Project Management tools BTEC National. General planning & scheduling tools Project management software helps you manage the administration, planning.

Slides:



Advertisements
Similar presentations
Project Management Skills for QOF leads Quality and Outcomes Framework Assessor Training.
Advertisements

Project Management Techniques and tools Move mouse over arrow to enter presentation End Show.
Gantt and PERT charts. Representing and Scheduling Project Plans Gantt Charts Useful for depicting simple projects or parts of large projects Show start.
Having Fun with Gantt PERT &.
CS3500 Software Engineering Project Management (1) In 1986 one well-known software engineer (Tom DeMarco) made the simple but important observation: “You.
CPA A house is to have new carpets fitted throughout. The work involved has been divided into a number of tasks, as shown in the table.
2 Project Management  Management of work to develop and implement an innovation or change in an existing organization Examples: –New buildings –Weapon.
Copyright 2012 John Wiley & Sons, Inc. Chapter 8 Scheduling.
System Planning (Overview of Feasibility)
McGraw-Hill/Irwin ©2008 The McGraw-Hill Companies, All Rights Reserved SECTION 12.1 PROJECT MANAGEMENT.
1 B. SW Project planning & scheduling Recap from previous slide: It is important to decide on who is responsible for each activity. See Yeates & Cadle.
Project Management March 9, 2001 Dr. Richard Chung Dept. Chemical & Materials Engineering San Jose State University.
Gantt Charts and PERT Charts. Copyright © 2009 South- Western/Cengage Learning. All rights reserved. 14–2 Managing Operations Systems Planning Sheet –
Project Scheduling & Budgeting CEE 402 Engineers Without Frontiers Lecture 6 February 26, 2003.
Chapter 5 Planning. 222 Learning Objectives  Clearly define the project objective  Develop a work breakdown structure  Develop a network diagram 
Gantt and PERT charts. Representing and Scheduling Project Plans Gantt Charts Useful for depicting simple projects or parts of large projects Show start.
Copyright © Allyn & Bacon 2008 POWER PRACTICE Chapter 5 Administrative Software START This multimedia product and its contents are protected under copyright.
Switch off your Mobiles Phones or Change Profile to Silent Mode.
Critical Path Analysis By: Troy Gonsalves. Motivation  The typical reason for failure is poor project-planning  Poor planning can result in missed deadlines,
Software Project Management Task Sequencing Activity Sequencing Concepts PERT charts Critical Path Analysis.
Unit4-IT Project BTEC NATIONAL – UNIT 4 Project Management.
8-1 Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall Project Management Chapter 8.
Lecture 5 – Gantt Chart GANTT Charts Constructing GANTT Charts
Page 1 ICT in Time Management Grade 11 ICT Mrs. Ghazaal.
Project Management HNC Computing 2000 Unit 8 Quality Management Prepared by S Hargrave.
Lecture 3 Scheduling CSCI – 3350 Software Engineering II Fall 2014 Bill Pine.
Lean Project Management
Dr. Jana Jagodick Polytechnic of Namibia, 2012 Project Management Chapter 7 Project Manager’s Toolkit for Time Management.
PROJECT SCHEDULING By Deepika chaudhary. Project Scheduling Scheduling means estimation of time and resources required to complete activities and organise.
Chapter 17 Project Tracking. Objectives Identify, develop, and use project management tools to track project progress: Schedules Gantt Charts Toll Gate.
Unit4-IT Project BTEC NATIONAL – UNIT 4 Project Management MS PROJECT.
Tm&i 2010 VI.1 technology management & innovation introduction to project management (ii) project planning methods & tools.
Ch. 41 Project control. Ch. 42 Work Breakdown Structure WBS describes a break down of project goal into intermediate goals Each in turn broken down in.
1.Pareto Analysis 2.Fish Diagram 3.Gantt Chart 4.PERT Diagram 5.Job/Worksite Analysis Guide.
Project Management Formal Methods. How do you monitor a project?
More on Scheduling. Recap of Last Class Activity dependencies are shown through CPM/PERT Chart. Critical path Completion date Slack time in non-critical.
Geog 469 GIS Workshop Project Management.
8-1 Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall Project Management Chapter 8.
1 OMGT 3123 Project Management  Project Controlling  Project Management Techniques: PERT And CPM  The Framework Of PERT And CPM  Network Diagrams And.
Project Schedules Chapter 4 Applied Software Project Management, Stellman & Greene See also:
CS211 Slide 10-1 ADCS 21 Feasibility and Cost Analysis Tools Project Management Tools Alternative System Development Methodologies (Chapter 10) Tools for.
A2 Technology Product Design Systems and Control Notes DT4 - Exam.
Project Scheduling Software
Scheduling Work I love deadlines. I love the sound they make as they fly by. -- Douglas Adams.
Information Systems System Analysis 421 Chapter 3 Managing the Information Systems Project.
Project Management Inspections and Reviews 1 February.
Project Management Organization Scheduling 31 January.
Project Scheduling Class 7.
ANALISA & PERANCANGAN SISTEM Disusun Oleh : Dr. Lily Wulandari Program Pasca Sarjana Magister Sistem Informasi Universitas Gunadarma.
Project Management Concepts Gantt Chart – shows tasks as bars whose length indicates timing. PERT* chart (Network Diagram) – shows relationships between.
PERT Gantt WBS.
Chemistry careers in SMEs Introduction to project management Samantha Pugh University of Leeds.
Tools to Help  Product flow Dependencies and relationships of deliverables  Work breakdown structure The parts  PERT charts Program Evaluation and.
Managing the Information Systems Project Cont’d
What Is a Project? “A project is a temporary endeavor undertaken to create a unique product or service.” Instructor Do Solicit answers from participants.
Project Management Project Controlling
PERT & GANTT CHARTS An Introduction.
REQUIREMENTS Project management tools
Project Management and Information Security
Creating team solutions
Most commonly used methods for project management.
2nd Task of Your Project „All you have to decide, is what to do with the time that is given to you.“ J.R.R. Tollkin Prof. Dr. Christian Bleis 1 Interaktionskompetenz.
2.2 | Use Planning Tools.
Action planning: Logical activity schedule
Unit 4 Project Design, implementation and evaluation
Chapter 5 Planning
SE Tasks for a Concept Development Project
Tools for Visualization
I love the sound they make as they fly by.
CIS 210 Systems Analysis and Development
Presentation transcript:

Project Management tools BTEC National

General planning & scheduling tools Project management software helps you manage the administration, planning and scheduling of your project. You can often use the software charting facilities included in this software to produce graphical versions of your plans. Project management software has the following features: Create a task Store information about a task (e.g. who will do it, how long it will take etc) Update task information as your project changes Generate plans based on tasks Publish charts and reports to help you manage the project and to present information to the stakeholders

Gantt chart & PERT charts The common charts are Gantt charts and PERT charts A Gantt chart is a picture of how long all the tasks should take. You can use Excel to create a Gantt chart

Gantt chart & PERT charts The common charts are Gantt charts and PERT charts A PERT chart (program evaluation and review technique) shows the dependencies between tasks. It depicts the task, its duration and dependency information T = 1wk T = 2wks T = 4wks T = 2wks T = 1wk A E F A C B G D

Critical Path Methods Critical path methods identify the minimum time needed to complete a project. They show which tasks are on the critical path. This lets you, as project manager, prioritise these tasks to make the project more likely to finish on time. Critical path analysis (CPA) works on the principle that some tasks cannot start until previous tasks are finished. For example, you cannot test a program until after you have coded it. you must complete these dependent tasks in a sequence. Often tasks are not dependent on other tasks starting or finishing, so you can do these tasks in parallel.

Critical Path Methods Consider this series of tasks for a computer system. Specify and design system Code program 1 Test program 1 Code program 2 Test program 2 Test and implement system The project manager works out the dependencies and timescales and draws up the critical path (shown on next slide). From this you can see that tasks 1, 2, 3 and 6 are on the critical path. A minimum time of 21 days is needed for this project.

Critical Path Methods From this you can see that tasks 1, 2, 3 and 6 are on the critical path. A minimum time of 21 days is needed for this project. Task 1 5 days Task 2 10 days Task 3 4 days Task 6 2 days Task 5 2 days Task 4 5 days

Specialised software packages To help manage a project there are many packages available. At the simplest, there are freeware or shareware packages available from the Internet. Microsoft Project is a popular middle-of-the-range tool that can help manage a wide variety of projects. For large construction or IT projects involving very many tasks and workers, there is expensive, specialised software available.