9-1
9-2 Chapter Nine Project Scheduling
9-3 Gantt Chart for Five Activities (Refer to Example 9.1) Fig. 9-1
9-4 Project Network for Example 9.2 Fig. 9-2
9-5 Incorrect Network Representation for Example 9.3 Fig. 9-3
9-6 Correct Network Representation for Example 9.3 Fig. 9-4
9-7 Network for Example 9.4 Fig. 9-5
9-8 Network for Example 9.4: Activity-on-Node Representation Fig. 9-6
9-9 Gantt Chart for Software Development Project of Example 9.4 Fig. 9-7
9-10 Project Network for Problem 4 Fig. 9-8
9-11 Network for Problem 5 Fig. 9-9
9-12 The CPM Cost-Time Linear Model Fig. 9-10
9-13 Optimal Project Completion Time Fig. 9-11
9-14 Probability Density of Activity Time Fig. 9-12
9-15 Uniform Density of Activity Times Fig. 9-13
9-16 Answer to Example 9.7, Part 1 Fig. 9-14
9-17 Answer to Example 9.7, Part 2 Fig. 9-15
9-18 Answer to Example 9.7, Part 3 Fig. 9-16
9-19 Network for PERT Example 9.8 Fig. 9-17
9-20 Project Network (for Problem 20) Fig. 9-18
9-21 Gantt Chart for Modified Schedule for Example 9.9 Fig. 9-19
9-22 Two Projects Sharing Two Resources Fig. 9-20
9-23 Load Profiles for RAM and Permanent Memory (Refer to Example 9.10) Fig. 9-21
9-24 Project Network (for Problem 25) Fig. 9-22