ITS Subsystems Availability MACS Week, June 2011 E. Sargsyan PP-110620-a-ESA_ITS_MACS_Week_June2011.pptm E. Sargsyan ITS Subsystems Availability 1.

Slides:



Advertisements
Similar presentations
BEPCII RF POWER SYSTEM RF group, IHEP Sep ~ April 1.The 1 st transmitter had finished installing,commissioning and SAT (Site Acceptance Test).
Advertisements

WP CO Status and Progress December 8th, 2010 Johannes Gutleber PR a-JGU, December 8th, 2010 J. Gutleber 1 R. Gutleber.
R. Corsini, CLIC Project Meeting - 24 th May 2013 CTF3 1 CTF3: Highlights of the 1 st run R. Corsini for the CTF3 Team 1.
Alessandro Cappelletti for CTF3 collaboration 5 th May 2010 RESULTS OF BEAM BASED RF POWER PRODUCTION IN CTF3.
E. Beebe LEBT & Ion Injection EBIS Project Technical Review 1/27/2005 LEBT and External Ion Injection Ed Beebe Preinjector Group Collider-Accelerator Department.
What I figured out up to now PP a-AKE_MACS_week_BDC_intro.pptm A. Kerschbaum BD controls MACS week 1.
ESS DTL beam commissioning
Proposal for Decisions 2007 Work Baseline M.Jonker for the Cocost* * Collimation Controls Steering Team.
Uli Raich CERN BE/BI Instrumentation for the new H - Source Test Bench Linac-4 Ion Source Review 2011 Uli Raich CERN BE/BI Linac 4 ion source review, CERN.
ASTA roadmap to EPICS and other upgrades Remote monitoring and control DAQ Machine protection Dark current energy spectrometer.
HINS 6-Cavity Test 3 Month Plan Jan 12, Current Schedule 2-3 day shutdown scheduled to start Jan 18 (Wednesday) to upgrade BPM system and reinstall.
CLIC Implementation Studies Ph. Lebrun & J. Osborne CERN CLIC Collaboration Meeting addressing the Work Packages CERN, 3-4 November 2011.
EBIS ARR Jim Alessi May 4- 7, 2010 Technical Overview.
Alain Blondel MICE VC 12 March 2009 Brief MICE news 1. Decay solenoid: operations will restart in early July. Criteria for acceptance have been specified.
The Stripping Foil Test Stand in the Linac4 Transfer Line
Ion Sources – Hardware and Operation MACS Week Friday 8th October 2010 PP a-LPE, 8 th October 2010, MACS Week 2 Liviu Penescu, „Ion Sources.
Jørgen S. Nielsen Institute for Storage Ring Facilities (ISA) Aarhus University Denmark 1 ESLS-RF 14 (29-30/9 2010), ASTRID and ASTRID2 new LLRF.
February 2010 ALBA Synchrotron Light Source Francis Perez.
14 th ESLS RF Meeting – Trieste, September 2010 ALBA RF Status 1/28 ALBA RF Status Francis Perez.
Overview and Status of the Fermilab High Intensity Neutrino Source R&D Program Giorgio Apollinari for Bob Webber.
Design, integration and installation milestones Legend: 2015/Q1= 1 st quarter of 2015 (January-March) Phase 1 = proton & laser beams operation Phase 2.
Injector RF and Synchrotron RF Present Status, Activities, Plans PP a-GKO_MACS_RfStatus G. Kotzian WP RF - Present Status 1.
Commissioning of REX Jose Alberto Rodriguez, BE-OP-PSB (167538) on behalf of the ISOLDE operations team.
K.Hanke / TDR Meeting / 13 June 2006 Linac 4 Diagnostics L4: K. Hanke, M.Pasini (requirements, specifications, integration) AB/BI: U.Raich et al. (technical.
3 MeV test stand measurement plans A. Lombardi for the LINAC4 team 10/01/2013BCC MeV test stand measurements1.
1 CTF3 CLEX day July 2006 CLEX day 2006 Introduction G.Geschonke CERN.
Beam Measurements After the Sources at the Ion Source Test Stand Including H 2, N 2 and Kr Gas Injection R Scrivens, Linac 4 10/04/2014 Lots of input from.
SPS 200 MHz RF Upgrade Eric Montesinos LIU-SPS coordination meeting 15 th August 2012.
D.Macina TS/LEATOTEM Meeting25/02/2004 Roman Pot test at the SPS Test of the Roman Pot prototype in the SPS proposed in December 2003 (CERN/LHCC ):
LINAC3 UPGRADE Source and LEBT modifications for YETS and recommissioning timetable 28/10/2015 Ville Toivanen.
LINAC4 emittance measurements BI Day Divonne, 24 th November 11/24/2011 B.Cheymol, E. Bravin, D. Gerard, U. Raich, F. Roncarolo BE/BI 1.
PXIE Beam Instrumentation Status Update – Preparing for MEBT 1.1 Beam Vic Scarpine Feb. 9, 2016.
IIFC Meeting February 24-25, 2015, RRCAT P. R. Hannurkar, Akhilesh Jain, M. R. Lad RF Systems Division 650 MHz RF Power 1.
Tobias Stadlbauer, Tony Fowler Special Magnets MedAustron 28 June 2011 Special Magnets Controls Status StatusIntroductionDetailsStatusAOBComponents.
PXIE warm front end status A. Shemyakin PIP-II technical meeting 3 May 2016.
Linac4 BCC 14/10/2010 Linac4 Measurement and Dump Lines BCC on the Linac4 Transfer Line Status.
V Thermo-siphon Workshop Test protocol Jan Godlewski PH/DT-PO On behalf of thermo-siphon working group
ILCTA_NML Progress at Fermilab Jerry Leibfritz August 16, 2007.
Programme for the Physics Start-up Stable and radioactive beams Jose Alberto Rodriguez, BE-OP-PSB (167538)
WIR SCHAFFEN WISSEN – HEUTE FÜR MORGEN Steps towards beam commissioning: Low Level RF system group Thomas Schilcher :: Paul Scherrer Institut SwissFEL.
Laser Line work package (WP6) AWAKE Technical Board meeting 19 May 2014.
V Review SPARC Diagnostic & Control Status G. Di Pirro On behalf control and diagnostic group.
ELENA installation progress F. Butin / ELENA collaboration.
Report Technical Director Storage-Ring-Installation Completed
Areal RF Station A. Vardanyan
Report Technical Director Storage-Ring-Installation Completed
IBBelle: Status & Plans
NICA injection complex status
Diagnostic & Control Status
ECR ion sources for MedAustron
Experience with beam instrumentation at Linac4
PLC-based control systems at SOLEIL - ICALEPCS 2017
Options and Recommendations for TL and Dumps
Accelerator layout > 1000 components (almost 300 magnets and power converters, 153 beam diagnostic devices, about 400m of vacuum pipes, a not neglectable.
LINAC4 Vacuum Control System Review
Hongyu Bai LCLS-II 2 K Cold Box FDR March 9, 2017
LINAC 4 source & LEBT measurement results
352MHz Klystron Control for the 3MeV Linac test stand
XFEL Vacuum System Commissioning
DC Injector and Space Charge Simulation Status
How to run ions in the future?
LLRF and Beam-based Longitudinal Feedback Readiness
JINR NICA beam transfer channels CS
LINAC4 commissioning plans etc.
Preparation of the CLAS12 First Experiment Status and Time-Line
Advanced Research Electron Accelerator Laboratory
commissioning and measurements
Physics Design on Injector I
(Beam) Commissioning Plan
ThomX – Commissioning Meeting – 25/01/2018
Presentation transcript:

ITS Subsystems Availability MACS Week, June 2011 E. Sargsyan PP a-ESA_ITS_MACS_Week_June2011.pptm E. Sargsyan ITS Subsystems Availability 1

ITS overview  A test set-up of the MedAustron Injector (Ion Source, partial LEBT and the RFQ) will be installed and tested in building 184 at CERN  Commissioning and performance tests of different subsystems of the Injector (Ion Source, BD, RFQ, Magnets, CO etc.)  Up to Sep. 2011: technical and IT infrastructure preparation  Oct – Dec. 2012: commissioning and beam tests  Beginning of 2013: removal of the ITS to Wiener Neustadt PP a-ESA_ITS_MACS_Week_June2011.pptm E. Sargsyan ITS Subsystems Availability 2

ITS layout in building 184 PP a-ESA_ITS_MACS_Week_June2011.pptm E. Sargsyan ITS Subsystems Availability 3 Racks RF amplifiers ECR Ion Source Control room Mechanical workshop RFQ

Beam measurements and transport optimization  Ion Source acceptance tests and performance optimization  Ion species scan (MBH-A + FCN)  Current measurements (FCN, CTA)  Profile measurements (WSX, PGX)  Emittance measurements and beam matching (SLX + WSX/PGX)  Beam trajectory steering (MCX + WSX, PGX)  RF amplitude and phase setting based on beam measurements (RFQ and Buncher)  Optimization of the RFQ beam transmission and emittance  Beam energy measurements (TOF measurements with 3 PHPs)  … PP a-ESA_ITS_MACS_Week_June2011.pptm E. Sargsyan ITS Subsystems Availability 4

ITS network  ITS private network required to remotely configure and control different subsystems (as many as possible, e.g. Ion Source, BD Power Converters, RF amplifiers)  The ITS network is required for end of August 2011 (?)  Switch/router based solution for the private network is proposed and will be implemented and supported by CERN IT  General Purpose Network outlets in the ITS control room will be available  M. Thonke takes care of the document specifying the design and planning of the ITS computing and networking infrastructure and communicates it to CERN IT  Large amount of measurement data shall be stored and treated. How do we identify the measurement data and where do we store it?  Is the ITS CO deployment document ready? PP a-ESA_ITS_MACS_Week_June2011.pptm E. Sargsyan ITS Subsystems Availability 5

ECR Ion Source and spectrometer  MedAustron IS and the Pantechnik’s spectrometer dipole are the first subsystems to be delivered and tested at the ITS end of Oct MedAustron final spectrometer to be delivered March  Two week of IS and spectrometer CO integration tests have to be performed right after the installation and before the IS SAT. Will the IS CO be fully functional after those two week?  Scan of the ion species using the spectrometer dipole (sweeping of the power converter current and recording of the beam intensity in the FCN downstream the spectrometer) is an essential measurement for the IS acceptance tests. How this procedure will be implemented (MA and PK spectrometer)?  Synchronization between the spectrometer power converter and the FCN for the scan of the ion species?  Implementation of the IS long term stability regulation using the FCN-A? PP a-ESA_ITS_MACS_Week_June2011.pptm E. Sargsyan ITS Subsystems Availability 6

Beam diagnostics  BD is indispensable tool for the beam measurements and subsystem commissioning and will be permanently used at the ITS, therefore needs to be most advanced in terms of control.  1 st BDT-D and BDT-A downstream the spectrometer equipped and fully functional (hardware) will be available for the IS acceptance tests end of Oct  BD FEC with FECOS implemented and MAPS communication protocol for control and data transfer will be tested in the BD Lab. and ready by end Sep  Emittance measurement procedure will be ready by end Oct  1 st tests of the BD (WSX, SLX and FCN) with the beam (2 weeks of commissioning of the full readout chain) during the IS SAT (1 week shared with CO?). The same types of the BD in the rest of the beamline do not require additional testing.  PGX and CTA readout chain shall be tested with the beam (1 week for each monitor) PP a-ESA_ITS_MACS_Week_June2011.pptm E. Sargsyan ITS Subsystems Availability 7

Faraday Cup Cylindrical (FCC)  The FCC may not be ready by the end of 2011 to be installed in the beamline. Use vacuum pipe instead.  The FCC could be installed and tested in 2012, if available  Is FCC required for the IS stability monitoring at the ITS?  If yes, what should be done for its control? PP a-ESA_ITS_MACS_Week_June2011.pptm E. Sargsyan ITS Subsystems Availability 8

Power converters  Power converter current setting (magnet setting) is one of the most varied parameters during the beam transport optimization!  Ion species scan (spectrometer dipole field sweeping and beam intensity measurement) requires large number of different current settings and beam measurement data points (~3000?)  Given the large number of power converters (23) and due to the reasons mentioned above, it is very important to be able to remotely control the power converters  Three families (A, B and C) of power converters are used at the ITS for different types of magnets (MBH, MQZ, MSO and MCX)  1 st family A power converter required in Oct (for MBH-A)  1 st family B power converter required in Oct (for MCX-A)  1 st family C power converter required in May 2012 (for MQZ-M)  What is envisaged for power converter control?  Do all the power converters of the same family have the same control? PP a-ESA_ITS_MACS_Week_June2011.pptm E. Sargsyan ITS Subsystems Availability 9

Magnets  Interlock system will not be available for the ITS (?)  Interlock signal (from thermo switch and/or flow meter) should be directly sent to the corresponding power converter  From magnet point of view the two signals can be combined.  Do all the power converters have an interlock input? PP a-ESA_ITS_MACS_Week_June2011.pptm E. Sargsyan ITS Subsystems Availability 10

RF amplifiers and LLRF  30 Nov kW RFQ RF amplifier (includes 10kW predriver), 10kW Buncher RF amplifier and the LLRF delivery to CERN  11 Jan amplifiers installed, commissioned and accepted on a dummy load (no MedAustron Control involved) -> amplifiers fully functional and can be connected to the RFQ and the Buncher for RF conditioning and later operation with the beam  LLRF information needs to be accessed remotely from the ITS control room to perform e.g. RF amplitude and phase scans combined with beam measurements. Procedures would be useful.  Control integration tests could be performed for the Buncher amplifier with a dummy load after 11 Jan (tests for Buncher same as for RFQ, except for the amplifier’s PLC).  Control integration tests on a resonant load required?  Timing system for synchronizing the BD with the RFQ pulses necessary? PP a-ESA_ITS_MACS_Week_June2011.pptm E. Sargsyan ITS Subsystems Availability 11

Vacuum system  During the RF conditioning the RF power coupled into the RFQ (Buncher) has to be gradually increased while monitoring the vacuum pressure (surface outgasing) to avoid electric breakdown  The vacuum level in the RFQ and the Buncher has to be communicated to the corresponding RF amplifier (analog? signal VAC OK (predefined value or interval)) during the RF conditioning and the operation.  Procedure planned for the RF conditioning or manual? PP a-ESA_ITS_MACS_Week_June2011.pptm E. Sargsyan ITS Subsystems Availability 12

Fast Deflector (EFE)  EFE ready to be installed at the ITS end of 2011  EFE power converter PKF with switches and controls available spring 2012 (tentative)  How is EFE operation via control system intended?  How is the timing/synchronization with the RFQ pulses is assured? PP a-ESA_ITS_MACS_Week_June2011.pptm E. Sargsyan ITS Subsystems Availability 13

Open questions  ITS CO deployment document ready? Data identification and storage?  Full functionality of the IS control after two weeks of CO integration tests?  Implementation of the ion species scan procedure (MA and PK spectrometer) / synchronization between the spectrometer power converter and the FCN for the scan of the ion species?  Organization of the BD tests with the beam (1 week shared with CO integration tests)?  Power converter remote control?  Necessity of control integration tests on a resonant load?  Necessity of a timing system for synchronizing the BD with the RFQ pulses?  Procedure planned for the RF conditioning or manual?  Integration of EFE in control system?  Timing/synchronization of the EFE with the RFQ pulses?  Is FCC required for the IS stability monitoring at the ITS?  What should be done for the FCC control?  Anything else…? PP a-ESA_ITS_MACS_Week_June2011.pptm E. Sargsyan ITS Subsystems Availability 14