Step IV Infrastructure update STFC Tim Hayler Eddie Holtom Norbert Collomb Graham Stokes 14 th December 2011 MICO170 meeting 1Tim Hayler.

Slides:



Advertisements
Similar presentations
1 UK Project Alan Grant, STFC. Finance How savings are made Update on stepIV position Milestones Critical Path - stepIV Concerns 2.
Advertisements

Project Managers Update Roy Preece Particle Physics Department, STFC MICE Video Conference, 18 th September 2014.
1 MICE CM31 Key schedule drivers for Step IV Schedule table Milestone summary Comment on Step V Step VI Andy Nichols, STFC, 3/11/11.
Detector Systems Update MICO March 17, MICE Detector Systems  CKOV u Mississippi RAL  TOF0/1 u Hamamatsu PMT assemblies show an increasing.
MICE Hall – South Mezzanine Jason Tarrant - STFC l Contents »Device checks with current South Mezzanine »South Mezzanine change summary »Conclusion.
CM30 University of Oxford Engineering session Peter Ford Tim Hayler Eddie Holtom Roy Preece Jason Tarrant Steve Virostek.
MICE Collaboration meeting May 31 st – June 3 rd 2009 RAL Tim Hayler, Andy Lintern DRAFT SEQUENCE OF EVENTS STEPS
Spectrometer Solenoids MICO 146 Steve Virostek LBNL June 6, 2011.
1 MICE PM Report General Update –Phase I civil engineering –R5.2 in June –Phase II design work –Phase II hardware –A few questions –Schedule, milestones.
Spectrometer Solenoid Report and Coupling Coil Update Michael S. Zisman MICE Operations Manager Center for Beam Physics Lawrence Berkeley National Laboratory.
Project Report Paul Drumm CM15, FNAL June MICE Schedule Overview First beam September/October 2007 –Shutdown from January 2007 –Eight months for.
Spectrometer Solenoid Fabrication Update Steve Virostek Lawrence Berkeley National Lab MICE CM23 at ICST, Harbin January 14, 2009.
1 MICE Radiation Shutter Description Present status Plans, schedule and remaining work MICE CM26, 24-27th March, 2010.
MICE Video Meeting, 10 Jan 081 Spectrometer Magnet Progress Michael A. Green Lawrence Berkeley Laboratory.
1 MICE PM Report Installations to date Future installation work Preparations for Phase Two Target status MICE Video Conference, 22nd May, 2008.
1 Status of infrastructure MICE Video Conference, August 17, 2005 Yury Ivanyushenkov Applied Science Division, Engineering and Instrumentation Department.
Detector Systems Update MICO March 10, MICE Detector Systems  CKOV u No update  TOF0/1 u Tests with laser injection system progressing. u Tests.
Update Hardware for conductive cooling of the quench resistors has been fabricated at LBNL. Preparation for installation to start this week. Installation.
Detector Systems Update MICO Feb 25, MICE Detector Systems  CKOV u CKOV installation planned during March shutdown u Cable issues resolved. Geneva.
An updated Baseline Design for MICE From proposal to technical reference Paul Drumm, Dec 2003.
Progress status of the Cherenkov / TOF support stand & TOF Shielding cage.
RF Cavity / Coupling Coil Module
1 Summary of MICE beamline & hall installations This is a very rough summary of the progress since mid-December Richard Apsimon & Andy Nichols MICO meeting.
Alan Grant OsC 30/4/ UK Project Finance & Schedule.
1 MICE PM Report Phase One installations to date Phase One remaining items Progress with Phase Two Phase Two planning sequence Worries Don’t have time.
1 MICE CM32 Summary Scheduling and planning; aims for this year Schedule update Main schedule drivers Keeping us on schedule Comment on Steps V & VI Detail.
MICE RFCC Module Update Allan DeMello Lawrence Berkeley National Laboratory MAP Winter Collaboration Meeting at JLab, Virginia February 28, 2011.
1 MICE - INFRASTRUCTURE MICO meeting 7 th February 2008 Tim Hayler.
1 UK PM Report Costs & Schedule Alan Grant, STFC.
MICE Integration Engineering Jason Tarrant - STFC l Contents »South Mezzanine change summary »Integration Envelope Model »A/C Move »Maus Geometry »AFC.
Preparations in the MICE hall Video Conference 25 th June 09 Tim Hayler Andy Lintern Peter Lau Geoff Barber.
MICE Coupling Coil Update Steve Virostek for Allan DeMello Lawrence Berkeley National Laboratory MICO January 23, 2013 January 23, 2013.
Status of the MICE Project & Dashboard MICE Project Board 14 th November 2013 Roy Preece.
PRY Implementation - Contents l Fit with Experimental Devices (& services connections) l Fit with Tracker Cryo l Fit with Floor & Trench l Fit with Mezzanine.
Spectrometer Solenoid Fabrication & Testing Update Steve Virostek Lawrence Berkeley National Lab MICE CM25 at RAL November 6, 2009.
Spectrometer Solenoid Fabrication Status and Schedule Steve Virostek Lawrence Berkeley National Lab MICE RAL October 20, 2008.
MICE FAC Alain Blondel 21 september   MICE The International Muon Ionization Cooling Experiment BRIEF STATUS OF MICE.
MICE RFCC Module Update Allan DeMello Lawrence Berkeley National Laboratory MICE CM29 at RAL, UK February 17, 2011.
Spectrometer Solenoid Schedule MICE Schedule Review May 23 rd 2011 Roy Preece (STFC RAL, LBNL)
1 MICE Beamline Installation, status & plans Contents: Upstream & Target, BPM Decay solenoid DSA, D2, Q4,5,6 cKOV support Q7,8,9 Open issues & concerns.
UK Update Package Managers Meeting 001 Roy Preece 13 th January 2014.
MICE Project Report Alan Bross (for Paul Drumm). Project Issues ● Key dates: – ISIS Synchrotron start-up scheduled for 1st August ● Shielded area around.
CM27 – 8 th July 2010 LH2 System Progress and Future Plans M Hills T Bradshaw M Courthold I Mullacrane P Warburton.
Spectrometer Solenoid Fabrication Status and Schedule RF Cavity / Coupling Coil Module Plan and Progress Steve Virostek Lawrence Berkeley National Lab.
Spectrometer Solenoid Fabrication Update Steve Virostek Lawrence Berkeley National Lab NFMCC at LBNL January 25, 2009.
Pre-CM33 schedule planning SuperMICO meeting, June 6th Motivation: For all of us to understand the main drivers behind the top-level MICE schedule So that.
OsC mtg 24/4/2014 OsC mtg Alan Grant. 2 OsC mtg 24/4/ MICE Finances - Forward Look.
Muon Ionization Cooling Experiment Update 1Alan Bross AEM October 14, 2013.
1 UK PM Report Costs & Schedule Alan Grant, STFC.
Status of the MICE Construction Project Resource Loaded Schedule Review 29 th April 2014 Roy Preece.
1 Status of infrastructure MICE Collaboration Meeting, Frascati, June 26-29, 2005 Yury Ivanyushenkov Applied Science Division, Engineering and Instrumentation.
1 Project Infrastructure for steps I-III Tim Hayler, STFC – RAL MICE Collaboration Meeting, RAL, nd October 2008.
OsC mtg 15/10/2014 MICE Step IV Alan Grant. Content Step IV – Construction Status – Finances – Schedule – Risks – Summary 2.
Technical Board Summary Alan Bross MICE CM17 CERN February 25, 2007.
1 UK Project Roy Preece – STFC Alan Grant, STFC. Finance Staffing Update on stepIV position Milestones Critical Path – stepIV Magnetic field mitigation.
1 MICE PM Report Phase One installations to date Phase One remaining items Progress with Phase Two Worries Don’t have time for a detailed status report,
MICE Construction Project Update: SSs, PRY, Cavities, Tracker… 1MAP Friday Meeting – January 30, 2015 Alan Bross.
US Construction Project: SSs, PRY, Cavities and test program 1.
Schedule to completion, Risk and Critical Interfaces Roy Preece STFC RAL RLSR 16 th April 2015.
Schedule and Milestones Roy Preece STFC RAL FAC 17 th April 2015.
1 UK Project Finance & Schedule. Overview Finance  Budget Setting 2013/14  June Finance  Forward look to complete stepVI Schedule  Overview 2.
1 MICE CM25 Engineering Session Summary Contents: Infrastructure Diffuser Coupling Coils Radiation Shutter AFC module EMR Andy Nichols, STFC, 4-7 th November.
Radiation Shutter Re-Purposing Roy Preece STFC RAL 18 th December 2014.
Integration of the Spectrometer Solenoid Magnets
Status of the MICE Construction Project
MICE Partial Return Yoke Mechanical Design
MICE CM31 Schedule summary
Spectrometer Solenoid Fabrication Status and Schedule
Far Detector Activities Late 2017 – Early 2018
Introduction Jason Tarrant – Integration Engineering Step IV Removal
Presentation transcript:

Step IV Infrastructure update STFC Tim Hayler Eddie Holtom Norbert Collomb Graham Stokes 14 th December 2011 MICO170 meeting 1Tim Hayler

MICE major Infrastructure milestones TaskBaselineStatus Downstream spectrometer solenoid base plate installation complete 31/12/11Complete He window manufacture complete 30/6/12Detail drawings complete, currently out for Quotation. TOF cage and Virostek plate bracket design complete 31/12/11Detail drawings complete, currently out for Quotation AFC rolling platforms tested31/12/11Complete Radiation shield manufacture and testing complete 30/3/12Design review held at the Technical board meeting 21 st November, some open issues. Ready for AFC & SS installation 30/3/12Depends on the MICE hall schedule of events 2Tim Hayler

Downstream spectrometer solenoid base plate installation complete All step IV base plates installed: Upstream spectrometer base plate (in beam and out of beam) AFC base plate (in beam and out of beam) Downstream spectrometer base plate (in beam only, there will be no possibility of moving the downstream spectrometer out of beam) 3Tim Hayler

He window manufacture, currently out for quotation 4Tim Hayler

TOF cage and Virostek plate bracket design complete Detail drawings of the bracket design are complete. We have worked closely with the Spectrometer team to make sure all the necessary compliance is in the design e.g. The way the brackets fasten to the Spectrometer and positioning of the TOF cage. Currently going through the tendering process. Expect delivery in march Tim Hayler

TOF cage and Virostek plate test support stand Support frame to test: The bracket assembly to the TOF cage and Virostek plate. TOF detector assembly, movement of the detector on the sliding mechanism. The mechanical arm for removing the split ring Expect the need to do some re-work on the Virostek plates, split rings, drill and tap holes, some machining Expect to start the build in March Tim Hayler

AFC rolling platform tests complete Testing specification for the MICE Moving Platform: Ensure the platform raises and lowers and moves horizontally Leak check/pressure drop check (Hydraulic system) Ensure the platform raises sufficiently to permit moving the unit without interference Visual inspection of components under load regarding deformation There are no unforeseen failures of components The moving of the platform along its intended path 7Tim Hayler

AFC rolling platform tests complete 4 tonne load test done at Daresbury Lab Hydraulic jacks raise the platform. Roller stakes move the platform in and out of the beam. 8Tim Hayler Final testing needs to be done in the MICE hall early 2012

The Radiation Shield The review presentation is on the technical board website, meeting minutes 21 st November Tim Hayler

Actions from the radiation shield review ActionDateResponsibleStatus A test plan devised for all operating scenarios (in vacuum) 02/Jan/2012Norbert Collomb WIP Manual method to open and close the shutter doors 02/Jan/2012Norbert Collomb WIP Add radiation monitor to the design 01/Feb/2012Tim Hayler and Norbert Collomb Need specification from the collaboration 10Tim Hayler

Spectrometer Solenoid stand Tim Hayler11 Support frame design is being worked on at RAL with close collaboration with the Spectrometer team

Spectrometer Solenoid stand Tim Hayler12 The frame will be built in the UK and installed in the MICE hall as part of the Step IV build The Spectrometer team will now provide the SS with just the four support feet shown. This helps with shipping issues.

Local magnetic shielding for the MICE hall compressors and beyond Tim Hayler13 Prototype being made in mild steel for a fit check

Ready for AFC and SS installation 30/03/2011 The readiness date for the AFC and SS installation is very much dependant on the MICE hall schedule of events. We want to install all the moving platforms for step IV Can we move the KL detector downstream to progress the Engineering build in the first SS position? First raised at the TB, 21 st Nov meeting, slides by Ken Long Are we taking beam in the first quarter of 2012? What is the Hydrogen project doing? What other work is scheduled for the first quarter 2012? In building up the Infrastructure we would expect unknowns, items lost and unforeseen events. It would be very useful to start the work in January. Tim Hayler14