The following tutorial demonstrates the use of MSPROJECT for Project Management which organizes and tracks the required activities. It is intended to be.

Slides:



Advertisements
Similar presentations
EZ Grade Pro Becky Koss French & Spanish Teacher Lake-Lehman Sr. High School.
Advertisements

Microsoft Project Tutorial for Chapters 6 & 7
Microsoft Project Entering and Organizing Tasks Adapted from the Microsoft Step by Step Series by Aaron Schroeder.
PERTEMUAN 3 PPSI Microsoft Project Presentation. What is a Gantt Chart? A Gantt Chart is a visual tool to help Plan, Manage, and Track a project or projects.
MS Project Tutorial EMEN. Entering Project Properties Choose File Properties Click the Summary tab You can now enter general information about the project.
Microsoft Project Tutorial for Chapters 4 & 5 This Tutorial explains how to: Build a MSP Project Network Build a Probabilistic MSP Network Use the Calendar.
Microsoft Project.
McGraw-Hill/Irwin © The McGraw-Hill Companies, All Rights Reserved Creating Gantt Charts With Microsoft Project Technology Plug-In T12.
Building Your Project Work Plan in March 2, 2007 HP Project & Portfolio Management by Dan Gallagher See NOTES page for Presentation Discussion, Tips &
Project Information: Customizing and Printing Lesson 7.
Projmgmt-1/18 DePaul University Evaluating Schedule In MicroSoft Project Instructor: David A. Lash.
Project Basics Lesson 1. Skills Matrix SkillsMatrix Skill Start Microsoft Project Standard Create a project planOpen a new project plan Specify a start.
Q7503, Principles of Project Management, Fall Software Project Management Session 6: MS-Project Intro & Mid-term Exam.
Using MS Project To draw a Network diagram. Add tasks Add the 8 tasks listed for making a cup of tea. Add the duration of each –Note: MS Project doesn’t.
Projmgmt-1/15 Depaul University Intro To MicroSoft Project Instructor: David A. Lash.
Projmgmt-1/23 DePaul University Tracking the Progress of Your Project In MicroSoft Project Instructor: David A. Lash.
Starting a New Project Cheryl A. Wilhelmsen Lee Ostrom.
Microsoft Project Presentation By Corey Johnson 10/11/00.
Project Plan Formatting – Fundamentals Lesson 6. Skills Matrix SkillsMatrix Skill Format a Gantt ChartModify the Gantt Chart using the Bar Styles dialog.
Copyright © Software Process Group 1 Software Process Group Microsoft Project Tutorial Steve Meyers
Fine-Tuning Tasks Lesson 11. Skills Matrix SkillsMatrix Skill Manage task constraints and dependencies Explore the effects of constraints and dependencies.
Microsoft Office Project 2007: Managing Projects.
Managing Multiple Projects Lesson 9. Skills Matrix SkillsMatrix Skill Manage consolidated projectsCreate a consolidated project plan Create dependencies.
Project Management Software Tools Cheryl A. Wilhelmsen Lee Ostrom.
MS-Project tutorial Phongphan Danphitsanuphan CSSE – Computer Science Dept University of Southern California.
USING MS PROJECT 2010 Project management software programs such as Microsoft Project 2010 can be used for developing the project schedule and budget, and.
Q7503, Fall Software Project Management Session 9: Project Control MS Project.
SWE 466- Resources Tutorial # 2. So far… TasksMilestones Summary Tasks Duration of the tasks.
Tracking progress on tasks and assignments TUTORIAL # 3.
Refining Your Project Plan Lesson 4. Skills Matrix SkillsMatrix Skill Apply a task calendar to an individual task Change task typesChange scheduling formula.
Microsoft Project – Tutorial 2 Project Goal network company computers to easily share resources within a time frame of three months and within a budget.
Abeer Bin Humaid. Project management is “the application of knowledge, skills, tools, and techniques to project activities in order to meet project requirements”
 Starting Excel 2003  Using Help  Workbook Management  Cursor Management  Manipulating Data  Using Formulae and Functions  Formatting Spreadsheet.
Lecture 1 Saima Gul. What is a Project? A Project is a job that has a beginning and an end (time), a specified outcome ( scope) at a stated level of quality.
11-1 ELC 347 project management Snow Day. Committed to Shaping the Next Generation of IT Experts. Essentials Microsoft Project 2003 Dawn Parrish Wood.
The Project Plan IT Project Management COSC
MS project Abeer Bin Humaid. What is project management? Project management is “the application of knowledge, skills, tools, and techniques to project.
*** CONFIDENTIAL *** © Toshiba Corporation 2008 Confidential Creating Report Templates.
Microsoft Project Tutorial for Chapters 4 & 5 This Tutorial explains how to: Build a MSP Project Network Build a Probabilistic MSP Network Use the Calendar.
TUTORIAL 2 INSTRUCTOR: HANIF ULLAH ID: OFFICE #: 2029 DATE: 19/02/2012 Introduction to MS Project 2007.
SOFTWARE PROJECT MGT. SESSION # 3– LAB MANUAL AMAN QUADRI
MS Project Tutorial 1 Goal: Introduce you to the basic idea of MS Project The basic idea is to answer the following questions and record the answers as.
PROJECT MANAGEMENT 3RD YEAR UNDERGRADUATE UNIT U13451 PRMAN DL Tutor: Kathy Parker WEEK FIVE Adapted from slides by Dr Philip J. Scott MSc PhD FBCS CITP.
ELC 347 project management
Advanced Project Plan Tracking Lesson 15. Skills Matrix SkillsMatrix Skill Record actual start, finish, and duration values of tasks Enter actual start.
Microsoft Project – Tutorial 4 Leveling Overallocations In some cases, a resource could be assigned more work in a given time period than it has working.
Establishing Resources Lesson 2. Skills Matrix SkillsMatrix Skill Establish people resourcesEstablish individual people resources Establish a resource.
Title of presentation goes here Name of presenter Location/date © 2006 MPA. All rights reserved. Organizing Tasks Using Outlining and Work Breakdown Structures.
1 Software Project Management Session 6: MS-Project Intro & Mid-term Exam.
Microsoft Project Tutorial Jesal Bhuta
6. TRACKING PROGRESS. OBJECTIVES Save current schedule values in a plan as a baseline. Record progress on tasks through a specific date. Record tasks’
DECISION MODELING WITH MICROSOFT EXCEL Chapter 14 Copyright 2001 Prentice Hall Publishers and Ardith E. Baker Part 3 andand PERT CPM.
Project Plan Tracking – Fundamentals Lesson 8. Skills Matrix SkillsMatrix Skill Establish a project baseline Track a project as scheduled.
Introduction to MS Project.  IN THIS EXERCISE, YOU’LL START PROJECT PROFESSIONAL Starting Project Professional.
Project Setup and Execution For PMPlan Enterprise Presented by AlNik Solutions Copyright ©
Smart Center. Welcome to Smart Center Please logon with your Medical Domain Account.
Microsoft Project Tutorial for CSCI 577 Fall 2006 Jesal Bhuta
Microsoft Project 2010 ® Tutorial 5: Tracking Progress and Closing the Project.
Microsoft Project – Tutorial 3 Creating a Report open LAN-3 from the tutorials folder save the file as LAN-3-your initials click Reports > Reports double-click.
© 2008 Prentice HallAppendix A -1 Introduction to Project Management Appendix Microsoft Project Tutorial Information Systems Project Management: A Process.
Using MS-Project INFS MS-Project: 3 Major Parts 1. Project Planning 2. Project Execution & Tracking 3. Project Reporting.
New Task Properties UI Change most tabs to Property/Value grids Provide option to dock Task Properties on the side (vertical layout) or on the bottom (horizontal.
Microsoft Project 101: How to Build a Project Plan
WHAT IS A GANTT CHART.
Software project mgt. session # 3– lab manual.
PROJECT MANAGEMENT Bill Biddle.
Information System Analysis
The following tutorial demonstrates the use of MSPROJECT for Project Management which organizes and tracks the required activities. It is intended to be.
Expedite Project Updates Using a Custom Status View
Microsoft Project 2010 Demo Part 3
Presentation transcript:

The following tutorial demonstrates the use of MSPROJECT for Project Management which organizes and tracks the required activities. It is intended to be used in “getting started” with the tool To use MSPROJECT for Project Management we: Define the required TASKS Establish the sequence and various DEPENDENCIES Make any required modifications to the CALENDAR Assign RESOURCES to complete the TASKS Once a satisfactory schedule has been developed, it is BASELINED so the MSPROJECT has a “history” it can employ in displays Finally, as TASKS are worked on, % COMPLETION is entered for each TASK Other functions are available which enable the user to adjust the schedule to optimize the chance for success. These include critical path analysis, resource leveling and many powerful Project Management tools.

Open application MSPROJECT and then list all known tasks and force all MILESTONES to be ZERO Days by clicking on the Duration cell and decrementing it to zero. Note that we have planned ahead by starting to create two summary task rows. Next we will indent subtasks.

Select Tasks1P-Milestone 5P and then click on INDENT to create subtasks. Repeat for Tasks1D – Milestone 5D. The INDENT is the GREEN right facing arrow in upper left of screen. Note display change with INDENTATION. INDENT

Create some initial dependencies by first selecting Task 1P, then while holding down the CNTRL key, select Task 2P and Milestone 1_2P and then click on Link Task, the “chain link” icon in the tool bar above. Note new “arrows” in display. Link Tasks

Repeat for Task 3P, Task 5P and Milestone 5 and click on Link Tasks. Repeat for Task 4P and Task 5P and click on Link Tasks.

Create more dependencies by first selecting Milestone 1_2P, then while holding down the CNTRL key, select Summary Task for Design and click on Link Tasks. Repeat for Milestone 5P and Summary Task for Design and click on Link Task. Now the Summary Task for Design is dependant upon completion of the two major Milestones under Summary Task for Planning !

Complete all dependencies under Summary Task for Design. Select Task 1D, then Task 2D, then Task 4D,then Task 5D and finally Milestone 5D and then click on Link Tasks. Repeat for Task 3D and Task4D.

Select Tools/Change Work Time – then HIGHLIGHT the Column for Saturday and then select Nondefault working time (box) followed by OK. This makes MON-SAT work days for the schedule. We decided Sunday is a day of rest!!

We now enter the duration estimates for each subtask in total hours of work required by clicking on the appropriate duration cell and entering the data. Task 1P is set to 10 hours by typing 10h. Note that the schedule now has automatically moved out in time. Next we will add resources (people). Initially we add our staff names… Tom, Dick, Harry & Janet by clicking on the resources icon in the toolbar above. As we add resources to each task, its duration will change. Resources

We have now added our resources… a first cut. After that we can now fine tune the schedule… longer or shorter as required by modifying the resource levels. Or we can actually adjust the duration directly via the duration cell. Once we are happy with the results we should “BASELINE“ the schedule which means that MSPROJECT will remember what the schedule looks like at this point. We BASELINE by selecting Tools/Tracking/Save Baseline and select “Entire Project” followed by OK.

We now change our “View” to Tracking Gantt from our original setting of Gant Chart by selecting View/Tracking Gantt. To show the benefit of this chart which employs the established BASELINE, we will change Task 5D from 4 to 24 hours.

Note how the chart displays the change

And finally we opened Task 4D and marked it as 60% complete to demonstrate MSPROJECT’s tracking capability. Note display change.