11 T Dipole informal coil and assembly readiness review Long coil and fabrication tooling development status and plans September 22 nd, 2013 – F. Savary.

Slides:



Advertisements
Similar presentations
LM dipole status & plans – Fred Nobrega 1 Long Quadrupole (LQ) Workshop, February 7-9, 2007 BNL - FNAL - LBNL - SLAC Long Dipole Mirror (LM) Status and.
Advertisements

LQ & LM Status & Plan for FY08 – Fred Nobrega 1 LARP Collab. Meeting – SLAC, Oct , 2007 BNL - FNAL - LBNL - SLAC Long Quadrupole (LQ)-Long Dipole.
CIEMAT technological contributions to linear colliders Fernando ToralGandía, 3/12/2005.
Mikko Karppinen Nb3Sn Coil Production for 11 T Dipole Model Magnets.
11 T Dipole for DS Status of CERN Activities M. Karppinen CERN TE-MSC On behalf of B. Auchmann, L. Bottura, B. Holzer, L. Oberli, L. Rossi, D. Smekens,
EuCARD-HFM ESAC review of the high field dipole design, 20/01/2011, Maria Durante, 1/40 EuCARD-HFM ESAC Review of the high field dipole design Fabrication.
September 2007 FP7-IA HFM JRA proposal G. de Rijk (CERN)1 FP7-IA HFM JRA proposal   The proposal is under discussion: we welcome input from potential.
SHMS Design, Engineering & Construction Status for Hall C Users meeting Paul Brindza January 2010.
CEA DSM Irfu - Bernard GASTINEAU - R3B Technical Board Meeting -April 4, Reactions with Relativistic Radioactive ions Beams GSI Large Acceptance.
11 September 2007 FP7-IA HFM JRA proposal G. de Rijk (CERN)1 FP7-IA HFM JRA proposal   Outline Motivation General description Proposed Work Packages.
MUTAC Review, 9 April MuCOOL and MICE Coupling Magnet Status Michael A. Green Lawrence Berkeley Laboratory Berkeley CA
Preliminary Design of Nb 3 Sn Quadrupoles for FCC-hh M. Karppinen CERN TE-MSC.
Raúl Morón Ballester TE-MSC-LMF
F. Savary. FSY - ColUSM #51 – Outline Mandate of the review panel Composition of review panel Programme Main outcomes/recommendations Actions.
Trip Report on the visit to ICST of HIT, Harbin, China Derun Li Mike Green Steve Virostek Mike Zisman Lawrence Berkeley National Laboratory (from December.
ILC Main Linac Superconducting Cryogen Free Splittable Quadrupole Progress Report V. Kashikhin for Superconducting Magnet Team.
1 Warm Magnets Work Package Status J. Bauche, TE-MSC Technical Meeting, 9th January 2014.
RF Cavity / Coupling Coil Module
TD/MSD TORUS CMM PRODUCTION: OVERVIEW G. Velev Clas12 Torus CCM Production Readiness Review –Dec 4, 2013.
DOE Review of LARP – February 17-18, 2014 Helene Felice P. Ferracin, M. Juchno, D. Cheng, M. Anerella, R. Hafalia, Thomas Sahner, Bruno Favrat 02/17/2014.
MQXF considerations MDT section 11/04/2012. Summary Revised planning Development Personnel Production: strategy and personnel Cost Planning issues not.
Thoughts about the MQXF development plan P. Fessia Thanks to discussions within the MDT section (P. Ferracin, J. C. Perez, E. Todesco, P. Ferracin), L.
Ultra-Compact Electrical Machines for Wind Energy DE-FOA : Demo Machine C. L. Goodzeit and M. J. Ball May 1, 2014 General List of Tasks by Performance.
CERN/CEA Collaboration agreement No. KE2275/TE WP4 – Nb 3 Sn technology development Pré-Kick-off meeting 03/07/2014.
LQ status and plans – G. Ambrosio 1 LARP Collaboration Meeting - LBNL, April , 2006 BNL - FNAL - LBNL - SLAC OUTLINE: Goals, Input and Output Sub-tasks.
Schedule and Work We are moving into a very intensive 4 months with a lot of work to be carried out Electrical services to the devices – after the South.
11-T Dipole Collaboration Review Cold Mass Fabrication and Tooling Procurement F. Savary, with contributions from B. Auchmann, E. Grospelier, S. Izquierdo.
11 T Nb3Sn Demonstrator Dipole R&D Strategy and Status
F. Savary. Click here to add footer 2 Outline Context Constraints & Boundary conditions Project plan Production strategy A few words on QA Conclusions.
11 T Dipole Status at FNAL Fred Nobrega January 21, 2014.
Fred Nobrega, Nikolai Andreev 21 September, 2015.
Title – xxxx 1 LARP & US-HiLumi Contribution to the Inner Triplet Quadrupoles G. Ambrosio Cost and Schedule Review CERN, March 9 th -11 th 2015.
S. Caspi, LBNL HQ Progress and Schedule Shlomo Caspi LBNL LARP Collaboration Meeting – CM13 Port Jefferson November 4-6, 2009.
E. Cavanna, N. Bourcey, P. Ferracin, S. Izquierdo Bermudez, J. Mazet, J. C. Perez, F.O Pincot, X. Sarasola
Wound Conductor Test Facilities (TASK 2) (Short status…) Friedrich Lackner 2 nd of September 2015 FUTURE CIRCULAR COLLIDER MAGNETS TECHNOLOGIES.
F. Savary Question 1 A. Magnet design criteria for the prototype and production magnet to be tested before the installation into the tunnel.
Spectrometer Solenoid Fabrication Status and Schedule RF Cavity / Coupling Coil Module Plan and Progress Steve Virostek Lawrence Berkeley National Lab.
11 T Dipole Project Goals and Deliverables M. Karppinen on behalf of CERN-FNAL collaboration “Demonstrate the feasibility of Nb3Sn technology for the DS.
F. Savary Industrial service contracts for HL-LHC MSC Technical Meeting on
CERN/CEA Collaboration agreement No. KE2275/TE WP4 – Nb 3 Sn technology development Meeting 04/09/2015.
Hi-Lumi Conductor Procurement A.Ballarino, B. Bordini, L. Oberli HL-LHC/LARP International Review of Superconducting Cable for the HL-LHC Inner Triplets.
Summary The process and the components The tooling Production back log estimation The handles and the estimated cost and delay.
FRESCA2 Technical Meeting 5-Validation of coil winding with Cu coils Françoise Rondeaux 09/06/ CEA-Irfu-SACM-LEAS - 5-Rondeaux- FRESCA2 Technical.
11 T Dipole Project Cold mass integration status & plan F. Savary / TE-MSC-LMF.
11 T Dipole Project CERN Status M. Karppinen 11 T Management meeting 1 July 2013.
11 T Dipole Status May 2012 M. Karppinen CERN TE-MSC On behalf of CERN-FNAL collaboration.
MQXF Short model and prototype plans P. Ferracin, G. Ambrosio HL-LHC/LARP International Review of the MQXF Design December 10-12, 2014 CERN.
Status of the Spanish contribution to CTF3 L. García-Tabarés, F. ToralCERN, 17/9/2006.
HiLumi-LARP Annual Meeting November 2014 MQXF pre-series and series magnets fabrication plans Ruben Carcagno November 19,
ESS | title of presentation | 2012-xx-xx | name of presenter Roles and Responsibilities sub title.
CERN MBHSM0101 and Plan for Future Models F. Savary on behalf of the 11T Dipole Project Team.
E. Cavanna, M. Duret, P. Ferracin, T. Genestier, L. Grand-Clement, F. Lackner, S. Luzieux, F. Savary, S. Triquet, J.C. Perez, M. Pozzobon, H. Prin, P.
Cold mass procurement, status and plan, QA-QC H. Prin With contribution from S. Becle, O. Housiaux, R. Principe, J.-L. Rudeiros Fernandez, F. Savary 3.
Long coil manufacturing plan and QC at CERN F. Lackner, P. Ferracin, H. Prin, M. Duret, F. Savary, L. Favier, S. Triquet, S. Luzieux, R. Principe, C. Scheuerlein,
EuCARD-WP7-HFM meeting 15 November 2011 Status of construction of FRESCA2 dummy coil assembly Attilio Milanese, Juan Carlos Perez.
QXF Coil Fabrication & Tooling Reaction / Impregnation
Procurement Status Miao Yu 11/19/2013.
11 T Dipole Integration & Plans M. Karppinen
CSP 25th November 2010 Technical agreement number 3: overview
11T Dipole – Single Aperture 2m Model
BINP, Sergey Pivovarov, Panda magnet meeting at GSl, June 07, 2016
FCC 16 T dipole 4578 dipoles + 5 % spares : 4807 dipole magnets
CEA KE 2775 progress meeting WP3 – FRESCA 2 Magnet
Spectrometer Solenoid Fabrication Status and Schedule
the MDP High Field Dipole Demonstrator
Introduction to the technical content The Q4 magnet (MQYY) for HL-LHC
MQXF updates P. Ferracin October 9th, 2014.
ELENA Magnet Installation Planning
QXF schedule and milestones
Budker Institute of Nuclear Physics,
Presentation transcript:

11 T Dipole informal coil and assembly readiness review Long coil and fabrication tooling development status and plans September 22 nd, 2013 – F. Savary with contributions from N. Dalexandro, L. Deparis, M. Karppinen, F. Lackner, V. Letellier, S. Luzieux, R. Moron Ballester, C.Y. Mucher, T. Sahner, and the short model crew in B927

Outlook  The Large Magnet Facility  Overall plan & milestones  Winding  Binder curing  Reaction furnace  Impregnation  Welding press  Conclusions Long coil and fabrication tooling development status and plans2

The Large Magnet Facility Long coil and fabrication tooling development status and plans3 180

The Winding House Long coil and fabrication tooling development status and plans4

Overall plan & milestones Long coil and fabrication tooling development status and plans5 Year MonthJASONDJFMAMJJASONDJFMAMJJASOND ACTIVITIES Wind trial coil/pole 2, Cu cable, bare React trial pole 2, Cu cable, bare Wind practice coil C1, Cu cable, insulated React practice coil C1, Cu cable, insulated Impregnate practice coil C1, Cu cable, ins. Wind practice C2, Nb 3 Sn React practice C2, Nb 3 Sn Impregnate practice C2, Nb 3 Sn Wind practice C3, Nb 3 Sn (RRP) React practice C3, Nb 3 Sn (RRP) Impregnate practice C3, Nb 3 Sn (RRP) Wind, react, and impregnate coil C4 Wind, react, and impregnate coil C5 Wind, react, and impregnate coil C6 Wind, react, and impregnate coil C7 6 months 8 months 12 months Trial sc cable 1 Sc cable 3 Trial sc cable 2

Winding, Long coil and fabrication tooling development status and plans6  Shorten the winding machine from 10 to 6 m  By the end of 2013  Integrate a support frame for the outer layer spool  PE launched  Installation by the end of January 2014  Revamp the control system  Order launched  Installation and commissioning scheduled in March 2014, and completion expected by the end of March

Winding, Long coil and fabrication tooling development status and plans7  Fabricate winding mandrel  2 options o Full-length mandrel o Assembly of short elements  PE launched  Delivery expected by the end of February 2014  Coil head restraints  Design nearly finished  Delivery expected by the end of February 2014

Winding, 3  Will start with making (a few turns of) a long racetrack coil (pictures show parts and tooling of a short one)  To train staff, who need to learn how to use the winding machine  Scheduled in February 2014, preparation work to be done before Long coil and fabrication tooling development status and plans8

Binder curing Long coil and fabrication tooling development status and plans9  Curing press available  15-m long, sectorized  Study to implement resistance heaters in lieu of the oil heating system on-going, decision to be taken by the end of September  Learn the system, and implement changes as needed, scheduled in Nov.-Dec  Model and drawings of the curing mold exist, and are to be reviewed

Reaction furnace  Contract on-going  CD dated  Contractor GERO in Germany  Final design file, manufacturing & inspection plan by the contractor to be delivered to CERN this week  Procurement of raw materials started  Acceptance tests at the contractor premises scheduled in the beginning of February 2014  Delivery to CERN expected by the end of Feb  Commissioning, and training of CERN staff, by the end of March Long coil and fabrication tooling development status and plans10

Impregnation  Contract for the vacuum impregnation system just signed  F629/TE  Contractor Telstar in Spain  Kick-off meeting soon, within 2 weeks Long coil and fabrication tooling development status and plans11  Delivery expected by the end of May 2014

Handling tools  Have to be designed, and fabricated  Preliminary design study of a handling girder for the inner layer with the winding mandrel, and the outer layer spool, which need to be moved together to the curing press Long coil and fabrication tooling development status and plans12

Welding press  See presentation by F. Lackner  Assembly and welding process demonstrated with satisfactory results in terms of induced pre-stress, and weld quality  Short welding press ready available Long coil and fabrication tooling development status and plans13

Resources  CERN staff  1 technician + another one part time till the end of LS1, thereafter, more t.b.d.  2 academic engineers (1 fellow) part time till the end of LS1, thereafter, more t.b.d.  FSU’s as needed, only after LS1, i.e. September 2013 t.b.c.  Service contracts with specialized firms (initial duration ~2 years)  Academic engineer, technical engineer, draftsman, and experienced practitioner  To anticipate technology transfer towards industry at an early stage  To take into account, also at an early stage, constraints due to industrial production Long coil and fabrication tooling development status and plans14 Work package DescriptionFirm Effort [FTE] Start [* t.b.c.] WP1Cable insulation, winding, and binder curingAlstom Power Systems~ WP2 Reaction heat treatment, coil instrumentation, impregnation Babcock Noell~ WP3Construction of the collared-coil dipoleASG Superconductors~ * WP6Active part construction for collared-coil dipoleASG Superconductors~ * WP9Finishing of the cold mass assemblyAlstom Power Systems~ *

Conclusions  Work plan established, possible but quite ambitious  Contracts for major tooling on-going  Contracts for tooling ancillaries to be launched  Personnel plan established  CERN staff  Service contracts with experienced contractors  And later (after LS1), FSU’s Long coil and fabrication tooling development status and plans15