Development of the Wastewater Collection and Treatment System in Szombathely County Town Implementation of sewage-sludge Composting Plant 2003/HU/16/P/PE/021.

Slides:



Advertisements
Similar presentations
Stanlick Sewer Treatment Plant Upgrade Implementation Date: September 1, 2008.
Advertisements

Floyd County Board of Commissioners Special Town Hall Meeting Topic: Update on status of Georgetown WWTP.
PRESENTATION TO THE SELECT COMMITTEE ON APPROPRIATION 19 OCTOBER 2010.
Arrangements regarding ECP 2014–2020 implementation 1.Implementation of the Republic of Slovenia Budget Act Specific section for the period:
Development of the Wastewater Collection and Treatment System in Szombathely County Town Reconstruction and Upgrading Works of the Wastewater Treatment.
Chubaka Producciones Presenta :.
HR 08 IB SPP 02 TWINNING PROJECT “ENHANCEMENT OF CAPACITY FOR EFFECTIVE MANAGEMENT OF EU COHESION POLICY FUNDS” 1 The most significant results of Component.
PROJECT OVERVIEW FM Budget € Total contracted € –EU Grant € –National Co-financing –Total contracted /
2012 JANUARY Sun Mon Tue Wed Thu Fri Sat
Development of the Wastewater Collection and Treatment System in Szombathely County Town 2003/HU/16/P/PE/021 EXTENSION OF THE SEWER NETWORK IN THE WEST-TOWN.
MINISTRY OF TRANSPORT OF THE REPUBLIC OF LATVIA Implementation of Cohesion Fund Projects in Transport Sector Cohesion Fund Monitoring Committee 11 April.
Geldy Saryev Head of Industry, Transport and Communications Financing Department of the Ministry of Finance of Turkmenistan.
COHESION FUND MONITORING COMMITTEE 11 April 2008 Jurijs Spiridonovs Ministry of Environment Head of Project Development Department.
Audit of Public Procurement
Report about controlling activity and its results in the programme in 2013 TOP Monitoring Committee Meeting
Public Procurement Exchange Platform Efficient implementation of Procurement - Centralized Purchasing Mr. Safet Hoxha, President of PPRC Mr. Ilaz Duli,
1 PUBLIC PROCUREMENT AND USE OF FIDIC CONTRACTS IN LATVIA Procurement Monitoring Bureau 2013.
ERDF for Education And Science Ministry of Education And Science 1st of October 2013.
WATERCYCLE planning and managing water resources Adriatic New Neighbourhood Programme INTERREG/CARDS-PHARE Sisak-Moslavina County Koprivnica, 16 th January.
EU TWINNING PROGRAM “SUPPORT TO THE PARLIAMENT OF THE REPUBLIC OF MOLDOVA” Mrs. Eszter Kertészné Gérecz Head of IT Department
“Remediation of Historically Polluted Areas in Sarkandaugava” Progress from April 2014 till March 2015.
Slovak Environmental Inspectorate Procedure of issuing the permits in the Slovak Republic.
Energy for the Future Belene Nuclear Power Plant Project Status.
Phare 2003 Sector: Economic and Social Cohesion Title: Water Supply and sewerage in tourism and resort settlements.
WATROPEC project 1 Vlaams Kenniscentrum Water FITA premission seminar CROATIA Brussels, 25 November 2011.
Hungarian proposals for the revision of EGTC Regulation and EGTC good practices Presenter: Dr. Erika Szabó Minister of State for Territorial Public Administration.
Environmental Investment Centre (EIC) ISPA Unit Rävala pst 8, TALLINN Tel: Fax:
WORD JUMBLE. Months of the year Word in jumbled form e r r f b u y a Word in jumbled form e r r f b u y a february Click for the answer Next Question.
“Remediation of Historically Polluted Areas in Sarkandaugava” Progress from April 2013 till March 2014.
8th Cohesion Fund Monitoring Committee 11 April 2008 Technical Assistance for the Cohesion Fund Management in Latvia No.2005/LV/16/C/PA/001.
1 MINISTRY OF REGIONAL DEVELOPMENT AND PUBLIC WORKS MANAGING AUTHORITY FOR COHESION FUND (REGULATION 1164/94) MANAGEMENT OF PROJECTS, FINANCED BY COHESION.
PRIME MINISTRY REPUBLIC OF TURKEY TURKISH STATISTICAL INSTITUTE Foreign Relations Department Projects Group TurkStat Meeting of the Policy Group on Statistical.
DATE POWER 2 INCOME JANUARY 100member X 25.00P2, FEBRUARY 200member X 25.00P5, MARCH 400member X 25.00P10, APRIL 800member.
Progress with Priority Environmental Infrastructure Investment Projects in Croatia PEIP Regional Meeting - 26 th November 2007 Brussels MINISTRY OF ENVIRONMENTAL.
Sustainable public transport – electric transport development project for the capital.
Structural Funds Managing Authority – Ministry of Finance 1 Technical Assistance Ilze Aleksandroviča Head of Control and Development Division EU Funds.
DESCRIPTION OF THE MONITORING AND EVALUATION SYSTEM IN POLAND Action Plan and the Two-year NRN Operational Plans.
EU Funds in Latvia Aleksandrs Antonovs Ministry of Finance Deputy director of Department of EU Funds December 4, 2006.
1 Maribor Wastewater Treatment Plant Presentation of PPP Model in Maribor - Slovenia Conference Danilo ŠALAMON – Chief of the Infrastructure projects Department.
2011 Calendar Important Dates/Events/Homework. SunSatFriThursWedTuesMon January
Prokurimi Publik në Kosovë Public Procurement System in Kosovo Public Procurement activities for 2011 Mr. Safet Hoxha, President of PPRC Mr. Ilaz Duli,
7 th Cohesion Fund Monitoring Committee CR 1164/94 ISPA Measure 2001 BG 16 P PE 006 Wastewater Collection and treatment located in Pazardjik, Republic.
Ministry of Interior Progress of Bulgaria in the preparation for joining the Schengen area January July 2009 July January
ISPA Measure 2003 BG 16 P PE 019 Kardjali Regional Waste Management Centre in Bulgaria 10 th Cohesion Fund Monitoring Committee CR 1164/94.
Galati Municipality – project status - PCT meeting, Enns, 6-8 March
9 th Cohesion Fund Monitoring Committee CR 1164/94 ISPA Measure 2002 BG 16 P PE 018 Shoumen Water Cycle Improvements.
Recent sucessful steps taken by Republic of Serbia in implementation of Balkans project Prepared by Jasmina Bogdanovic Workshop to Promote the Ratification.
July 2007 SundayMondayTuesdayWednesdayThursdayFridaySaturday
CFCU PROGRESS AND MONITORING REPORTS (PMRs)
1 Energy/Compost Facility Action Plan City Council Meeting July 2, 2012.
Non-profit Business Support Centres in Hajdú-Bihar and Bihor counties: Development of operation an cooperation facilities HURO/0802/108_AF Experiences.
Supply Chain Management of Second Line Drugs: Russian Example Dr Vadim V. Testov Central TB Research Institute, Moscow, the Russian Federation.
PRESENTED BY HENRY RUHNKE WALD, RUHNKE & DOST ARCHITECTS, LLP SIERRA HOUSE & DROP-IN CENTER.
Prof. dr. Giedrius Vanagas
Ministry of Finance Contribution of the Operational Programmes to the implementation of the NSRF objectives Boriana Pencheva Director Management.
Water projects under The Cohesion Fund.
PUBLIC PROCUREMENT SYSTEM IN UZBEKISTAN
Dictation practice 2nd Form Ms. Micaela-Ms. Verónica.
Establishment aid coordination and management mechanisms
COHESION FUND MONITORING COMMITTEE
Liquefied Natural Gas Terminal in Lithuania
McDonald’s calendar 2007.
State of Play Programme level
Dr. Katja Šnuderl, Contract manager
National Transition Facility / Phare / Cards
Mr. Alper GÜCÜMENGİL Head of Projects Group, TURKSTAT
WP 1 Management and Coordination
McDonald’s calendar 2007.
2015 January February March April May June July August September
Presentation transcript:

Development of the Wastewater Collection and Treatment System in Szombathely County Town Implementation of sewage-sludge Composting Plant 2003/HU/16/P/PE/021

2003/HU/16/P/PE/021 – Implementation of sewage-sludge Composting Plant Implementation of the Project Signing the Financing Memorandum, tasks of the contracting Tasks of the Project Implementation The Public Procurement Procedure and its phases Implementation Financial implementation Monitoring – checking – evaluation Completion of the Project

2003/HU/16/P/PE/021 – Implementation of sewage-sludge Composting Plant TENDERING Preparation Works of the Development program financed by the Cohesion Found has been completed on 4th February 05. Predictable Date of Completion was 31st December 07 for the entire Project The total cost of Euro have been covered in 60% by the Cohesion Found, in 30 % by State Budget and in 10 % by the local Municipalities

2003/HU/16/P/PE/021 – Implementation of sewage-sludge Composting Plant PUBLIC PROCUREMENT PROCEDURES PROCEDURES TARGETING WORKS OF IMPLEMENTATION: Development of the Sewage and Rainwater Collecting System in western part of Szombathely Upgrading the technology of Sewage Treatment Plant I. Upgrading of the mechanical pre-treatment system and the Sewage Treatment system II. Construction of new Composting Plant PROCEDURES TARGETING SERVICES: Expert’s Services of tasks of „Engineer” and Technical Surveyor Providing Services of Information and Public Relations connecting to the Project Expert’s Services for the Project Implementation Unit

2003/HU/16/P/PE/021 – Implementation of sewage-sludge Composting Plant On 28th November 03 the Financing Memorandum of the Project has been signed by the European Comission On 11th February 04 the Financing Memorandum of the Project has been signed by the Republic of Hungary On 28th May 04 a Consortium Agreement has been signed by the Municipalities involved into the Development for the implementation of the Project. In this Agreement Szombathely County Town has been nominated as a Gestor. The agreement bonds the VASIVÍZ ZRt for cooperation on the course of implementation. The preparation of the Project has been completed on 4th February 05 by signing the Financing Memorandum made between Szombathely County Town and the Ministry of Environment and Water The first Service Contract of the Project has been signed on 22nd September 05 to provide Expert’s Services by the Canor International Ltd. for the tasks of „Engineer” Implementation of the Project

2003/HU/16/P/PE/021 – Implementation of sewage-sludge Composting Plant On the 9th December 05 the winner of the Public Procurement Procedure for PR Services, namely the Medius Iroda signs the Service Contract with the Beneficiary On 9th March 06 the TECHNOPLUS Környezetvédelmi Technológiai Fejlesztő Kft. contracts for Expert’s Services for the Project Implementation Unit working in the Mayor’s Office of Szombathely Public Relation : Information about the utilisation of compost products in agriculture – at the settlement of Balogunyon Public Relation : Information about the utilisation of compost products in agriculture – at the settlement of Kőszeg

2003/HU/16/P/PE/021 – Implementation of sewage-sludge Composting Plant On the 22nd March 06 the winner of the Public Procurement Procedure relating to the implementation new Composting Plant, namely the TEERAG – SWIETELSKY Konzorcium (TEERAG-ASDAG AG Niederlassung Burgenland és Swietelsky Építő Kft) signs the Works Contract

2003/HU/16/P/PE/021 – Implementation of sewage-sludge Composting Plant On 16th June 06, with the contribution of Mr. Pál Kiss, the head of Institute of Development in Ministry of Environment and Water, furhermore dr. György Ipkovich Mayor of Szombathely the foundation-stone of the Sewage-sludge Composting Plant has solemnly been positioned on Szombathely

2003/HU/16/P/PE/021 – Implementation of sewage-sludge Composting Plant Implementation of sewage-sludge Composting Plant Earthworks of Composting Plant

2003/HU/16/P/PE/021 – Implementation of sewage-sludge Composting Plant Providing detailed preliminary information had underlined importance during the whole Project The following demonstrations have been organised on the course of campaign: -22. May Szombathely -17. October Táplánszentkeresz -18. October Lukácsháza -27. November 2006 Kőszeg, Torony -11. December Balogunyon -12. December Salköveskút Detailed information of the Public

2003/HU/16/P/PE/021 – Implementation of sewage-sludge Composting Plant Progress of Works 1st June 06-31st March 07 The net contracted value was ,-. Date of Site Delivery was 15th June 06. The Design and Works have been commenced according to the approved Time Schedule Soil exchange has been completed by the submitted and approved Earthwork Plan Formwork of walls at the Fermentation tower Construction Composting Plant – earthwork, soil exchange

2003/HU/16/P/PE/021 – Implementation of sewage-sludge Composting Plant 1st April 07 – 30th June 07 Problems were reported by the Contractor in February and March 07 regarding to the purchasement of laminate-cover. Examining the claim, it became clear, that replacement of the inflatable system is required. Processing and approval of the Amendment of the Contract has been commenced. 1st July 07 – 31st December 07 The 1st Amendment of the Contract has been signe on 20th September 07 by the Parties. The amended Date of Completion is 15th August 08. The Contractor has carried on design and has submitted the Drawings for approval. Works of Sanitary Engineering, earthworks and foundation Works were going on. Keeping the Site Log is continuous. Documentation for the amendment of Building Permit has been processed by the Contractor. Application for the Amendment of Building Permit has been submitted by the Beneficiary on 1st October 07. Approval of Claim for the Amendment No. 1 and process for the Amendment No. 2 are in progress

2003/HU/16/P/PE/021 – Implementation of sewage-sludge Composting Plant 1st January 08 – 31st May 08 On 14th March 2008 the 2nd amendment of the contract was signed. The 1st amendment of the contract referred to the modification of the termination date and the replacement of the inflatable system. The 2nd amendment of the contract referred to the modification of the termination date based on the delay caused by the authorities. The construction works (structure construction, mechanical engineering works, sanitary engineering works, electrical mounting works) of the composting plant have been finalized. The expected date of taking over process and the finalisation of the trial operation (after 6 months) is 30th November st June th November 08 On 1st June 08 Trial Operation has been commenced. On 30th November 08 the Trial Operation has been successfully completed. On 30th November 08 the Taking over process has been successfully completed.

17th October 08 – In the frame of Open Day the Public had the opportunity to get a view into the modern technology of sludge treatment and composting on a Site Visit and a chance to get convinced about the successful results achieved in the Project 2003/HU/16/P/PE/021 – Implementation of sewage-sludge Composting Plant Open Day at the Composting Plant

The 6 months long Trial Operation launched on 1st June 2008 has been completed on 30th November 08. The Project has been completed in time, meeting with requirements of the Amended Contract. Results achieved  The planned facilities for treatment of sludge coming from the Wastewater Treatment Plant furthermore planned facilities of compost production have been implemented  Conditions of operation has been established, on one hand satisfying both of Hungarian and EU legislation and on the other hand providing long-term feasible operation of sludge-treatment and Compost production technology  Elimination of odour-pollution of air in the neighborhood of the Composting Plant is predictable. 2003/HU/16/P/PE/021 – Implementation of sewage-sludge Composting Plant

Thank you for your kind attention! Source: