Presentation is loading. Please wait.

Presentation is loading. Please wait.

Bywater Reliability Update Gary Huntley Entergy New Orleans, Inc. Regional Manager Entergy New Orleans, Inc. July 28, 2010.

Similar presentations


Presentation on theme: "Bywater Reliability Update Gary Huntley Entergy New Orleans, Inc. Regional Manager Entergy New Orleans, Inc. July 28, 2010."— Presentation transcript:

1 Bywater Reliability Update Gary Huntley Entergy New Orleans, Inc. Regional Manager Entergy New Orleans, Inc. July 28, 2010

2 2 Why we are here Update on Bywater Reliability Plan ENO Reliability Program Overview What effect this has had 2008-2010 What to expect going forward Summary

3 3 Bywater Area About 5,500 customers Serviced from Almonaster substation by three feeders: 621  1,800 customers 622  2,400 customers 623  900 customers Feeder

4 4 Bywater Reliability in 2008 Numerous reliability complaints Ongoing post-storm remediation Initiated focused efforts for reliability improvements

5 5 Reliability Programs R Recloser Inspections Capacitor Bank Inspections Backbone Inspections T A C T I C S Vegetation Pole Inspections Infrared Inspections Substation Breaker

6 6 How ENO Prioritizes Reliability Projects Selection Process Gather performance data on all circuits Circuit Review: Operations Customer Service Engineering Circuits ranked by performance & customers affected Circuits patrolled and work identified Design jobs created Schedule projects by priority

7 7 Reliability Improvement Work Since 2008 Added two feeders Replaced cross arms Upgraded shield wires around the substation Installed and replaced ground wires Installed fuses Installed fault indicators Replaced jumpers Inspected equipment (reclosers, capacitors) Performed infrared inspections Trimmed trees

8 8 Bywater Feeder Performance SAIFI - Average number of interruptions that a customer would experience.

9 9 Recent 2010 Bywater Outages  Lightning/wind/weather  Equipment failures  Animal contacts  Public damage  Vehicle  Theft  Foreign Objects

10 10 Week of July 19 th :  Detailed inspection of feeders began. Week of July 26 th :  Determine corrective actions needed on feeders.  Conduct pole inspections. August 2010 – October 2010:  Begin implementation of corrective actions.  Conduct infrared inspections. November 2010 – May 2011  Addition of feeder breakers to further sectionalize customers.  Implementation of Automatic Load Transfer Scheme between Almonaster and Tricou Substation to reduce customer impact. (Project approved and equipment on order) What to Expect in Bywater Going Forward

11 11 What to Expect Going Forward (cont’d) ENO has and will continue to manage system reliability: Planned projects and activities should further improve reliability.  Monitor reliability performance indicators (SAIFI, SAIDI).  Routine inspections and repairs.  Analysis of outages to identify repetitive problems.  Continue to review technological advancements that reduce customer outages. Communicate our progress Provide updates to Bywater Neighborhood Association. Provide update to Council in first quarter of 2011.

12 12 Summary We understand inconvenience for customers. We are working diligently to continue positive trend in reliability. We will continue to provide updates. We are committed to providing safe, reliable service.


Download ppt "Bywater Reliability Update Gary Huntley Entergy New Orleans, Inc. Regional Manager Entergy New Orleans, Inc. July 28, 2010."

Similar presentations


Ads by Google