Electrical Measurement Methods I

Slides:



Advertisements
Similar presentations
An Introduction to On-line Partial Discharge Surveys
Advertisements

Moisture effect on the dielectric response and space charge behavior of mineral oil impregnated paper insulation Jian Hao1, 2, George Chen2, Ruijin.
Influence of Ageing and Temperature on the Polarization/Depolarization Current Behaviour of Paper Immersed in Natural Ester Jian Hao 1, 2*, Ruijin Liao.
New Energy Horizons Opportunities and Challenges Fault Current Contributions from Wind Plants Dean Miller PacifiCorp July 25,
New Frontiers of DGA Interpretation
Managing Director, HVPD Ltd
TESTING, MAINTENANCE & PROTECTION OF DISTRIBUTION TRANSFORMERS
GENERATOR PROTECTION.
Topics Unidentified Flying Objects Alien Abductions Flying Saucers End of the World April 1, 2014.
DECLERCQ Jan BE Alpha 4 – Block 2 Barcelona May TRANSFORMERS FOR WIND TURBINES NEED FOR NEW DESIGNS OR BUSINESS AS USUAL Dr. Jan Declercq.
Corrosive Sulphur & Oil Passivation
Novocontrol Alpha Analyzers Fundamentals
Sweep Frequency Response Analysis (SFRA) and Transformer Diagnostics M5100 Product Series Doble Engineering Knowledge Is Power SM Apparatus Maintenance.
Dry type transformers Zaragoza Traction application
GE Consumer & Industrial Multilin  Single & Three phase models  Specific mount CT’s  Rectangular & Toroidial models  Plastic case & cast models  Multi.
Generator Protection. Amount of Protection Rated power of the generator Ratio of its capacity to the total capacity of the system Configuration of the.
High Voltage Insulation Diagnostics
DET 310 UNDERGROUND CABLES
NEW TOOLS FOR DIAGNOSTIC MEASUREMENTS ON ELECTICAL ROTATING MACHINES
Chapter 2 Transformers.
1 CONSEIL INTERNATIONAL DES GRANDS RESEAUX ELECTRIQUES INTERNATIONAL COUNCIL ON LARGE ELECTRIC SYSTEMS STUDY COMMITTEE A2 TRANSFORMERS Presentation of.
Aspects of partial discharge measurement
Transformer.
Levels of high voltage: World over the levels are classified as: LOW MEDIUM HIGH EXTRA and ULTRA HIGH Voltages However, the exact magnitude of these levels.
ea technology Effective Condition Assessment of MV Switchgear
ON LINE TRANSFORMER OIL REGENERATION PROCESS OF GT-8
All rights reserved Gas-insulated Switchgear (GIS)
DIAGNOSIS AND FAULT FINDING ON POWER TRANSFORMERS
Dry type transformers Zaragoza Aluminum vs. Copper
IEEE CIGRE Liaison Report on SCA2 Transformers
Dielectrometry Measurements of Moisture Diffusion and Temperature Dynamics in Oil Impregnated PILC Cables Zachary M. Thomas Wolf, Greenfield & Sacks P.C.
Transformer condition assessment with an integrated test van
POWER HOUSE.
A PRESENTATION OF PRACTICAL TRAINING ON “400KV GSS “ \
A Presentation On 132 KV GSS BEHROR
SEMINAR PRESENTATION ON 220 KV GSS UDAIPUR
Department of Electrical Engineering
A SEMINAR ON 400 KV GSS(RRVPNL) BIKANER.
Submitted To:- Submitted By:- Mr.
S. MELQUIOND France Session 1 – Block 1 – Question 1- 5 Barcelona May Question 1-5 Is the transformer protection by mean of protection switch.
PRESENTED BY Gupta.Deepakkumar.R ( ) Condition Monitoring of Transformer (The heart of Power System)
HIMACHAL PRADESH STATE ELECTRICITY BOARD LTD.
Diagnostics of power cables – DC-measurements Condition Monitoring of Electrical Equipment L School of Electrical Engineering Pyry Karhu Slide 1/
ONLINE MONITORING APPLICATIONS OF POWER TRANSFORMER Deepak Subedi.
DIELECTRIC DIAGNOSTICS MEASUREMENTS OF TRANSFORMERS AND THEIR INTERPRETATION Claudia Martorella Spring 2016.
EE 2353 HIGH VOLTAGE ENGINEERING
IDAX 300 Insulation Diagnostic Analyzer Dielectric Frequency Response Also known as: Frequency Domain Spectroscopy.
“Ageing Phenomenon of Paper oil insulation in power transformer”
Outage of Generator Transformer due to High DGA. BRIEF HISTORY 200 MVA 400 kV GT erected at site. After satisfactory pre-commissioning checks GT was successfully.
Md.Hamidul Haque ID: Prog:BSEEE SEC:E/3 International University of Business Agriculture and Technology (IUBAT )
STUDY OF ELEMENTS OF A 220/132/33KV SUBSTATION
SWEEP FREQUENCY RESPONSE ANALYSIS AS A DIANOSTIC TOOL TO DETECT TRANSFORMER MECHANICAL INTEGRITY by:Luwendran Moodley Brian de Klerk ETHEKWINI ELECTRICITY.
ET 332b Ac Motors, Generators and Power Systems 1 Lesson 11_et332b.pptx.
PE Systems Pvt. Ltd. Bangalore
TESTING AND MAINTENANCE OF POWER TRANSFORMER
Sensor presentation.
WELCOME.
Testing of Transformers
Capacitance and Dielectrics
CIGRE SC B5 COLLOQUIUM CALGARY
A presentation on Measurement of Winding Resistance and Insulation Resistance of 3 Phase 11 kV/ 433 V, 16KVA Oil cooled type Transformer PRESENTED BY:
Quick help for fault location and reliable detection of defects
Sensor presentation.
Alexander Dierks – Alectrix (Pty) Ltd, South Africa
المحولات Transformers
Lesson 11: Transformer Name Plate Data and Connections
CHAPTER 3 INSULATION TEST OF POWER SYSTEM EQUIPMENT
Figure 25.2 (a) When the electric field E is directed downward, point B is at a lower electric potential than point A. When a positive test charge moves.
Quick help for fault location and reliable detection of defects
Substation Equipment's
Presentation transcript:

New Experience in the Transformer Diagnosis Michael Krüger, OMICRON Austria

Electrical Measurement Methods I

Electrical Measurement Methods II

Content Winding Resistance Measurement Fault Finding on Transformer Windings with FRA Moisture Measurement on Transformers Partial Discharge Measurement on Transformers

Winding Resistance Measurement

Diverter Switch Contact of Phase V

Winding Resistance after Repair

Content Winding Resistance Measurement Fault Finding on Transformer Windings with FRA Moisture Measurement on Transformers Partial Discharge Measurement on Transformers

Fault on a 115kV / 34.5kV Transformer There was a breakdown in phase B of the 34.5 kV busbar in the substation The differential protection relay of the faulty transformer tripped Example from David Stelmach. – a person was working in the substation, one 115kV line was falling down on the 34.5kV lines, first on phase B, then also on the other phases. Transformer saw overcurrent on B phase and then tripped out on Differential.

DGA Phase 1: Trip out of Service, Differential Phase 2: DGA second DGA showed 19ppm C2H2

Transformer Model for FRA 28/11/2006 Transformer Model for FRA

Swept Frequency Response Analysis (SFRA) 28/11/2006 Swept Frequency Response Analysis (SFRA) Magnitude Phase This slide explains the so-called sweep frequency method. In contrast to the impulse method, here we work with a sinusoidal signal, which is swept between 10 Hz and 10/20 kHz (or more). Vin – represented in red – is the input signal, which is standardized to 1 or 100%. We sweep the signal over the whole frequency range and measure the signal Vout - represented in blue - at the other end of the winding. We see that the blue signal (output signal) compared to the red signal (input signal) shows both a damping as well as a phase shift. The transfer function (H) in dB is the result of the calculation according the shown formula: H(dB) = .... Advantages of the sweep FRA method: The input amplifiers of the equipment can be realized with a very small bandwidth; by that it can be avoided that other distortion signals superimpose the measurement signal Over the whole frequency range we have a constant amplitude of the oscillator signal and by that no limitation of / a constant energy at higher frequencies. This allows a more sensitive measurement of particularly at higher resonance frequencies.

FRA LV Winding – Comparison of the 3 Phases B Phase

Radial Forces Buckling with inner supports Buckling without inner Higher order or forced Buckling The conductors can bend between the supports all along the circumference Free mode or free Buckling Source: Brochure CIGRE WG 12.19 : The Short Circuit Performance of Power Transformers

Radial Failure (Buckling) This slides shows the standard FRA measuring method: The yellow cable (generator output) is connected to the beginning of the winding, with the red cable the injected voltage is measured back to compensate wiring influences (reference channel). With the blue cable (output) the damped signal at the other end of the same winding is fed back to equipment to the measurement input. This is the standard FRA method which should be applied as a minimum for all FRA measurements. The measurement is performed for each phase: If a transformer has two voltage levels this means that six measurements are performed, if we have a three-winding transformer (upper, medium, and low voltage winding), nine such measurements are necessary. © OMICRON Academy

Failure Modes due to Radial Forces B phase with buckling C phase without buckling Source: Cigre Brochure 342 “ MECHANICAL-CONDITION ASSESSMENT OF TRANSFORMER WINDINGS USING FREQUENCY RESPONSE ANALYSIS (FRA)”

LV Winding with Cigre Case Study of Buckling Comparison FRA LV Winding with Cigre Case Study of Buckling Systematic shift of several resonances www.e-cigre.org B Phase

B Phase Take a closer look

B Phase

Content Winding Resistance Measurement Fault Finding on Transformer Windings with FRA Moisture Measurement on Transformers Partial Discharge Measurement on Transformers

Diagnosis of Tranformer On-load Tap Changers 29 November 2006 Water in the Transformer Most of the water is contained in the paper! Mass of the oil: 100,000 kg = 220,000 Lbs Water content at 60 °C: 40 ppm Mass of the water, dissolved in the oil: 4 kg = 8.8 Lbs Mass of the solid insulation: 13,000 kg = 20,000 Lbs Water content at 60 °C: 4 % Mass of the water contained in the paper: 520 kg = 1200 Lbs Paper 4 -

Diagnosis of Tranformer On-load Tap Changers 29 November 2006 Determination of the Water Content in Paper [Karl Fischer Titration and Equilibrium Curves] Curves are only valid for new oil and new paper, for aged oil/paper different curves are necessary Oil sampling is critical (round robin tests) Balance between water content in the paper and in oil needs constant temperatures over a long period Only average measurement Paper 4 -

History of Dielectric Diagnostic Methods 1991 RVM for water determination Soon questioned by users (Kachler 1996) 1960+ Dissipation factor at power frequency Polarization index At that time: No reliable method for onsite moisture diagnostics 1999+ Polarization Depolarization Currents Technical University Zurich Switzerland 1999+ Frequency Domain Spectroscopy KTH Stockholm with ABB 2007 Combination of PDC and FDS

Diagnosis of Tranformer On-load Tap Changers 29 November 2006 Dielektric Response in the Time Domain Polarisation Depolarisation Current (PDC) Current = f(t) Paper 4 -

Diagnosis of Tranformer On-load Tap Changers 29 November 2006 Dielektric Response in the Frequency Domain Frequency Domain Spectroscopy (FDS) or Dielectric Frequency Response (DFR) Paper 4 -

Dielectric Response Measurement with Frequency Domain Spectroscopy (FDS) and Polarisation & Depolarisation Current (PDC) Current [nA] Time [s] Trans- formation Frequency [Hz] Power factor 0.001 1 1000 100 0.1 PDC FDS 2 4 6 8 10 12 14 PDC FDS DIRANA Duration / h 0,0001 0,001 0,01 0,1 1 100 1000 Frequency range / Hz Combination of PDC und FDS reduces measurement time

Interpretation and Analysis Transition from Capacitive to Resistive Voltage Distribution Pressboard: Water, lmw Acids Oil: Carbon, Sludge, hmw Acids Öl 1pS/m 10 Pressboard Dissipation factor 1 Pressboard 0,5 1,0 2,0 Overall Response 1%, 1pS/m, X30, Y15 0.1 0.01 0.001 0.0001 0.0001 0.001 0.01 0.1 1.0 10 100 1000 f/Hz

Analysis of the Water Content by Comparison to Model Results Measurement Laboratory Results Water Content Oil Conductivity Comparison Fitting X Oil XY-Model Barriers Spacers Y Temperature Moisture determination bases on a comparison of the dielectric properties of the real transformer to modelled dielectric properties. The model bases on laboratory measurements on pressboard samples (upper right photograph) and the conductivity of oil. Both are combined by the XY-model taking into account the geometry condition of the transformer and the insulation temperature. A fitting algorithm arranges the modelled dielectric properties in order to get a good agreement to the measured dielectric properties. The best fitting curve provides the moisture content and oil conductivity of the real transformer. Here you can demonstrate how the software works using the link to C:\Program Files\OMICRON\DIRANA\Dirana.exe Source: Weidmann

FDS / PDC Measurement on a 130 MVA Transformer – Situation 2006 Diagnosis of Tranformer On-load Tap Changers 29 November 2006 FDS / PDC Measurement on a 130 MVA Transformer – Situation 2006 130 MVA 230 / 115 / 48 kV Year of manf. 1967 Rubber membrane in the expansion vessel Paper 4 -

FDS / PDC Measurement on a 130 MVA Transformer – Water Content Distribution 5 Oilsample Karl Fischer mg/kg (Oommen equilibrium) 4 Oilsample RH % Average Moisture in paper [%] 3 FDS HV-LV Tertiary not in use 2 1 FDS LV- Tertiary FDS Tertiary- Tank FDS/PDC 1mHz-1kHz

130 MVA Transformer On-Line Drying Diagnosis of Tranformer On-load Tap Changers 29 November 2006 130 MVA Transformer On-Line Drying Paper 4 -

History 2006 – 2008 - 2010

Content Winding Resistance Measurement Fault Finding on Transformer Windings with FRA Moisture Measurement on Transformers Partial Discharge Measurement on Transformers

Diagnostic Measurement on a Cast Resin Type Transformer

Cracks in the Epoxy

PD Measurement Circuit

Test Arangement CPC100 CP CU1 Compensating Capacitors

Test Arangement Coupling Capacitor and MPD600

Separation of PD Sources in 3CFRD 500kHz 2 MHz 8 MHz 500kHz 8MHz 2MHz timeframe 1 µs 500 kHz 2 MHz 8 MHz 3CFRD = 3 Center Frequency Relation Diagram

PD Measurement without 3CFRD Filtering

3CFRD Filtering

PD Measurement with 3CFRD Filtering

PD Measurement without 3CFRD Filtering

On-Line PD Measurement on a Transformer

On-Line PD Measurement on a Transformer GIS - Cable Connection (GIS Side) 2 1 3

Online PD Measurement at the GIS Side red phase GIS yellow phase GIS blue phase GIS

Sensors 1, 2 and 3 at the GIS Side and Sensor 4 at the Transformer Side

PD Measurement at the GIS and the Transformer Side blue phase GIS blue phase Tr

PD Measurement at GIS and TR Side Trigger = TR Side - Delay on GIS Side trigger = blue phase Tr delayed signal blue phase GIS

Jumper between Oil/Oil Bushing and Cable Termination

Jumper between Oil/Oil Bushing and Cable Termination

michael.krueger@omicron.at Questions and Remarks?

A last Example: Fault Investigation on a 220kV Transformer

DGA

Ratio Measurement HV to LV

Ratio HV to LV Phase A=R 2kV on HV -> 23mV on LV on all taps !

Ratio HV to LV Phase B=S All taps have the same ratio 7.2:1 of position 11 !

Ratio HV to LV Phase C=T All taps have the same ratio 7.2:1 of position 11 !

FRA HV Interruption in phase R, HV side

FRA LV with HV open Short circuit in phase R, but on LV or HV side ???

FRA LV with HV Open and Shorted A LV with open loop HV (red line) B LV with open loop HV (blue solid line) B LV with shorted HV (blue dashed line)

Winding Resistance of LV Phase R LV doesn’t look damaged

Conclusions Phase R=A is interrupted on HV side The tap changer is broken – in position 11 The limb R has a shorted winding The short circuit in limb R is not on the LV side but on the HV side

Opening of the OLTC Compartment

Opened OLTC Compartment Interruption in phase R, HV side

Interruption due to Open OLTC Contacts

Removed OLTC – Cables to the Tap Winding

FRA on the Single Tap Winding Segments

FRA on the Single Tap Winding Segments 11 - 13 9 - 11 8 - 9 7 - 8 6 - 7 5 - 6 4 - 5 3 - 4 2 - 3 14 - 2

FRA on the Single Tap Winding Segments

Winding Resistance of the Tap Winding Segments 4 The fault was between tap conductor 4 and 6 ! 25mΩ 7mΩ 14mΩ 6mΩ 5 6

michael.krueger@omicron.at Questions and Remarks?