WILLBROS A Good Job On Time Hydrostatic Testing Practices Establishing Verifiable, Traceable, and Accurate Documentation August 20, 2013 Hal Ozanne Willbros.

Slides:



Advertisements
Similar presentations
Why Lab. Certification? Laboratory certification tries to insure that the laboratory is qualified and capable of analyzing the sample and obtaining quality.
Advertisements

Tips to a Successful Monitoring Visit
PRINCIPLES OF A CALIBRATION MANAGEMENT SYSTEM
Spill Prevention Control & Countermeasures Compliance and Planning.
U.S. Department of Transportation Pipeline and Hazardous Materials Safety Administration Gas Gathering Update Pipeline Safety – Getting to Zero Pipeline.
1 HYDROSTATIC TESTING Approved for Public Release.
Software Quality Assurance Plan
PHMSA Perspectives Construction Process & Standards
Contractor Safety Management
Crane Operations Objective
Establish Verification Procedures (Task 11 / Principle 6)
World Health Organization
SAE AS9100 Quality Systems - Aerospace Model for Quality Assurance
Lecture 8. Quality Assurance/Quality Control The Islamic University of Gaza- Environmental Engineering Department Environmental Measurements (EENV 4244)
GLAST LAT ProjectLAT Engineering Meeting, April 1, 2003 GLAST Large Area Telescope: Performance & Safety Assurance Darren S. Marsh Stanford Linear Accelerator.
Calibration (Qualification) of Centrifuge
Documents and Records-Writing a Quality Manual-Module 16 1 Quality Manual Structure and Contents Quality Manual Structure and Contents - optional.
Short Course on Introduction to Meteorological Instrumentation and Observations Techniques QA and QC Procedures Short Course on Introduction to Meteorological.
Quality Assurance/Quality Control Policy
OHSAS 18001: Occupational health and safety management systems - Specification Karen Lawrence.
©2004 Fluke Corporation Insulation Resistance Testing 1 Insulation Resistance Testing.
FPSC Safety, LLC ISO AUDIT.
Chapter 10 Verification Procedures. Objective In this module, you will learn: u How to define verification u What functions are part of HACCP plan verification.
Process Engineer’s Role in Project Management Dr Abdullah Malik.
Radiopharmaceutical Production
Seafood HACCP Alliance for Training and Education Chapter 10 Principle 6: Establish Verification Procedures.
World Health Organization
QUALITY MANAGEMENT SYSTEM ACCORDING TO ISO
Control Selection Techniques Employed for D&D Projects with Emphasis on Nuclear Criticality Safety Controls Brenda L. Hawks Engineering Director Oak Ridge.
Regulatory Overview.
Good Manufacturing Practices
Authorization and Inspection of Cyclotron Facilities Inspections.
Visit us at E mail: Tele: www.globalmanagergroup.com.
Maricopa County Air Quality Department Performance Test Specifics Rob Arpino Environmental Engineering Specialist.
1/18/2005Module 41 How the NCSX Project Does Business Work Planning & Design Review Processes.
ISO OPERATIONAL CONTROL
FCS - AAO - DM COMPE/SE/ISE 492 Senior Project 2 System/Software Test Documentation (STD) System/Software Test Documentation (STD)
Presented by Steven P. Feltman Food Safety and Quality Specialist.
1 Saxony-Anhalt EU Twinning RO 04/IB/EN/09 State Environmental Protection Agency Wolfgang GarcheWorkshop European Standards Requirements of.
Student Book © 2004 Propane Education & Research CouncilPage Documenting Vapor Distribution System Installations Documenting your work.
Aloe Vera of America: A Quality IASC-Certified Producer of Aloe Vera Presented by Walt Jones.
Third Party Verification Services. Who are these people?  These are 3 rd party verification companies hired by large companies, often called Owner.
TRENTON Casing Filler Presentation
Proposed Rule for Preventive Controls for Animal Food.
Proposed Rule: 21 CFR 507 Proposed Rule for Preventive Controls for Animal Food 1.
A FSP is a Program designed to identify and control hazards in order to establish and maintain food safety. (Based on HACCP principles) 1 version 2 Dec.2009.
WHAT DOES IT MEAN FOR YOUR MAOP? REAUTHORIZATION, SAN BRUNO, AND PHMSA’S ADVISORY BULLETIN.
Active Corrosion Process Nisource – COH/CKY. Objectives  Understanding the terminology –Active Corrosion –& Suspected Areas of “Active Corrosion”  Developing.
Validation | Slide 1 of 27 August 2006 Validation Supplementary Training Modules on Good Manufacturing Practice WHO Technical Report Series, No. 937, 2006.
U.S. Department of Transportation Pipeline and Hazardous Materials Safety Administration Verification of Records Linda Daugherty – Dep Associate.
GOOD DOCUMENTATION PRACTICES (GDP)
SWPPP: Stormwater Pollution Prevention Plan Creating/Implementing a Plan for Compliance.
Hot Work Permit Osan AB Fire Emergency Services.
Responsibilities of Test Facility Management, Study Director, Principal Investigator and Study Personnel G. Jacobs Belgian GLP Monitorate Zagreb, 17 December.
Process Safety Management Soft Skills Programme Nexus Alliance Ltd.
QUALITY ASSURANCE MODULE 3. Definitions Quality Assurance - A process/effort that ensures that processes are followed, that the processes of doing right.
Chapter 10 Verification Procedures.
BSB Biomanufacturing CHAPTER 4 GMP – Documentation Part I (SOP)
Administration of a FIDIC Contract - Project Control
How to Implement an IG Manufacturing Quality Procedure System
Author: Nurul Azyyati Sabri
Temporary Works Co-ordination
Chapter 10 Verification Procedures.
First Break To establish minimum safety requirements when performing a first break “First Break” – Refers to the initial opening of piping/equipment.
Good Laboratory Practices
TRENTON Casing Filler Presentation
Role and Responsibility for Quality Assurance Vishnu P. Shrestha
Role and Responsibility for Quality Assurance Vishnu P. Shrestha
Permit to Work Process​ HSE GROUP RULE (CR-GR-HSE-402)
Fiber Reinforced Polymer Systems
Presentation transcript:

WILLBROS A Good Job On Time Hydrostatic Testing Practices Establishing Verifiable, Traceable, and Accurate Documentation August 20, 2013 Hal Ozanne Willbros Engineers

WILLBROS 2 Hydrostatic Testing Practices Verifiable, Traceable, Accurate Documentation  Hydrostatic Testing Calculations  Hydrostatic Test Plans  Hydrostatic Test Reports  Data Collection and Final Verification Pipeline and Hazardous Materials Safety Administration (PHMSA)  Audits  Record Keeping  Approvals/Signatures

WILLBROS 3 Hydrostatic Testing Practices Hydrostatic Testing Calculations  Detailed calculations based on pipe characteristics and specifications –OD, wt, grade, weld/seam type, length of segment –Flange or no flanges (ANSI rating could be limiting factor for pressure) –Based on 100% SMYS or 125% MAOP –Surveyed pipe elevations –Test medium, volume, and temperature constraints  Segment lengths based on elevations and SMYS requirements  Project Management Review and Approval –Engineering Project Manager –Client Project Manager

WILLBROS 4 Hydrostatic Testing Practices Hydrostatic Testing Calculations  MAOP Verification calculated and determined by final hydro test results

WILLBROS 5 Hydrostatic Testing Practices Hydrostatic Test Plan  Set it up right and make it fully complete with Environmental Input –To comply with permits, environmental needs to be involved to ensure compliance (BLM, Corps of Engineers, FERC, NEPA, etc) –Advise on supply sources and discharge areas  Fabrication Test (4hr) or Mainline Test (8 hr) –Fabrication Test for HDDs and long bores prior to installation –Mainline Test for mainline (including HDDs) once in ground

WILLBROS 6 Hydrostatic Testing Practices Hydrostatic Test Plan  Environmental Requirements and Stipulations –Water Source –Discharge Location –Water Quality  Detailed to describe all parts of Hydro Test –Filling and pressuring up –Performing Test –Gathering Data –Completion of test –Dewatering of segment –Move water from one segment to the next or new water each segment –Drying and Cleaning –Final Verification and sign off

WILLBROS 7 Hydrostatic Testing Practices Hydrostatic Test Plan  Max and min test pressures for each Segment –Provide location of expected occurrence in plan –Provide expected test site location pressure  DOT/PHMSA Requirements (also use API RP1110) –Depends on type of test (spike test, strength test, leak test) –Pressure test medium, equipment, and materials –Qualifications of contractor and personnel performing test –Test period, failures, leaks –Test records and drawings kept for useful life of pipeline –Approval Signatures (operator of test, witness of test, personnel certifying the test)

WILLBROS 8 Hydrostatic Testing Practices Hydrostatic Test Plan  Acceptance Criteria established prior to conducting test  Proper Approvals and Signatures –Project Engineer –Project Manager –Construction Manager –Client Project Manager

WILLBROS 9 Hydrostatic Testing Practices Hydrostatic Test Report  Set it up in the beginning so that all data required to be gathered is understood by test operators  Based on Operating Company Standards and DOT/PHMSA Requirements (also API RP 1110)  Attention to Detail

WILLBROS 10 Hydrostatic Testing Practices Hydrostatic Test Report  Proper Recording of Measurements –Pipe Diameter and wall thicknesses –Pipe Grade and SMYS and/or ANSI rating –Location and elevation –Test Medium description, source, and volumes –Any additives description and volumes –Date and time of start and stops –Pressure vs. Time log –Temperature (ambient and pipe or test medium) –Weather conditions –Segment length

WILLBROS 11 Hydrostatic Testing Practices Hydrostatic Test Report  Completeness of Forms and Records  Proper Approvals and Signatures –Test Operator –Operator Supervisor –Construction Manager –Project Engineer –Client Authorized Representative (can be construction manager or project engineer in many cases)

WILLBROS 12 Hydrostatic Testing Practices Hydrostatic Test Data Collection  Planning and Preparation  Understanding Test Report and Forms –Anyone involved in the test or reviewing/approving of the test data –Allows those involved to know exactly what is required to be gathered and what is required to be approved based on what is provided  Maintain and Include Raw Data Gathered into Final Test Report Book

WILLBROS 13 Hydrostatic Testing Practices Hydrostatic Test Data Collection  Calibration of Instruments and Equipment –High volume pump and associated piping and meter for line fill –Injection pump for corrosion inhibitors, leak detection dyes or gases, or other chemicals –Variable speed PD pump for pressurization with known volume per stroke and a stroke counter –Pressure sensing device and deadweight tester –Continuous pressure recording device –Test medium temperature sensing device and display –Ambient temperature sensing device and display –Continuous temperature recording device for test medium and ambient –Test medium sampling equipment –Gas/oxygen detecting equipment

WILLBROS 14 Hydrostatic Testing Practices Hydrostatic Test Data Collection  Collecting/Recording All Details and Information Required on Reports and Forms –Test medium volumes, pressures, temperatures, times –Ambient pressures, temperatures, weather conditions –Pipe conditions and specifications (OD, wt, grade, high/low point, etc) –Instrument/Equipment calibration information –Failures, leaks, condition changes –Approvals  Maintain and Clean up All Field Notes on Drawings and Books –Incorporate into overall Test Report  Maintain All Failure Record Data for Final Book

WILLBROS 15 Hydrostatic Testing Practices Hydrostatic Test Data Collection  Temperature Recorders –Weather condition changes can affect volume of test medium to maintain constant pressure on pipeline –Secure temperature bulb directly to bare pipe, insulate, and backfill to ground level 12 hr prior to test –12 hr allows for fill medium, pipe, and ground temps to stabilize –Locate temperature bulbs on pipe a minimum of 500’ from exposed pipe

WILLBROS 16 Hydrostatic Testing Practices Hydrostatic Test Data Collection  Temperature Changes –As temp increases, pressure increases –As temp decreased, pressure decreases –Temp changes can affect volume of medium in pipe –Important to not conduct test during periods of day when temperature change is significant (frost levels play important role in test temperature as well)

WILLBROS 17 Hydrostatic Testing Practices Hydrostatic Test Data Collection  Small Leak or Change in Temperature? –Compare change in pipe temp to change in weather conditions –Change in pipe temp should correlate to change in ambient temp (changes show up on temperature plot for test) –Corrected volume equations at beginning and end of test account for change in pressure and temperature which correlates to change in volume –Spreadsheet set up to determine corrected volumes - part of test plan/report

WILLBROS 18 Hydrostatic Testing Practices Final Verification  Verify that final book is complete and contains all information in one location –Hydro Test Plan and Calcs –Test specifications –Survey data –Calibration certificates –Hydro test reports –Original test charts

WILLBROS 19 Hydrostatic Testing Practices Final Verification  If all required data is in one place, then it is easier to gather, maintain, and deliver to auditors  Ensure that the following people have signed off on the Test Report and Data Collected –Field Person Responsible for Gathering Data –Field Supervisor Over Hydro Test –Construction Manager –Project Engineer –Project Manager –Client Project Manager

WILLBROS 20 Hydrostatic Testing Practices PHMSA  Audits –Checks during construction to verify proper records being kept –Documentation is the first thing to be checked during a field audit –First impression set the tone for the audit  Record Keeping –Records should have proper approvals and signatures on them –Should be same throughout duration of project –Fabrication testing (HDDs) and Mainline testing (main pipeline)  Documentation Approvals/Signatures –Checks for field personnel, engineering personnel, and Company personnel signatures and approvals of test records and reports

WILLBROS A Good Job On Time