2015 MASS Re-Issue Changes-Division 60
MASS’s many hats Capital Projects Private Development Private Systems Outside communities Agency Use - ADEC PM&E use ADOT&PF use
Say what we do (MASS) and do what we say (You)
2015 MASS Div 60 Changes General Changes – Added a new article covering submittals to Sections through Section 60.08
2015 MASS Div 60 Changes General Changes – Moved materials to the materials articles
2015 MASS Div 60 Changes General Changes – Moved construction instructions to construction articles
2015 MASS Div 60 Changes General Changes – Moved common items under one Section
2015 MASS Div 60 Changes General Changes – Added new material Field applied coating
2015 MASS Div 60 Changes General Changes – Required a new item Valve Box
2015 MASS Division 60 Index Changes Went from 20 sections down to 8 Where did they go?
MASS 2009 R3 Index
2015 MASS Div 60 Index
Division 60 Table of Contents Section – General No consolidation Section – Furnish and Install Pipe Section – Fire Lines Section – Polyethylene Encasement Section – Connect to Existing Water System Section – Relocate Water Main
2015 MASS Div 60 Index Division 60 Table of Contents Continued Section – Furnish and Install Valve Section – Replace Valve Box Section – Reset Valve Box Sections Below Finished Grade Section – Replace top section of valve box Section – Adjust valve box to finish grade Section – Furnish and install Fire Hydrant Section – Water Service Lines Section – Water Service lines Section – Raise or Lower Water service Section – Adjust Key Box
2015 MASS Div 60 Index Division 60 Table of Contents Continued Section – Furnish and Install Galvanic Anodes Section – Furnish and Install Galvanic Anodes Section – Furnish, Install and Remove Temporary Water system Section – Temporary Water System Section – Decommission Water system and components Section – Abandon Pipeline Section – Abandon Private Water Well Section – Remove and salvage existing fire hydrant (This could go to abandon as well) Section – Water Service line – Disconnection only
2015 MASS Div 60 Changes Made use of General Definitions found in MASS Division 10, Section Utility Company – The entity (person, corporation, company, agency, or other) that furnished service(s) (including petroleum and petroleum products, electricity, sanitary sewer, communications, water, natural gas, traffic signal control and storm sewer) utilizing conduit pipe, wire, cable or other transmission lines. Utility Company was used in lieu of AWWU Why this is important – It allows us to control who and when another company can work on our infrastructure. We have an obligation to protect the health and well being of our customers above all else.
2015 MASS Div 60 Changes – General Made it applicable to all following sections Article 1.1 Scope of Work Added work area and bid link Added Contractor secured areas Added restoration
2015 MASS Div 60 Changes – General Article 1.1 Scope of Work Added who is to act as the Engineer when an Engineer is not assigned that duty. This is for private systems Article 1.3 – Surveys Made survey incidental unless paid for under a bid item.
2015 MASS Div 60 Changes – General Article 1.4 Definitions (NEW) Added definitions for common items stated in the following sections of Division 50 in MASS. Water Connection – water pipe and associated apparatuses from the point of connection to a water main to the terminus of the Utility Company maintenance responsibility, usually the property line or Utility Company easement. For copper water services the keybox is normally the terminus point of Utility Company maintenance requirements. Water Extension – typically it is water pipe and associated apparatuses on a parcel of land that begins where the Water Connection ends. A Water Extension typically ends five feet outside a building foundation. Service – connection, extension, and/or building piping from the Utility Company water distribution system to private property and typically to one structure Main Line – Water pipe servicing multiple customers usually within an easement or right of way under the maintenance responsibility of the Utility Company. Water Distribution System – Anything that is used to distribute potable water. Fire Line – A portion of the water service with no additional branches that has the primary purpose of providing fire protection inside of a building. Typically a service that originates at a mainline or at a valve downstream of a fire hydrant tee continuing directly into a building with a sprinkler fire suppression system. Water extensions that are four inches (4”) and larger will be considered a fire line for the purpose of pressure testing. Sewer – Non-domestic and domestic wastewater as defined in 18 AAC 72
2015 MASS Div 60 Changes – General Removed insulation requirements as we no longer specify insulation requirements higher than what is found in Division 20.
2015 MASS Div 60 Changes – Furnish and Install Pipe Article General Added a more defined scope in general. Requirements to meet the DCPM – Official link between MASS and the DCPM Article 2.2 – Submittals (NEW) Article 2.3 – Materials Added one new category of pipes (coated) with three options Zinc Coated Polyurethane Coated Epoxy Coated
2015 MASS Div 60 Changes – Furnish and Install Pipe Article 2.3 – Materials Continued PE pipe resin is to be PE4710 Electro-fusion couplings are removed as an allowed fitting Copper pipe changed to coated copper pipe Requires silver solder brazing States factory coating States field applied coating Field applied coating systems (NEW) Thrust restraints now must be FM Global or UL listed and/or ASTM certified. Reduction of lead act for copper pipe and fittings (Public Law )
2015 MASS Div 60 Changes – Furnish and Install Pipe Article 2.4 – Construction Water interruptions Defined the period of time the Utility Company (AWWU) has to figure out the water shut off impacts (14 working days) Provided the Contractor a basis of bid on what a shutdown means
2015 MASS Div 60 Changes – Furnish and Install Pipe Article 2.4 – Construction Water interruptions Moved (from 60.13) and revised penalties for shut offs longer than six hours.
2015 MASS Div 60 Changes – Furnish and Install Pipe Article 2.4 – Construction Item D – Connection to existing water lines Trench Safety and Live taps – worked with O&M to create wording that supported their activities when completing live taps. Item F – Alignment and Grade Survey – Required a qualified line and grade person and gave the Engineer authority to remove unqualified line and grade person Item K – Detectable Warning Tape Warning tape burial has changed due to numerous comments received on 18”. Revised to a new minimum of 24” and a maximum of 36”.
2015 MASS Div 60 Changes – Furnish and Install Pipe Article 2.5 – Flushing and Testing Added pre-disinfection (AWWA C651) Clearly stated order of testing procedures Did you know that we could back charge the Contractor for canceling a test without providing proper notice? This was in the previous versions of MASS.
2015 MASS Div 60 Changes – Furnish and Install Pipe Article 2.5 – Flushing and Testing Item A – Pre-disinfecting Provide water piping fill parameters (1ft/sec) and wait 1 hour prior to flushing. Did you know AWWA C651 Requires a backflow preventer to fill the line? The Utility Company does not require this.
2015 MASS Div 60 Changes – Furnish and Install Pipe Article 2.5 – Flushing and Testing Item B – Flushing Added metering to the discharge side of the flush tank to show that the sewer system is not inundated and meets the flow requirements set by the Utility Company (Dan Creegan)
2015 MASS Div 60 Changes – Furnish and Install Pipe Article 2.5 – Flushing and Testing Item B – Hydrostatic testing Added requirement to test at the highest end of the pipe when the elevation change is greater than 10 feet. This puts the testing requirement in line with AWWA requirements. The term of maximum allowable operating pressure was troublesome.
2015 MASS Div 60 Changes – Furnish and Install Pipe Article 2.5 – Flushing and Testing Item B – Hydrostatic testing Vents – When are they used?
2015 MASS Div 60 Changes – Furnish and Install Valves Article 3.3 Materials Item D – Valve Boxes Added Valve Box Adaptor II (rubber centering ring)
2015 MASS Div 60 Changes – Furnish and Install Fire Hydrants Article 4.3 Materials Item 8 – Color didn’t change, but specification did. AWWA C502 requires the color to be per federal standards. This change was made to align better with the standard we prescribe, rather than making up a color “caterpillar yellow”. This is a good example of say what you do and do what you say. Prior 2009 R3, we didn’t do what we said, which was follow the AWWA standard C502
2015 MASS Div 60 Changes – Furnish and Install Fire Hydrants Article 4.3 Materials Item 8 – Color didn’t change, but specification did. From AWWA C502
2015 MASS Div 60 Changes – Furnish and Install Fire Hydrants Article 4.3 Construction Clarified and linked to Section field applied coatings for hydrant barrel.
2015 MASS Div 60 Changes – Water Service Lines Kept separate from to help Field Services to address some of the common issues with construction of water lines without plans Require silver solder for all copper pipe to pipe connections. Pipe to valve/shutoff is to be done by flaring. E.g. no three-part unions What is good for the goose (no three part unions in the ROW – AWWU) is good for the gander (owner of the private water line).
2015 MASS Div 60 Changes – Anodes No big changes – Added submittal Article just like the other sections
2015 MASS Div 60 Changes – Temporary Water Systems Increased the amount of information in Article 7.1 – General Testing of hose bibs prior to turning on water Basis of bid for connection to the house is at the furthest hose bib Modification of interior plumbing Added lead safe requirements for tearing out sheet rock to replace interior plumbing
2015 MASS Div 60 Changes – Decommission Water System and Components Mainly combined other portions of other sections that took out anything to do with a water system (Private or Public).
2015 MASS Div 60 Changes - Details New Trace Wire detail
2015 MASS Div 60 Changes - Details New Joint Bonding detail
2015 MASS Div 60 Changes - Details New Mid-span thrust block detail
2015 MASS Div 60 Changes - Details Updated Valve Box detail to show rubber center ring
2015 MASS Div 60 Changes - Details New Dust Pan/thaw wire detail
2015 MASS Div 60 Changes - Details Updated Hydrant detail – lettering This will be modified to reflect actual location based on required size of lettering
2015 MASS Div 60 Changes - Details Updated Water Service detail to show blow off rather than extension
2015 MASS Div 60 Changes - Details Added Extension Details