically operated electrical switch designed to protect an electrical circuit from.
TECHNICAL PAPER ON SIMULTANEOUS AC-DC POWER TRANSMISSION
AC Machines. BOOSTER Basic Function:- -Sometimes when we use electrical power we need different voltage level to main supply. It is provided by Booster.
OEZ s.r.o. Quick and universal solution for your order Modeion 05/2012.
PROPRIETARY INFORMATION - © 2015 WOODWARD, INC. PAGE 1 HighPROTEC-2 MRI4-2 Feeder Relay Sales presentation 2015/08/10.
SYNERGY INSTITUTE OF ENGINEERING AND TECHNOLOGY
TITLE: 555 Timer OM INSTITUTE OF TECHNOLOGY Subject: Analog Electronics ( ) Semester: 03 Prepared By:
Equipment 1.Circuit Breaker. 3.Fuses. 4.Protecti- ve relay.2.Bus bar. TYPES OF SWITCH GEAR EQUIPMENT:-
 The figure below shows a protection system for a transmission line, consisting of a CT, PT, a relay and its associated circuit breaker.
Power System Protective Relaying-Part One
© 2015 Eaton Corporation. All rights reserved. This is a photographic template – your photograph should fit precisely within this rectangle. Eaton software.
This is a photographic template – your photograph should fit precisely within this rectangle. © 2016 Eaton. All rights reserved. Eaton software tools xSpider.
Automatic Transfer Switches
HighPROTEC-2 MCA4-2 Directional Feeder Relay Sales presentation
555 Timer EEE DEPARTMENT KUMPAVAT HARPAL( )
LV Safe Powering from UPS to Clients
the CERN Electrical network protection system
GROUND-FAULT GROUND-CHECK MONITOR
Grid feeding monitoring relay
Circuit Breakers & Reclosers
Outline Introduction Switchgear Modeling in IEC 61850
Protection Philosophy
HighPROTEC-2 MRDT4-2 Transformer Protection with differential Sales presentation 2015/08/10.
ELECTRICAL POWER-II Electrical engineering sixth semester
BE5B14SP1 – Electrical machines and electrical apparatus 1
easYgen-3000XT Series Training
Backup Power supply for Electrical substations Overview 01/2012
Presentation transcript:

Electrical Distribution Training Training for Sepam Series 20/40/80 Control and monitoring functions

Load shedding principle Motor load shedding is done to reduce the load on the electrical system so as to keep the voltage within an acceptable range. Block diagram

Load shedding implementation Setting the load shedding function The outputs for load shedding orders and inhibition of closing are part of the switchgear control function.

Restart principle With this function, motors can be automatically restarted after a shutdown triggered by a voltage dip (load shedding). The restart function is to be associated with the load shedding function. It allows staggered restarting of process motors as long as the voltage dip that caused load shedding was brief.

Restart implementation Setting the restart function The outputs for restart orders are part of the switchgear control function

Generator shutdown and tripping Generator shutdown and tripping involve: tripping of the circuit breaker connecting the machine to the network (1) tripping of the excitation circuit breaker (2) shutdown of the prime mover (3). The combination of these three orders determines four types of shutdown and tripping orders: total shutdown (1,2,3), often referred to as simultaneous tripping generator tripping (1,2) generator separation (1) sequential tripping (1,2,3 sequentially).

Generator shutdown and tripping Genset shutdown The genset shutdown function, only present in generator applications, is used for mechanical shutdown by shutting down the prime mover and electrical shutdown by tripping the generator. Genset shutdown is a control logic function which may be used to include or exclude protection function action in conjunction with genset shutdown. This operation may be disabled.

Generator shutdown and tripping Genset shutdown Genset shutdown may be initiated in the following ways: by a shutdown order by delayed protection functions protection functions unrelated to circuit breaker position:12, 21B, 24, 27TN, 32Q, 40, 51V, 64REF, 67, 67N, 81L, 87M, 87T protection functions dependent on circuit breaker position: 50/51, 50N/51N, 59N. The time-delayed, non-memorized outputs of these protection functions trigger shutdown only if the circuit breaker is open by logic equations

Generator shutdown and tripping Genset shutdown Participation in the function is to be set individually in the protection function setting tabs of the SFT2841 software for each protection unit that can take part in genset shutdown.

Generator shutdown and tripping De-excitation The de-excitation function, only present in generator applications, is used to quickly cut off the power supply to an internal fault when the generator is disconnected from the network. De-excitation is a control logic function that may be used to include or exclude protection function action. This operation may be disabled.

Generator shutdown and tripping De-excitation A de-excitation order may be initiated in the following ways: by a shutdown order by delayed protection functions protection functions unrelated to circuit breaker position:12, 21B, 24, 27TN, 32Q, 40, 51V, 64REF, 67, 67N, 81L, 87M, 87T protection functions dependent on circuit breaker position: 50/51, 50N/51N, 59N. The time-delayed, non-memorized outputs of these protection functions trigger de-excitation only if the circuit breaker is open by logic equations

Generator shutdown and tripping De-excitation Participation in the function is to be set individually in the protection function setting tabs of the SFT2841 software for each protection unit that can take part in genset shutdown.

Generator shutdown and tripping Add the outputs for the genset shutdown and de-excitation functions to the control matrix.

Automatic transfer Objectives Automatic transfer is used to increase the continuity of electrical power supply: to automatically replace a failing power supply, or to temporarily transfer the load to another branch of the power supply system for maintenance operations. An operating configuration is chosen as of the design of the installation according to technical and economic criteria. The chosen transfer principle calls for the installation of breaking cubicles and voltage sensors. A ladder diagram is created to control the transfer of breaking devices (circuit breakers, contactors or switches) and checking is done to help with the manual return to the usual operating position. The coupling of power supplies (parallel-connected) is a technical improvement which reduces disturbances for users at the time of the return to normal operation. Generally speaking, the coupling operation, when possible, only lasts for a short time.

Automatic transfer Description The Sepam series 80 substation, transformer, busbars and generator applications contain preprogrammed logic schemes that cover the majority of configurations found in MV or LV installations. 1 out of 2 sources is closed: There are 2 possible power supplies (one normal and one backup) on the same busbars. Just one of them supplies the busbars. Transfer consists of switching completely to the other source. 2 out of 3 circuit breakers are closed: 2 power supplies are connected to 2 separate busbars, which may or may not be coupled by a coupling circuit breaker. Each source is capable of supplying on its own all of the loads of both busbars. This is why there are some installations with just one power supply and coupling closed and others with 2 power supplies and coupling open. An automatic load shedding system is sometimes associated with the «backup» power supply. When there are 2 independent sources, a synchro-check device (ANSI 25 function) is required to enable parallel connection (coupling of sources). This function is only used for the return-to-normal operation.

Automatic transfer: «One out of two» transfer (no coupling breaker) Operating position After transfer Transfer ! 1) In the normal operating mode, only one power supply is closed. The other one is on standby. This can be a generator or the same line, separated upstream. 2) The loss of voltage or tripping by inter-tripping (fault upstream) trigger the tripping of the supply circuit breaker. The transfer is activated. 3) If all the conditions are met on the opposite circuit breaker (ready to close, correct voltage, etc.), it closes and the busbars are supplied again by this source.

Automatic transfer: «One out of two» transfer (no coupling breaker) Operating position Return of source Manual return with or without coupling Coupling with or without ANSI 25 ! 2 5 2 5 N O

Automatic transfer: «Two out of three» with coupling open Operating position After transfer Transfer ! 1) In the normal operating mode, both power supplies are closed. Coupling is Normally open. 2) The loss of voltage or tripping by inter-tripping (fault upstream) trigger the tripping of the corresponding breaker (for example, in the diagrams, the power supply on the left). 3) The transfer is activated and the coupling breaker closes. The busbars are supplied again by this source. N.B. Since the function is symmetrical, the operation described is identical for tripping of the source on the right. It is important for each power supply to be capable of withstanding the load on its own. Otherwise, a load shedding system may be activated at the same time as the transfer.

Automatic transfer: «Two out of three» with coupling open Operating position Manual return with or without coupling Return of source ! Coupling with or without ANSI 25 N O 2 5 The return without coupling triggers another disconnection of the half-busbars (here the busbars on the left) and therefore a disturbance for the users. The return with coupling is "transparent" for the users, but calls for monitoring of the 2 sources, to avoid problems such as: de-synchronization, reverse power, upstream fault, fast energy transfer, etc.

Automatic transfer: «Two out of three» with coupling closed Operating position After transfer Transfer !

Automatic transfer: «Two out of three» with coupling closed Operating position Return of source Manual return with or without coupling ! Coupling with or without ANSI 25 2 5 N O

Automatic transfer Implementation in SFT2841 First operation: activation of predefined control logic Tr Latching of close order Stabilization of the difference between the 2 sources 1) Closing with synchro-check is used for the coupling of two sources for the transfer (voluntary manual control) and the return (return to the normal operating scheme). 2) The order latching time is useful when the 2 sources are in the process of synchronizing. Closing takes place during this time interval. 3) The synchronization confirmation time is short for the coupling of 2 variable sources and may be 2 to 3 s for the coupling of 2 lines from the same network (since, in theory, there shouldn’t be any difference). 4) This time (tr) is applied after the return of voltage to the NC source to enable a return to normal. 5) This is where the configuration is chosen according to the substation busbars. 1/2: one out of two breakers is closed, or 2/3: two out of three breakers are closed. Type of transfer Acknowledgment of the “close enable (ANSI 25)” input

Automatic transfer Implementation in SFT2841 Description of standard assignments - compulsory ____ - optional ------- To record input and output numbers

Automatic transfer Implementation in SFT2841 Second operation: standard assignment and activation of the use of output relays This input can be connected to one of the outputs of the MCS025 synchro-check module Third operation: add, cancel or reassign inputs according to the configuration, habits and operating requirements. Example: - no coupling, - manual control….

Automatic transfer Implementation in SFT2841 Fourth operation: confirm and set the thresholds of the protection functions used by the transfer function. Example: 27-1 (20%Un) to activate transfer 59-1 (90%Un) to enable a correct return to normal voltage No latching No tripping of CB

Automatic transfer Implementation in SFT2841 N.B. No latching or tripping

Automatic transfer Implementation in SFT2841 N.B. No latching or tripping The messages linked to the 59-1 threshold must be deleted or else it will appear continuously. Delete standard «overvoltage» messages

Automatic transfer Implementation in SFT2841 Fifth operation: assign logic to outputs for interconnection with other cubicles and indications. Tripping by automatic transfer: this refers to the tripping of the circuit breaker by one of the transfer conditions. Tripping by 2/3 or 1/2 logic: NO circuit breaker tripping order.

Automatic transfer Implementation in SFT2841 Sixth operation: Delete the standard «overvoltage» messages for 59 -1

Automatic transfer A few comments Installations are symmetrical, so ladder diagrams in Sepam units may be identical, The selector designating the «NO» normally open circuit breaker is used to create the usual operating configuration and therefore differentiate the operation of automatic transfer ladder diagrams. Not all controls are compulsory. The inputs (compulsory or optional) have a default value in the ladder diagrams. This must be taken into account since when they are declared in Sepam, they become active in the ladder diagrams. Internal variables (for example: V-trans-on_flt, V_close_NO_ord...) are available for «remote control» of transfer and the creation of partially or totally specific ladder diagrams. The «equation editor» and «Logipam» tools provide this adaptation flexibility.

Capacitor bank switchgear control Objective The control logic embedded in the Sepam C86 may be used to protect and control a circuit breaker and 1 to 4 capacitor bank switches. The capacitors banks may be star-connected or delta-connected. In the case of star-connection, Sepam provides short-circuit protection of the link to the capacitor bank steps and monitors each link between the 2 stars of each step (fault = unbalance current). In the case of delta connection of each capacitor bank, the Sepam C86 mainly protects against short-circuits (there is no need for a link between capacitor banks). Voltage and frequency monitoring, as well as adaptive thermal overload protect the capacitors against the destructive effects of overvoltage and harmonic frequencies (number 13).

Capacitor bank switchgear control Description Circuit breaker control is linked to capacitor bank control voluntary manual control triggers, first of all, the staggered opening of capacitor bank step switches, followed by the opening of the circuit breaker. When a fault occurs, the circuit breaker opens the circuit and then orders the simultaneous opening of all the capacitor step switches. Position matching is monitored for each breaking device. In «automatic control» mode, an external reactive-energy regulator can control the use of the capacitor bank steps.

Capacitor bank switchgear control Implementation in SFT2841 The «capacitors step ratio» is the lowest capacitive value of one of the capacitor bank steps. The other steps are expressed as multiples of this value. By combining the closing of different steps, it is possible to progressively stagger the value of the capacitance to be connected to the network. e.g. The capacitor bank value is 42KVAR, i.e. three steps with a capacitor step ratio of 1,2,3, so the capacitor step ratio value is 42 divided by (1+2+3) = 7KVAR. Step 1 = 7KVAR, Step 2 = 14KVAR and Step 3 = 21KVAR. Combinations can be made to obtain: 1, 2, 3, 4, 5 and 6 times the lowest value of step 1. In other words: 7, 14, 21, 28, 35 and 40KVAR. First operation: Set the number of capacitor steps according to the installation, the connection and capacitor step ratios*

Capacitor bank switchgear control Implementation in SFT2841 Second operation: select circuit breaker control and capacitor step control. This is the capacitor discharge time (given by the manufacturer) These times are used to stagger the opening of the steps. The outputs assigned to capacitor bank control should not be set up as «pulse» to acquire the value of this pulse order. To adapt control* to different breaking devices.

Capacitor bank switchgear control Implementation in SFT2841 The outputs dedicated to capacitor bank control are set up as «latched». (i.e. not pulse) Third operation: assign the inputs and confirm the outputs. e.g. 3 steps and manual or automatic control possible by external reactive-energy regulator.

Capacitor bank switchgear control Implementation in SFT2841 Fourth operation: confirm and set the protection functions. Change the messages when required.

Capacitor bank switchgear control Implementation in SFT2841 Fifth operation: assign the outputs to control logic and indication.

Capacitor bank switchgear control A few comments Internal variables are available for «remote control» and the creation of partially or totally specific ladder diagrams. The «equation editor» and «Logipam» tools provide some adaptation flexibility.