PIP Update Linac Utilities for 2014 shutdown Matthew Gardner, 4/23/14.

Slides:



Advertisements
Similar presentations
Substation L1/ MCC L1 Update March 21 st, Current Location.
Advertisements

LCW Upgrades - Final Booster RF Cavity LCW Isolation Valve Replacement. – 8 valves and unions previously replaced – An additional 10 valves and unions.
Denver Place North & South Towers Case Study Matt Urquhart Amerimar Realty Management Company Jack Wolpert E-Cube, Incorporated.
1 BROOKHAVEN SCIENCE ASSOCIATES NSLS – II ASAC Review Conventional Facilities Briefing Electrical Utility Service Dennis Danseglio, P.E. Project Engineer.
Proton Source Workshop Booster Downtime Wednesday, December 8, 2010 T. Sullivan.
"AIR COOLER" Heat Exchanger
Condensation Piping and Installation Drain Pans
UPS Improvements to Beam Availability at the Australian Synchrotron Light Source Don McGilvery.
Team 2: Kelly Foster Chad Mills Lirjon Llusho Dave Rosso September 30, 2009.
A. Bross MTA RF WS August 22, Welcome MTA RF Workshop.
PEP-II Overview & Ramp Down Plan J. Seeman DOE PEP-II Ramp Down-D&D Review August 6-7, 2007.
CURRENT STATUS OF CV INSTALLATIONS, WORKS DURING LS1 AND PROBLEMS ENCOUNTERED DURING START-UP NORTH AREA Bill Bannister / Jani Lehtinen EATM – 7 th October.
PIP Update July Agenda Summary Update – Budget/RLS – Current Activities – Upcoming Activities/ Changes Update Slides High-Power Ferrite TestingDennis.
08/24/07Shutdown’07 Week 3 F.G. Garcia1 MTA beam line installation Weekly Report August 24, 2007 Period covered: August 17 th to August 24 th (Week 3)
Global Design Effort - CFS Baseline Assessment Workshop 2 - SLAC Reduced Bunch Number 1 BASELINE ASSESSMENT WORKSHOP 2 CONVENTIONAL FACILITIES.
Learning, our way Examples of bad installation. CONTENT Installation related examples Installation related examples Application related examples Application.
ILCTA_NML Progress at Fermilab Jerry Leibfritz September 10, 2007.
University of Michigan, CSG, May 2006 UM/MITC Data Center.
CV activities on LHC complex during the long shutdown Serge Deleval Thanks to M. Nonis, Y. Body, G. Peon, S. Moccia, M. Obrecht Chamonix 2011.
Linac Marx Modulator Update Trevor Butler 10/29/2014.
Machine Advisory Committee Review APS Upgrade Installation Plan and Schedule John Noonan November 15, 2006.
PIP Update Aug 6 th Agenda Summary Update – Current Activities/Updates – New Tuner Test Result: Reid & Slabaugh – Anode Supplies: Crawford.
Air Handler Terminology
Ion Source Update. We now have 2 running sources Source B has been running since the first part of June Both sources have been modified extensively since.
NOvA APD Cooling Water Update William Gilbert University of Minnesota.
Air Handler Terminology
Proton Source Water Systems Proton Source Workshop December 8, 2010 Maurice Ball.
Marriott Corporate Headquarters
PIP Update 3 September 26 th, L1 Future Plans  Installation is halted until further notice (plan for 2014 shutdown or when needed)  Substation.
All Experimenters’ Meeting November 03, 2014 Photo by Greg Vogel.
July LEReC Review July 2014 Low Energy RHIC electron Cooling Al Pendzick LEReC Civil Construction.
Claudio Bortolin. 1 st June: PT100 electrical connection failure (Temp Chiller water In&Out) 1) it required an access to the cavern to be fixed 2) access.
Proton Improvement Plan Bob Zwaska January 7, 2013 All-Experimenters Meeting.
08/31/07Shutdown’07 Week 4 F.G. Garcia1 MTA beam line installation Weekly Report August 31, 2007 Period covered: August 24 th to August 31 st (Week 4)
Injectors & LHC report K. Foraz on behalf of OSS members 14/06/2013LSC - K. Foraz1.
September 19-20, 2007 L. Snydstrup Controls, Diagnostics, Vacuum, Cooling Systems, Installation DOE Annual Review Controls, Diagnostics, Vacuum, Cooling.
PIP Update July 30 th Agenda Summary Update – Current Activities/Updates – Project Controls Update: K. Domann – Linac Lattice – Valeriy Kapin.
Matthew Gardner, 8/20/14.  Replace old water based AC system with conventional rooftop AC system. Drain and abandon old water lines.  Remove old air.
Substation L1/ Booster Substation Y-BE2 Update #3 August 15,2012.
IMPROVING THE EFFICIENCY GEOTHERMAL or GROUND SOURCE HEAT PUMPS.
Spent Fuel Pool Island Southern California Edison, San Diego Gas & Electric, Cities of Anaheim and Riverside CDP Application #: August 13, 2015.
Proton Improvement Plan Bill Pellico April 19, 2013 NOvA collaboration Meeting Bill Pellico NOvA.
Consolidation activities for GS-SE Luigi Scibile GS-SE Accelerator Consolidation Workshop, EDMS:
All Experimenters’ Meeting October 20, 2014 Photo by Greg Vogel.
All Experimenters’ Meeting December 8, 2014 Photo by Greg Vogel.
ATF hardware status - Orbit Stabilization T.Naito(KEK) ATF2 Project meeting Laboratoire de l'Accélérateur Linéaire (LAL) 1.Orbit oscillation.
09/07/07Shutdown’07 Week 5 F.G. Garcia1 MTA beam line installation Weekly Report September 07, 2007 Period covered: August 31 st to September 7 th (Week.
Substation L1/ MCC L1 Update #2 July 27,2012. Status of Procurement  Substation  All approval drawings submitted  Testing is expected to take place.
Booster Shutdown Work - Week 4 Dump and Shielding installation completed Q805/Q806 re-installed, Septum in place Need to align quads and septum before.
PIP Update Oct 29 th Agenda Summary Update – Current Activities – Updates – Additional Meetings/Notes.
August 2007 Booster RF Upgrades J.Reid Booster RF Upgrades West Gallery LCW modifications: – Headers in select locations to be upgraded by.
MTA Installation Meeting February 21, 2007 Agenda 1)Progress report (Fernanda+Carol) 2)Floor Plan layout (Fernanda+Larry) 3)AOB Key Red – critical Orange.
Update: Puck and Gun Magnet March 1, Magnetized Gun 2 K 2 CsSb Preparation Chamber HV Chamber.
FESS/Ops Shut Down Summary Week Ending 9/7/12. – FESS needs a CUB Cooling Outage for installation of Barriers in the CUB Chiller 4160 Volt Starter Cabinet.
Thomas Jefferson National Accelerator Facility Page 1 CEBAF Cryo & SRF Workshop April 3, 2014 Mathew Wright Cryogenic Systems Operations Engineer
FESS/Ops Week Ending 1/20/13. CUB Status – Boiler #1 ON LINE CB Kramer due in to Wire in second recirculating Pump and install NFPA 70E mitigations –
FESS - OPS SHUTDOWN UPDATE. ELECTRICAL Feeder 46A Cable tie in - COMP. A0,C0, E0 CRYO Transformers & Switchgear - Not Complete Master Substation - COMP.
FESS/Ops Shutdown Summary Week Ending 3Aug12. CUB Shut-Down Activities Shut Down Plant on July 21 hrs. Electrical – High Voltage Air Switch/Fuse.
5/15/ meeting. -21 work days to shutdown -31 calandar days to shutdown -Today is May 15 th all Jobs are supposed to be entered in the work list.
PIP Shutdown Status 9/17/2014. RIL/Linac Jobs L1 Transformer ◦Rigging complete ◦Electrical work started ◦Turn on this coming weekend Laser notcher flange.
CV Activities for PSB-LIU POPS-B (new MPS for the PSB-LIU) B 245 PSB Demi water cooling plant Stefano Moccia, EN-CV Meeting 07/03/16.
ILCTA_NML Progress at Fermilab Jerry Leibfritz August 16, 2007.
PIP Update May Agenda Summary Update – Activities – Budget – Plans Update Slides – Solid StateTom – ModulatorsRene – High Power Ferrite Testing.
10/3/2014 Proton Source Update. RIL Update Source B is back in place and under vacuum It will be baked over the weekend It will be started early next.
All Experimenters Meeting PIP Report Fernanda G. Garcia on behalf of PIP team 10/06/2014.
S A Griffiths CM42 June 2015 Electrical & Control.
Update on the PSB Cooling and Ventilation Systems
St. George Infrastructure
CBETA Technical Review
CERN Data Centre ‘Building 513 on the Meyrin Site’
Presentation transcript:

PIP Update Linac Utilities for 2014 shutdown Matthew Gardner, 4/23/14

PIP Linac Utilities Power Distribution – L1 substation LCW – Dual Temp system – Backup pump at Chiller 3 (CUB) Vacuum – New pumps 4/23/2014PIP Status Report2 M.Gardner

Dual Temp Water System 45 year old pipes Large, costly leak in August, 2011 Pipe thicknesses were measured – Nearly half of the locations measured were below standard System has run chilled water only since installation of Klystrons. 4/23/20143PIP Status Report M.Gardner

Dual Temp Water System Repipe Install new copper pipes over hallway Drain, purge, and cap old pipes Move isolation valves to a more accessible location New pipes can be laid while running, and connected during shutdown when equipment is off. Cost: $60k 4/23/20144PIP Status Report M.Gardner

Dual Temp Water System VRV-III Type of unit selected for Booster Gallery. Single unit needed for Linac South Gallery. Cannot cool when outside temp is below 23F. VRV-S Can cool down to -20F ambient Largest unit is 4 tons, 10 ton capacity is required. Having 3 units means additional concrete pads, refrigerant piping, and electrical work. Cost: $35k for units, $100k total. 4/23/20145PIP Status Report M.Gardner

Dual Temp Water System Rooftop AC units Requires multiple units, new duct work, and electrical. Space for duct work is limited in Linac Gallery. Can be installed without interruption to current system. Can use outside air for cooling during cold months. Holes must be cut into roof. Cost: TBD 4/23/20146PIP Status Report M.Gardner

Dual Temp Water System REPIPEVRV-IIIVRV-SROOFTOP LOW AMBIENT Yes23F-20F Yes (Outside Air) Installation Difficulty LowN/AMedium Installation duration 2 weeksN/A4 weeks Cost ~60k N/A ~100kTBD 4/23/20147PIP Status Report M.Gardner

Spare LCW pump for Chiller 3 Single pump for Chiller 3. – All other chillers have multiple pumps Refurbished pump has been purchased, along with valves and Control Panel. New pump can be installed while running on HX-3. 4/23/20148PIP Status Report M.Gardner

Spare LCW pump for Chiller 3 Timeline HX-3 heat exchanges with Processed Chilled system. During colder months, WH cooling also comes from heat exchanging with Processed Chilled system, making the temperature less stable. Once temperature is consistently warmer the WH chillers will be used. Linac will move to HX-3 while CH-3 maintenance is performed. (4 weeks) After CH-3 maintenance the backup pump will be installed. (2-3 weeks) 4/23/20149PIP Status Report M.Gardner

L1 Substation Replacement 4/23/201410PIP Status Report M.Gardner

L1 Substation Replacement Installation Moving Transformer to Linac Basement – 2 days – Will be done ahead of time Switching to Temporary Power – 1 day Dismantle L1 – 2 days Moving old substation out into storage – 1 day Moving new substation into position – 2 days Installing new substation – 5 days Switching back from Temporary Power – 1 day 4/23/201411PIP Status Report M.Gardner

L1 Substation Replacement Moving the Transformer Transformer weighs 17,700 lbs Crane must avoid Utilities, closest approach is 80 feet from the hatch. 250 ton crane required Can be done before the shutdown. Crane will disrupt horseshoe traffic, vehicle and pedestrian. Crane cannot travel before sunrise or after sunset, limits work time to 8:00-17:30 4/23/201412PIP Status Report M.Gardner

L1 Substation Replacement Linac Lower Level 4/23/201413PIP Status Report M.Gardner L1 L1 Storage Location

L1 Substation Replacement TaskCost (approx)Cost (weekend) 250 ton Crane$10k$12k New XMFR to Basement$6k$7k Temporary Power (each time) $5k$7.5k Dismantle L1$2kN/A Remove old XMFR and Install new XMFR (Rigging) $9kN/A Install New XMFR (Electrical) $9kN/A Total$46k$54k Estimates do not include Fermi labor, with time spent by Matt Gardner, Jim Ranson, Ryan Crawford, Greg Meyer, Steve Hays, Scott Crowell, Ray Lewis. 4/23/201414PIP Status Report M.Gardner

September MondayTuesdayWednesdayThursdayFridaySaturdaySunday Beam Off Power Off Tie in Temporary Power Dismantle L1 Substation Install new substation Switch power to new substation Move old Transformer out Move new transformer in L1 Substation Replacement 4/23/201415PIP Status Report M.Gardner

L1 Substation Replacement Alternative Options Fix Price bid through Procurement – High overhead costs Install New Substation in different location – Can be set up ahead of time, making switch faster – Requires re-routing the high voltage and conduits – LCW and Cable trays would be very close to substation Other Concerns Crane – High Traffic area, hard to keep people away during weekday. – Any delays would be costly. HV Cable – Expensive to replace if damaged during installation( ~$12k ) – Cables are on site, delay would be 2-3 days. – Cables were replaced in /23/201416PIP Status Report M.Gardner

Summary Dual Temp – Waiting on Cost estimate for Rooftop option – Most work can be done before shutdown CH-3 Pump at CUB – Working on final design – Can be installed before or during shutdown L1 Substation – Many difficulties to overcome – Planning is continuing – Estimated cost ~$50k (T&M) 4/23/201417PIP Status Report M.Gardner