D. Bozzini, EN-EL-HT, ATOP Days 2009, 4-6 March 2009 1 ELECTRICAL NETWORK: 18 KV NETWORK REVIEW AND STATUS OF THE SPS CONSOLIDATION PLAN D. Bozzini on.

Slides:



Advertisements
Similar presentations
Industrial Bus Health Test using Fluke 225C Color ScopeMeter Application.
Advertisements

Long shutdown 2013: Electrical distribution activities 09/03/2012 IEFC 2012 Workshop F. Duval on Behalf of EN/EL group.
Maintenance At Your WWTP August 2010
Intervention Priority Management This talk will show the CERN priority list, the corresponding check list and the tools used by operators to diagnose a.
CURRENT STATUS OF CV INSTALLATIONS, WORKS DURING LS1 AND PROBLEMS ENCOUNTERED DURING START-UP NORTH AREA Bill Bannister / Jani Lehtinen EATM – 7 th October.
Consolidation program SPS Main Power Converters (Dipole & Quadrupole) K. Kahle / Q. King / G. Le Godec (TE-EPC) IEFC Workshop, 9 March 2012.
DET 310 UNDERGROUND CABLES
This presentation is for illustrative and general educational purposes only and is not intended to substitute for the official MSHA Investigation Report.
Jean-Claude Guillaume ATOP Days – CERN, 5 March 2009 Review of irradiated cables in the SPS Part I – Present strategy Jean-Claude Guillaume Cables and.
Purpose Power lines Equipment Assured Grounding GFCI Conclusion.
Aspects of partial discharge measurement
CV activities on LHC complex during the long shutdown Serge Deleval Thanks to M. Nonis, Y. Body, G. Peon, S. Moccia, M. Obrecht Chamonix 2011.
UPS network perturbations in SX2 Vincent Chareyre EN-EL-SN ALICE Technical Coordination Meeting 7 May 2010.
1 EL Consolidation IEFC Workshop F. Duval on behalf of EN/EL
Prepared By :.  Introduction  Techniques Used  Case Study  Advantages  Application  Conclusion OUTLINE.
112/09/2013. Summary  Events on the network  Incidents  Network reconfigurations  Network operation  Update on activities  Tests  Projects and.
Review of the Project for the Consolidation and Upgrade of the CERN Electrical Distribution System October 24-26, 2012 THE HIGH-VOLTAGE NETWORK OF CERN.
Accelerator Consolidation Workshop TE/EPC consolidation plan 2 Jean-Paul Burnet ACC consolidation day, 12/09/2013.
1 LBDS Testing Before Operation Jan Uythoven (AB/BT) Based on the work of many people in the KSL, EC and TL sections.
LS1 : EL Upgrades & Consolidation Chamonix– February 8 th 2012 F. Duval on behalf of EN/EL The goal of LS1 is to implement everything needed for a safe.
Review of the Project for the Consolidation and Upgrade of the CERN Electrical Distribution System October 24-26, 2012 THE HIGH-VOLTAGE NETWORK OF CERN.
 A brief history of time  In the years BC.  My years at CERN  Current position  What is a Technical Coordinator?  The different type of intervention.
Substation Inspection Program. Mission Substation Incident The event occurred on December 20, 2003 during the peak Christmas shopping season A fire occurred.
Consolidation and Upgrade of the SPS Electrical Networks Current Status JP. Sferruzza, on behalf of EN/EL.
Utility Engineers, PC.  Generation  Transmission  Distribution.
BA6 Cooling Towers Test Day Process Control Functionality and Performance Tests TCR – PCR Monitoring.
K.Hanke – PS/SPS Days – 19/01/06 K.Hanke - PS/SPS Days 19/01/06 Recommissioning Linac2/PSB/ISOLDE from CCC  remote operation from CCC  upgrades & changes.
First results from the study of the LHC cycle power consumption FCC I&O meeting 24 th June 2015 Davide Bozzini With the contribution of G. Burdet, B. Mouche,
J. Pedersen, ST/EL Consolidation of the CERN technical infrastructure and civil engineering. J. Pedersen ST 6 th ST workshop, Thoiry, 1 – 3 April 2003.
Power Quality Karsten KAHLE Electric Power Converter Group (TE-EPC) High Power Converter Section Review of CERN’s Electrical Power Network October.
Static Var Compensator Status (SVCs for Booster and SPS) Situation in 2009 Karsten KAHLE, TE-EPC ATOP days March 2009.
ATC/ABOC Days, 22 January 2007 The safety electrical networks at CERN Anne Funken, TS-EL.
Overview of the main events related to TS equipment during 2007 Definition Number and category of the events Events and measures taken for each machine.
ABOC/ATC days Electrical Network: Selectivity and Protection Plan José Carlos GASCON TS–EL Group 22 January 2007.
On behalf on EN-EL October 1 st, 2015 YETS Works EN-EL [ CF excluded ]
BCWG - 16/11/20102 Content WHY do we need a HW Commissioning campaign? WHAT are we going to do? HOW are we going to do it? ElQA QPS Powering Tests Planning.
Consolidation needs for the Electrical Distribution, Control Cables and Optical Fibres Equipment F. Duval.
Quality assurance - documentation and diagnostics during interventions Corrective maintenance seen from the Technical Infrastructure operation Peter Sollander,
AB/CO Review, Interlock team, 20 th September Interlock team – the AB/CO point of view M.Zerlauth, R.Harrison Powering Interlocks A common task.
High power RF tests places at CERN O. Brunner, CERN 4th SPL Collaboration Meeting jointly with ESS.
Conclusions on UPS powering test and procedure I. Romera Acknowledgements: V. Chareyre, M. Zerlauth 86 th MPP meeting –
ATC / ABOC 23 January 2008SESSION 6 / MTTR and Spare Parts AB / RF GROUP MTTR, SPARE PARTS AND STAND-BY POLICY FOR RF EQUIPMENTS C. Rossi on behalf of.
Bywater Reliability Update Gary Huntley Entergy New Orleans, Inc. Regional Manager Entergy New Orleans, Inc. July 28, 2010.
EN-EL Activities for LS2 LIU, Consolidation, Maintenance, Operation Nicolas Bellegarde on behalf of EN-EL.
TE-CRG Activities D. Delikaris, TE-CRG.
LSC May 2013 Outcome of the magnets tests from the PS, Leir and transfer lines Dominique Bodart.
Design considerations for the FCC electrical network architecture FCC week 2016, Rome, April 2016 Davide Bozzini - CERN/EN/EL With the contribution.
CV works in the non- LHC accelerator complex during 2008 and plans for 2009 ATOP days 2009.
ELENA installation progress F. Butin / ELENA collaboration.
Supply and Distribution of Electrical Energy
YETS & LS2 Works EN-EL / Power distribution
Situation of the Static Var Compensators at CERN.
EYETS Works EN-EL [ FC excluded ]
YETS & LS2 Works EN-El on LHC / Power distribution
TE-MSC activities in SPS during LS2
the high-voltage network of CERN ToMORROW
Consequences of warming-up a sector above 80 K
PSB/PS/TT2/Linac2-3 YETS 2017–2018 & LS2 preparation meeting
Renovation of the 45-year old PS magnets
the CERN Electrical network protection system
SPS activities during LS2 TE-EPC (Power Converter Group)
YETS & LS2 Works EN-EL / Power distribution
Managing infrastructure faults to minimize accelerator down time
TE-MSC activities in SPS during YETS
F Duval, on behalf of EN/EL
Personal Protective Equipment
Incompatibility between MV Switchgear conforming TO the international standards and their use in DNO’s substations M. Arens – Y Tits – Belgium – Session.
F Duval, on behalf of EN/EL
ILO Industrial Opportunities Days, 6-7 June 2019
Presentation transcript:

D. Bozzini, EN-EL-HT, ATOP Days 2009, 4-6 March ELECTRICAL NETWORK: 18 KV NETWORK REVIEW AND STATUS OF THE SPS CONSOLIDATION PLAN D. Bozzini on behalf of EN-EL-HT With the contribution of EN-EL-OP section members and in particular G. Fernqvist, G. Cumer & C. Jach ATOP Days - Session 4 - Technical infrastructure

D. Bozzini, EN-EL-HT, ATOP Days 2009, 4-6 March Outline PART I Major events on HV electrical cable network in 2008 Major events on HV cells in 2008 Historical trend of failures on the SPS 18 kV network CASE 1: The 2008 SPS joints crisis CASE 2: BQ1 Compensator CASE 3: RESTO 1 PART II SPS Consolidation, status and future program BE-TI8 network layout SMB: what do we do? Failure location on HV cables network CONCLUSIONS

D. Bozzini, EN-EL-HT, ATOP Days 2009, 4-6 March Major Events on HV Electrical cables Network SPS 18 kV network –6 cable failures on the 18 kV network (Including the 4 ones mentioned by P. Sollander) 2 on the pulsed TI8 network, stop of the SPS machine (  2001) 3 on the pulsed network, operation of SPS possible in open loop (  1970) 1 failure on the SMB1, redundant network available (  1970) BEQ1 Compensator –Failure on a 18 kV cable head of the BEQ1 feeder in BE substation, fortunately not in operation during failure period (  2003) RESTO 1 Meyrin –Elastimold 18 kV elbow connector on a transformer powering the general services of Resto 1. (  2001) –Near miss failure detected tanks to the preventive maintenance and the reinforced visual inspections of the installation by the operation section.

D. Bozzini, EN-EL-HT, ATOP Days 2009, 4-6 March Major Events on CERN HV cells –ME24 cell explosion (  1995) 10 days stop of the machines feed through the ISOLDE loop –SE18 near miss (  1995) –Preventive action taken Problem limited to FLUAIR cell type on Meyrin substations and SE18 Monitoring of temperature and humidity Systematic Partial Discharge (PD) corona effects measurements Visual inspection inside cells whenever accessible Comments: In the past 5 years, 2 similar accidents and 3 near miss ! –ME59 switch closing failure during auto-tranfer exercise (  1968) Design life time 25 years, continuous operation at CERN 41 years ! Comments: Remember the 29 July 2006, same type of equipment ! ME9 Jura substation (  1968) critical installation

D. Bozzini, EN-EL-HT, ATOP Days 2009, 4-6 March Historical trend of failures on the 18 kV SPS network Nature of the failures A) Aged cables, made with XLPE affected by water- treeing effect B) Not directly the cable but the accessories (joints, terminals) Remarks for out of 6 failures affected recently installed SPS network segments (  2001) 2 remaining failures on old cables

D. Bozzini, EN-EL-HT, ATOP Days 2009, 4-6 March CASE 1: SPS joints crisis (1) - Failures

D. Bozzini, EN-EL-HT, ATOP Days 2009, 4-6 March CASE 1: SPS joints crisis (2)- Analysis

D. Bozzini, EN-EL-HT, ATOP Days 2009, 4-6 March CASE 1: SPS joints crisis (3) - Analysis Analysis of the joints Conclusions of ALL 8 joints examined ASSEMBLY PROCEDURE NOT FOLLOWED POOR QUALITY OF WORK

D. Bozzini, EN-EL-HT, ATOP Days 2009, 4-6 March CASE 1: SPS joints crisis (4) - Repair Corrective actions Repair of all joints that failed Preventive actions Replacement of all joints Improvement of the shielding continuity across the joints 2 new joints for each repair/replacement Now we have 80 joints instead of 40

D. Bozzini, EN-EL-HT, ATOP Days 2009, 4-6 March CASE 1: SPS shield currents Preventive action 68/80 joints have a reinforced shield continuity Modified assembly procedure approved by joint manufacturer Standard Reinforced shield continuity Signs of heating confirmed by the conclusions of the joints analysis This triggered a campaign to measure shields currents Sources and reasons not yet fully understood 100 A/div

D. Bozzini, EN-EL-HT, ATOP Days 2009, 4-6 March CASE 2: BEQ1 compensator – 18 kV cable terminal failure Conclusion ASSEMBLY PROCEDURE NOT FOLLOWED POOR QUALITY OF WORK Failure on a 18 kV cable terminal Date of installation 2003, place BE, Indoor Discharge to ground without load Analysis by third party (Cellpack Laboratory, DE) Outcome of the analysis Length of insulation dimensions not done according to the procedure Use of inappropriate tooling (knife) causing serious weaknesses on the insulation

D. Bozzini, EN-EL-HT, ATOP Days 2009, 4-6 March CASE 3: RESTO 1 - Elastimold 18 kV elbow connector failure Failure on a 18 kV Elastimold connector Date of installation 2003, place Bdg 500, Indoor Discharge to ground, circuit was on load Analysis by third party (Cellpack Laboratory, DE) Outcome of analysis Preparatory dimensions not done according to the procedure Use of inappropriate tooling (knife) causing serious weaknesses on the insulation Conclusion ASSEMBLY PROCEDURE NOT FOLLOWED POOR QUALITY OF WORK

D. Bozzini, EN-EL-HT, ATOP Days 2009, 4-6 March SPS Consolidation - Status on March kV cable network (SMB not included) and substations March-09 Segment LengthStablePulsed [m]Done BE-B3350 B3-B41300 B4-B51350 B5-B61260 B6-B7550 B7-B11100 B1-B21520 B2-BE1100 Total [m] Done [%] 5542

D. Bozzini, EN-EL-HT, ATOP Days 2009, 4-6 March SPS Consolidation – Short term work plan From March 2009 till December 2010 Install cables between BA6-BA6 (2X), BA1-BA2 (2X), BA2-BE (1X) Digging  6.6 km Prepare renovation of substations BA4 and BA2 Define and implement scheme for parallel coupling of the BE-TI8 antenna with BE-BA4 pulsed loop During shutdown Commissioning of installed cables Renovation and commissioning of substations in BA4 and BA2 Installation and commissioning of parallel coupling BE-TI8 with BE-BA4 pulsed loop

D. Bozzini, EN-EL-HT, ATOP Days 2009, 4-6 March SPS Consolidation – Mid term work plan By the end of shutdown 2012 Installation and commissioning of cables between BA4-BA1 (2X) Digging  1.1 km Renovation and commissioning of substations BA1 and BA3 By the end of shutdown 2013 Renovation and commissioning of substation BA6

D. Bozzini, EN-EL-HT, ATOP Days 2009, 4-6 March BA4-TI8 network layout Situation Power line added in 2004 to power the CNGS experiment On this line we also have the SPS stable network for BA4 Not being part of a loop -> no redundancy for powering CNGS and SPS pulsed network in BA4 Consequences If a fault appears on this line (ex: joint to be replaced), one week of shut down minimum Remedies Implement possibility to operate the TI8 line in // to the SPS pulsed loop from BE to BA4

D. Bozzini, EN-EL-HT, ATOP Days 2009, 4-6 March SMB Consequences If a fault appears on this line, one week of shut down minimum of the affected segment How to proceed? 1) Receive guidelines whether to include these circuits in the EN/EL SPS consolidation mandate or: 2) as recommended by the ATC on 27 th Oct study and find procedures for a fast repair and shorten DTTR Situation Old power lines affected by water treeing effect (  1970) Failure rate going up with the time Operation is not 100 % redundant (see 4 th ATC minutes 27 th October 2006) Fully operated by TE-EPC, maintained by EN/EL

D. Bozzini, EN-EL-HT, ATOP Days 2009, 4-6 March Failure location on HV network Current procedure As soon as a failure is detected, ERDF (Electricite Reseau Distribution France) is contacted and they intervene on average within three days to precisely localize the failure. Technique In most of t he cases reflectometry coupled with a pulsed surge generator. Limits Time of intervention depends on availability of ERDF. Also to consider that EDF network diagnostic has priority with respect to CERN. How to improve EN/EL has almost all the equipment to perform the same type of diagnostic A bit old but can be upgraded with a dedicated budget Today there are weaknesses on expertise, but if necessary on a short mid term period we can envisage to set up a EN/EL team for such diagnostic What is needed? Dedicated personnel, time for set-up and time for training on real cases

D. Bozzini, EN-EL-HT, ATOP Days 2009, 4-6 March CONCLUSION Failures 6 out of 8 major failures or near miss are related to bad assembly of HV components For the SPS, except for the “joint crisis”, 2008 as not been a bad year, 2 faults due to aging cables. One affecting SMB. But…remember what we saw on the video! Cells and substations: let us not underestimate the status of ME59 and ME9 Serious problem of HV components assembly quality Identification of specialized firms in ongoing with good results In-house expertise must be improved in order to follow the execution of repair High currents in SPS shields Require more time to investigate the sources of these currents Consolidation of SPS (assuming LHC will run over the winter) Installation of cables on two segments (BA5-BA6 and BA7-BA1) Re-configure substations in BA2, BA4 and improve the TI8 network layout Require solid budget and availability of sufficient and fully qualified personnel SMB: We need to know now what to do Failure location: there is room for improvement of the MTTR