ELI-NP The Way Ahead-Workshop March 10-11, 2011 Vacuum System for Beam Transport Catalin M. Ticos National Institute for Lasers, Plasma and Radiation Physics.

Slides:



Advertisements
Similar presentations
ILIAS WG1 meeting - Birmingham1 Cryogenic Trap Vs Brewster window & noise coupling through windows J. Marque.
Advertisements

IP Area Reconfiguration Conceptual Design Five Phases: 1.Transport (A) 2.Gas Chamber 3.Injection Chamber 4.Compressor 5.Transport (B) M. Litos July 24,
Liquid Hydrogen Absorber
HIE-ISOLDE HEBT: characteristics Beamline diameter: 40 mm (REX: 100 mm) Beamline height: 1.75 m Beamline vacuum: low 1e-7- high 1e-8 mbar Connection of.
11-13/10/2007 ILC BDS Kick-Off Meeting, SLAC, US 1 BDS Vacuum System Dr. Oleg B. Malyshev ASTeC Daresbury Laboratory.
Target Status Report Lara Howlett University of Sheffield.
Heinz Grote1 Presentation to NSCX WENDELSTEIN 7-X Assembly Max-Planck- Institut für Plasmaphysik KKS-Nr.: 1-AD Dok-Kennz.: -Txxxx.0 Heinz Grote October.
April 27th, 2006 Paola Puppo – INFN Roma ILIAS Cryogenic payloads and cooling systems (towards a third generation interferometer) part II: the Vibration.
Applications of Vacuum Technology in the NIF Laser System
MICE Target Status Chris Booth Sheffield 10 th May 2006.
Stewart Shen October 27, LCLS-XTOD Gas Attenuator LCLS FAC Meeting October 27, 2005 Stewart Shen, Keith Kishiyama and Marty Roeben.
UCN Phase 2 Design Status September 10, Design Components Bulk Shielding Target Crypt Cryogenic Insert Target Insert UCN Port Beam Window Cooling.
Compressor status AWAKE Technical Board meeting 19 May 2015.
PEEM III Endstation Design Review
Summary of the AWAKE Technical Board Meeting September 2014 – March 2015.
1 BROOKHAVEN SCIENCE ASSOCIATES Vacuum Systems H.C. Hseuh, Vacuum Group Leader 8 th ASAC Meeting for NSLS-II Project May 10-11, 2011.
Status of LCGT and CLIO Masatake Ohashi (ICRR, The University of TOKYO) and LCGT, CLIO collaborators TAUP2007 Sendai, Japan 2007/9/12.
Date Event Global Design Effort 1 Technical System Review John Noonan, ANL Yusuke Suetsugu,KEK Paolo Michelato, INFN Milano.
Shielding the Turbomolecular Pump: an update 14 May 2013 Kiril Marinov ASTeC, MaRS, DL 1.
LINAC 4 Project L4T/L4Z Design Status J.Humbert / B.Riffaud on behalf of EN-MME design team 1 st September 2011 LINAC4 – BEAM COORDINATION COMMITTEE B.Riffaud.
FACET II Project – User Area Christine Clarke 26 th June 2015.
PHYSICS 225, 2 ND YEAR LAB VACUUM TECHNOLOGY G.F. West Thurs, Jan. 12.
FP 420 Connection Cryostat Design and Integration Keith Potter, Jaak Lippmaa, Guido Ryckwaert, Benoit Florin, Thierry Renaglia, Thierry Colombet, Shrikant.
BDS 11 Vacuum System for BDS [Completeness of RDR] Y. Suetsugu J. Noonan and P. Michelato Design principle Basic design Cost estimation.
Polarized GaAs photo cathode development and the preparation of Gatling Gun cathodes at BNL The Single Cathode Activation Chamber.
ENEN H- INJECTION: STATUS ON MECHANICAL DESIGN - VACUUM SECTORIZATION - BHZ162 CHAMBER MODIFICATIONS - DUMP AREA - BHZ11 CHAMBER MODIFICATIONS.
Stress and Cool-down Analysis Yun HE MLC Internal Review 9/5/2012Yun HE, MLC Internal Review1.
PIMS IN INSTITUTE FOR NUCLEAR STUDIES Brazing Andrzej Soltan Institute for Nuclear Studies.
About the possibility to build a 10-PW femtosecond laser for ELI-NP till 2015 Razvan Dabu National Institute for Lasers, Plasma and Radiation Physics Bucharest.
Peter Spiller, COLMAT-Kick off meeting, Cryo-Collimator, CERN, COLMAT Kick-off meeting CERN Peter Spiller Cryo-Collimator (Catcher) for.
E-217 FACET users meeting 9/15/14 Ken Marsh. What happens to the experiment when laser fires full power in Lithium? Do we ionize the helium buffer zones?
Booster and Collider SC magnets. Design & prototyping of UHV and cryostat systems for Booster and Collider A.Smirnov JINR, Dubna, Russia NICA Machine Advisory.
Vacuum, H-C. Hseuh January 4, 2007 RHIC II Project Internal Cost Review Vacuum Systems H.-C. Hseuh January 4, 2007 Vacuum Systems.
The CNGS Target Station By L.Bruno, S.Péraire, P.Sala SL/BT Targets & Dumps Section.
Implantation of heavy ions 86 Kr and 132 Xe in emulsion with energy 1.2 A MeV K.Z. MAMATKULOV LHEP, JINR, Dubna, Russia. DjPI, Uzbekistan. “Workshop on.
SIDDHARTA future precision measurement of kaonic atoms at DA  NE Florin Sirghi LNF SPRING SCHOOL "Bruno Touschek" In Nuclear, Subnuclear and Astroparticle.
Experience Fabricating the Storage Ring Vacuum Chambers for NSLSII
ELI-NP: The Way Ahead, Bucharest, March 2011 Modeling propagation of femtosecond laser pulses in ionized gas media Valer TOSA National Intitute for.
EAR2 Beam Line Report on the Status C. Weiss EAR2 Beam Line - Report on the Status1.
56 Mhz Vacuum Mike Mapes Mhz Insulating Vacuum TURBO PUMP WITH GATE VALVE AND GAUGE SET MOUNTED ON TANK SIMILAR TO RHIC CRYOSTAT & VALVE.
SVT Stepper Motor Test Takashi Maruyama, SLAC HPS Collaboration Meeting June 16-18, 2014.
National Ignition Facility Vacuum Systems Presentation to OLAV Workshop, ORNL July 11-14, 2011 NIF Vacuum Subsystems Managers Igor Maslennikov* John Hitchcock.
Gen Magnet Design JLAB MENG Contributors: Supervisor: Butch Dillon-Townes Magnet Engineer: Robin Wines Mechanical Designer: Ron Lassiter Mechanical Engineer:
Conclusions of the Workshop Nicolae – Victor Zamfir.
Extreme Light Infrastructure in Romania: progress Daniel URSESCU Technical contact point for ELI in Romania INFLPR, Magurele, Romania.
09/07/07Shutdown’07 Week 5 F.G. Garcia1 MTA beam line installation Weekly Report September 07, 2007 Period covered: August 31 st to September 7 th (Week.
CW Cryomodules for Project X Yuriy Orlov, Tom Nicol, and Tom Peterson Cryomodules for Project X, 14 June 2013Page 1.
Vacuum conditions in PANDA pbar-line Alexander Gruber, SMI, Vienna, Austria.
DESIGN AND PERFORMANCE OF VACUUM SYSTEM FOR HIGH HEAT FLUX TEST FACILITY Rajamannar Swamy*, Prakash Mokaria, Samir Khirwadkar, Sunil Belsare, M S Khan,
Gamma Beam System at ELI–NP The ELI–NP Team* ELI–NP, IFIN–HH, Bucharest–Magurele, Romania * The ELI–NP Gamma Beam System (GBS) will.
Laser Line work package (WP6) AWAKE Technical Board meeting 19 May 2014.
7/8/08 John Amann LC Mechanical Engineering LC 18M W Beam Dump Mechanical Engineering Design Updates.
01/09/ KTAG 5/8 sectors equipped DCS system in pogress DAQ commissioning in progress Test pressure scan this week (t.b.c) 01/09/20142.
SPL RF coupler: integration aspects
INDUSTRIAL HYGIENE External EHS Expert Panel Workshop
Stephan Aulenbacher MAGIX Collaboration Meeting
1.3-GHz Cavity Vacuum Furnace at IB4
RTML Vacuum System RDR Summary FermiLab October 24, 2007
Proximity Cryogenics P&IDs meeting
Challenges of vacuum chambers with adjustable gap for SC undulators
Vacuum chamber for experiment HIHEX at FAIR
Vcuum system works in 2016 Liu Baiqi, Peng Xiaohua.
N-TOF EAR2 - Vertical beam design & construction - Irradiation facility proposal S. Girod EN-EA.
Future R&D: beta-beam Mats Lindroos Mats Lindroos.
(WBS ) Alan Wootton, LLNL April 24, 2002
ISRC and LEBT Vacuum System Design
BGC Collaboration Meeting –
Vacuum Control System for Monolith Vacuum
accumulation octopole
Presentation transcript:

ELI-NP The Way Ahead-Workshop March 10-11, 2011 Vacuum System for Beam Transport Catalin M. Ticos National Institute for Lasers, Plasma and Radiation Physics (INFLPR), Bucharest, Romania

ELI-NP The Way Ahead-Workshop March 10-11, 2011 Engineering issues related to beam delivery to target Motivation: Identify engineering issues related to beam propagation in vacuum Steps: 1. generation of PW laser beam (in compressor) 2. transport of PW laser beam to target Peculiarities: Max beam diam. 90 cm, large and heavy optics/vacuum compatible Transport over large distances (~30m) with little distortions!

ELI-NP The Way Ahead-Workshop March 10-11, 2011 Large beams are in vacuum Challenge: Lasers and target areas on 2 different concrete floors. Both floors are supported by a number of springs  m to mm displacement within beam line  mechanical stress  optical misalignment

ELI-NP The Way Ahead-Workshop March 10-11, 2011 Main issues Required: torr vacuum in beam pipes/compressors/chambers 2.Low (or no) vibrations along the beam line and at target chambers 3.Cooling of pumps (pipes /target chamber as well?) Needed: Proper vacuum system with integrated remote controls (pumps, gauges, valves, gas containers, filters, exhausts, etc) Reduce vibrations from mechanical/turbo pumps to pipes/compressor/ chamber Water/air cooling system for pumps

ELI-NP The Way Ahead-Workshop March 10-11, 2011 Vibration/stability issues (2) Large weight on floor can cause tilting To estimate mass we need to identify thickness and type of material for compressor/target chamber/piping e.g. Al large target chamber 3 t Same SS target chamber can have 9 t (ρ SS /ρ Al =8/2.7)

ELI-NP The Way Ahead-Workshop March 10-11, 2011 Vacuum solutions For Ø90 cm pipe  every 2 to 5m a turbo+roughing system Roughing (mechanical): atm. to torr; turbo: to torr Vacuum line segmented with pneumatically operated gate valves Cryogenic pumps on compressor and target chambers (~10 4 l/s) Backup system on compressor/target chambers based on turbopumps (repair or regeneration of cryopumps)

ELI-NP The Way Ahead-Workshop March 10-11, 2011 Vibrations solutions Laser interferometer for measuring the micro-motion between the 2 floors (laser and experimental areas) & for alignment of large optics Large bellows in the beam line Special stands for roughing pumps (w. damping springs) Special supports for target chambers (based on polymer layers) Cryopumps instead of turbo pumps

ELI-NP The Way Ahead-Workshop March 10-11, 2011 Other issues Large flanges with windows, also large viewing windows on compressor/target chamber Filters on exhausts for containing nuclear debris Separate vacuum pumps for Target Positioner System, or instrument manipulator (eg. TIM at LANL)etc

ELI-NP The Way Ahead-Workshop March 10-11, 2011 Conclusions Prerequisite for a good design is to identify and set the system parameters Tight collaboration with laser and civil engineering groups Learn from the experience of other facilities worldwide Work closely with companies to deliver the right solution Thank you!