Chandra Users’ Committee CXC Manager’s Status Report For the period April 09 – October 09 Edward Mattison CXC Deputy Manager 29 October 2009.

Slides:



Advertisements
Similar presentations
THE NSF BUDGET Overview of Agency Funding Processes Presented by Beth Blue National Science Foundation Office of Budget, Finance, and Award Management.
Advertisements

Master Plan. Citizens’ Health Care Working Group Master Plan November 2005.
Overall Office Assessment GAR RateRate Current Issues: (results of analysis) Low violent crime rates demonstrate that people living and working on Picatinny.
Line Efficiency     Percentage Month Today’s Date
Unit Number Oct 2011 Nov 2011 Dec 2011 Jan 2012 Feb 2012 Mar 2012 Apr 2012 May 2012 Jun 2012 Jul 2012 Aug 2012 Sep (3/4 Unit) 7 8 Units.
CXC Manager’s Status Report For the period Oct 05 – Mar 06 Chandra Users’ Committee Meeting Roger Brissenden 5 April 2006.
25 Jan 2005CUC Meeting CXC-Sponsored Workshops & Symposia Paul Green For the Chandra Directors Office.
19 Oct 2005Chandra Users' Committee Cycle 7 Peer Review: June 2005  747 proposals, 12 panels, 101 reviewers  Hilton, Logan Airport.
Chandra Users’ Committee CXC Manager’s Status Report For the period October 06 – March 07 Edward Mattison CXC Deputy Manager 25 April 2007.
Chandra Users’ Committee CXC Manager’s Status Report For the period October 08 – March 09 Roger Brissenden CXC Manager 06 April 2008.
Chandra Users’ Committee CXC Manager’s Status Report For the period April 08 – September 08 Roger Brissenden CXC Manager 15 October 2008.
CXC Manager’s Status Report Chandra Users’ Committee Meeting Roger J. Brissenden 12 January 2004.
CXC Manager’s Status Report Chandra Users’ Committee Meeting Roger J. Brissenden 25 January 2005.
Cxc CHANDRA X-RAY OBSERVATORY Press Events 39 Press Events 3 Space Science Updates - Perseus Cluster: Chandra "Hears" a Black Hole - RXJ : Star Being.
Chandra Users’ Committee, Oct 2009 Chandra Director’s Office Cycle 11 Peer Review Proposal Numbers:  668 submitted proposals  *5.6 oversubscribed.
CXC Manager’s Status Report For the period April 06 – September 06 Chandra Users’ Committee Meeting Roger Brissenden 17 October 2006.
Chandra Users’ Committee, Oct 2006 Chandra Director’s Office Chandra Director’s Office Proposal Cycle 8  725 submitted proposals  *6.4 oversubscribed.
Chandra Users’ Committee CXC Manager’s Status Report For the period April 07 – September 07 Roger Brissenden CXC Manager 19 September 2007.
Users' Committee, 25 Oct 2010 Chandra Director’s Office Cycle 12 Peer Review  June 2010, Hilton, Logan Airport  No major changes in Cycle 12 
CXC Manager’s Status Report Chandra Users’ Committee Meeting Edward M. Mattison 19 October 2005.
CXC Manager’s Status Report Chandra User Committee Meeting Roger J. Brissenden 25 June 2002.
Director's Office Chandra Users’ Committee, Sept 2007 Chandra Cycle 9  661 submitted proposals  *5.5 oversubscribed (based on time)  48 LP, 10.
CXC Chandra X-ray Observatory Operations. CXC Overview 1. Mission and Observatory Description 2. Chandra Operations 3. Chandra X-ray Center Architecture.
Chandra Users’ Committee, Oct 2008 Chandra Director’s Office Chandra Director’s Office Proposal Cycle 10  639 submitted proposals  *5.6 oversubscribed.
CXC Chandra Users' Committee Chandra Director’s Office Proposal Cycle proposals *6.4 oversubscribed (based on time) GTO for review: due 3 rd April.
CXC Manager’s Status Report Chandra Users’ Committee Meeting Edward M. Mattison 29 June 2004.
Hazardous Materials Emergency Preparedness Grant Oregon SERC/LEPC Conference 2015 Oregon Office of State Fire Marshal 1.
Implementing a Calibration Management System Cory Otto Principal Metrology Engineer, Boston Scientific 10 October 2012.
CXC Implementing 2007 NRC Portals of the Universe Report Chandra X-ray Center Recommended Best Practices Roger Brissenden and Belinda Wilkes 25 April 2012.
Advancing Excellence in Health Care 2.0 ETA December 2010 Carol Sniegoski AHRQ Annual Conference September 27, 2010 Preview:
Chandra Users’ Committee CXC Manager’s Status Report For the period October 2010 – September 2011 Edward Mattison CXC Deputy Manager 13 October 2011.
Chandra Users’ Committee CXC Manager’s Status Report For the period October 2011 – September 2012 Roger Brissenden CXC Manager 10 October 2012.
PDS Geosciences Node Page 1 Archiving Mars Mission Data Sets with the Planetary Data System Report to MEPAG Edward A. Guinness Dept. of Earth and Planetary.
Chandra Users’ Committee CXC Manager’s Status Report For the period October 2009 – April 2010 Roger Brissenden CXC Manager 27 April 2009.
Chandra Users’ Committee CXC Manager’s Status Report For the period May 2010 – October 2010 Roger Brissenden CXC Manager 25 October 2010.
Linda Washington, M.S. U.S. DEPARTMENT OF HEALTH AND HUMAN SERVICES Centers for Disease Control and Prevention National Center for Health Statistics Marketing.
Development Report Engineering Node August 2006
Contract Year 1 Review IMT Tilt Thompkins MOS - NCSA 15 May 2002.
Chandra Users’ Committee CXC Manager’s Status Report For the period October 2013 – September 2014 Roger Brissenden CXC Manager 23 October 2014.
Chandra Users’ Committee CXC Manager’s Status Report For the period October 2014 – September 2015 Edward Mattison CXC Deputy Manager 29 September 2015.
ProjectImpactResourcesDeadlineResourcesDeadline Forecast Plan Time Resources Risk 001xx 002xx 003xx 004xx 005xx 006xx 007xx TotalXX Example 1: Portfolio.
Jan 2016 Solar Lunar Data.
Roger Brissenden CXC Manager 22 October 2013
SPF MAG Quarterly Report – Feb 2015
Committee on Information Technology
Transition Implementation Status Reporting
Chandra Users’ Committee CXC Manager’s Status Report
Milestones & Deliverables BENE III period Jan 06 - Jun07
Average Monthly Temperature and Rainfall
ctclink Steering Committee
Gantt Chart Enter Year Here Activities Jan Feb Mar Apr May Jun Jul Aug
Q1 Q2 Q3 Q4 PRODUCT ROADMAP TITLE Roadmap Tagline MILESTONE MILESTONE
FY 2019 Close Schedule Bi-Weekly Payroll governs close schedule
Calendar Year 2009 Insure Oklahoma Total & Projected Enrollment
Electricity Cost and Use – FY 2016 and FY 2017
A Climate Study of Daily Temperature Change From the Previous Day
Text for section 1 1 Text for section 2 2 Text for section 3 3
Text for section 1 1 Text for section 2 2 Text for section 3 3
Text for section 1 1 Text for section 2 2 Text for section 3 3
Text for section 1 1 Text for section 2 2 Text for section 3 3
Q1 Q2 Q3 Q4 PRODUCT ROADMAP TITLE Roadmap Tagline MILESTONE MILESTONE
Text for section 1 1 Text for section 2 2 Text for section 3 3
Text for section 1 1 Text for section 2 2 Text for section 3 3
Text for section 1 1 Text for section 2 2 Text for section 3 3
Text for section 1 1 Text for section 2 2 Text for section 3 3
Text for section 1 1 Text for section 2 2 Text for section 3 3
Text for section 1 1 Text for section 2 2 Text for section 3 3
State of the Center 5/22/2019 Daad Rizk, Ed.D – Director
Q1 Q2 Q3 Q4 PRODUCT ROADMAP TITLE Roadmap Tagline MILESTONE MILESTONE
Catalog Production Timeline
Presentation transcript:

Chandra Users’ Committee CXC Manager’s Status Report For the period April 09 – October 09 Edward Mattison CXC Deputy Manager 29 October 2009

CXC Status Report/CUCPage 2 Topics Program Level Status –Program Management –Spacecraft –Science Instruments and Calibration –Mission Planning –OCC –Data Processing –CXCDS –Chandra Director’s Office –Education and Public Outreach Mission Metrics Chandra Grant Awards

29 October 2009CXC Status Report/CUCPage 3 Top Level Summary Spacecraft and instruments are performing superbly The CXC contract extension for up to 10 additional years and $573M is expected to be signed in mid- November

29 October 2009CXC Status Report/CUCPage 4 Program Level Status – Program Management Budget –The CXC’s budget is on track with the FY09 Operating Plan CXC contract extension –SAO submitted (in July) the requested proposal to extend the CXC contract for up to 10 years –We are currently working with MSFC and subcontractors to resolve audit questions and to deal with NGST rate changes that resulted from NGST’s corporate reorganization –Expect signed contract extension in mid-November

29 October 2009CXC Status Report/CUCPage 5 Program Level Status – Program Management Facilities –SAO and NGST studied the feasibility of moving the OCC from Kendall Square to Cambridge Discovery Park, to save ~$1M/yr –Produced detailed plan and schedule –After considering benefits vs. risk, MSFC declined to approved the move Reviews and Conferences –Peer Review (6/22/09) –Supernova Remnant workshop (7/8/09) –Quarterly review (9/2/09) –Calibration review (9/21/09) –Chandra’s First Decade of Discovery (9/22-25/09) –Einstein Fellows Symposium (10/27/09)

29 October 2009CXC Status Report/CUCPage 6 Program Level Status – CXC Organization

29 October 2009CXC Status Report/CUCPage 7 Program Level Status – Operations Spacecraft –Continues to operate extremely well overall –Nominal passages through summer eclipse season Science Instruments –Instruments are operating extremely well

29 October 2009CXC Status Report/CUCPage 8 Program Level Status – Operations Anomalies –Momentum Unloading Propulsion System (MUPS) pressure drop Propellant pressure reading decreased abruptly 7/19 Cause: Pressure transducer operates incorrectly Impact: Benign; Demonstrated CXC’s skill in handling anomaly situation –Grating status switch operates unexpectedly HETG move flag set to ‘failed’ 7/7/09 (grating move was okay) Cause: Previously-failed microswitch unexpectedly came to life Impact: Benign; Updated software to ignore switch state –Incorrect command sequence uploaded Cause: Operator error 8/28 Impact: Benign (but could have led to safing action if not identified); Updated procedures to prevent recurrence

29 October 2009CXC Status Report/CUCPage 9 Program Level Status – Operations Mission Planning: Load-interrupting TOOs –No load-interrupting TOOs during this period –Several loads were replanned to respond to anomalous conditions Data Processing –Automatic processing is current; mean time from end of observation to delivery to user remains at about one day

29 October 2009CXC Status Report/CUCPage 10 Program Level Status – Operations CXC Data System Releases VersionDateMain contents DS /24CfP11 proposal review support DS 8.07/14Migrate operations to Solaris 10 DS 8.19/16Migrate CDO, mission planning operations to Linux CIAO /20Port to Solaris 10; release Level 3 tools CAT /21CSCview, novice user fixes, VO cone search GoogleEarth1.0 6/26Web interface to CSC field of view & images CAT /18VO cone search verbosity fix CSC = Chandra Source Catalog VO = Virtual Observatory

29 October 2009CXC Status Report/CUCPage 11 Program Level Status – Operations Calibration Database (CalDB) Releases –CalDB /7ACIS T-gain epoch 37 –CalDB /17ACIS T-gain epoch 38 GO and Fellows Program, CXC Director’s Office –GO peer review 6/22; 668 proposals submitted, 207 approved –Einstein Fellows call for proposal posted; proposals due 11/5 –Grant issuance is current; average time to award < 3 weeks Education and Public Outreach –CXC’s “Beautiful Universe” HD podcast series won the Communicator Award of Excellence, the professional peer-judged award by the same group that oversees the Webbys –“From Earth to the Universe, ” the International Year of Astronomy exhibit developed by the CXC’s EPO group, has been exhibited in over 200 locations in 65 countries, including close to 40 installations in a variety of settings in the US. See

29 October 2009CXC Status Report/CUCPage 12 Mission Metrics MUPS Fuel Usage

29 October 2009CXC Status Report/CUCPage 13 Mission Metrics Thruster Warm Starts

29 October 2009CXC Status Report/CUCPage 14 Mission Metrics Observing Efficiency

29 October 2009CXC Status Report/CUCPage 15 Data Delivery Effectiveness As of middle of following month As of 10/8/09 MonthNumber of Obs Days to Data DeliveryNumber Deliv Number Outstanding Number Deliv Number Outstanding Comments MinAvgMax Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep

29 October 2009CXC Status Report/CUCPage 16 Grant Award Effectiveness Month of Data Delivery Federal Grants (1,3) SAO Grants (2) As of middle of following month As of 10/8/09 Non-Federal Grants (3) No. Grants Awarded No. Outstanding Avg days to award (4) No. Grants Awarded No. Outstanding Outstanding Awards Proposal no, Comments Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep (1)(1) Grants awarded to scientists at Federal institutions as interagency transfers through MSFC. (2)(2) Grants awarded to scientists at non-Federal institutions through SAO Contracts and Grants Department. (3)(3) Number of grants eligible for award, for which data were delivered to the observer in the month. (4)(4) Average days from data delivery to grant award to observer.