AMERICAN SPORTS BUILDERS ASSOCIATION CRITICAL PATH METHOD SCHEDULING FOR SUCCESS December 6-8, 2008 New Orleans, Louisiana Presented By: Bill Pronevitch.

Slides:



Advertisements
Similar presentations
Precedence Diagramming
Advertisements

Developing a Project Plan CHAPTER SIX Student Version Copyright © 2011 by The McGraw-Hill Companies, Inc. All rights reserved. McGraw-Hill/Irwin.
Chapter 6: Developing a Project Plan
464 Lecture 09 CPM Revision. Scheduling Techniques r The scheduling techniques are î To plan, schedule, budget and control the many activities associated.
PRJ566 Project Planning and Management Lecture: Network Diagrams.
PRJ566 Project Planning and Management Lecture: Dependencies and Network Diagrams.
1 Lecture by Junaid Arshad Department of Engineering Management Abridged and adapted by A. M. Al-Araki, sept WBS: Lowest level OBS: Lowest level.
CSSE Sep.2008 Constructing and Analyzing the Project Network Diagram Chapter 6.
A simple set of tasks in “timeline-schedule” form Req. Gathering Req. Analysis High Level Design Detail Design & Code Test Case DevelopmentTest Execution.
CSSE 372 Week 6 Day 2 Constructing and Analyzing the Project Network Diagram  PERT Chart PERT was invented for the Nautilus submarine project. Ok, maybe.
إدارة المشروعات Projects Management
PREPARED BY : NOR AZAH BINTI AZIZ KOLEJ MATRIKULASI TEKNIKAL KEDAH PROJECT NETWORK DIAGRAM.
MGMT 483 Week 8 Scheduling.
Management & Development of Complex Projects Course Code - 706
5/4/20151 NETWORK SCHEDULING TECHNIQUES. 5/4/20152 Network Diagrams  PMI defines the scheduling process as: “the identification of the project objectives.
Dr. Hany Abd Elshakour 5/4/2015 3:55 PM 1. Dr. Hany Abd Elshakour 5/4/2015 3:55 PM 2 Time Planning and Control Activity on Node Network and Precedence.
Chapters 8, 9, and 10 Design Stage 1 Preconstruction Stage 2: Procurement Conceptual Planning Stage3: Construction Stage 4: Project Close-out.
Copyright © 2009 T.L. Martin & Associates Inc. Chapter 2 Key CPM Scheduling Terms.
© 2000 by Prentice-Hall Inc Russell/Taylor Oper Mgt 3/e Chapter 6 Project Management.
Time Management Ahmed Awad, Ph.D., PMP. Time Management It includes the processes required to ensure timely completion of the project. b Activity Definition.
Introduction to Project Management A basic introduction to common project management processes that may be typically encountered during a projects lifetime.
Where We Are Now. Where We Are Now Developing the Project Plan The Project Network A flow chart that graphically depicts the sequence, interdependencies,
The Critical Path – Precedence diagram method Luise Lorenz Christina Mohr.
Time Planning and Con trol Precedence Diagram.  Precedence Diagramming  An important extension to the original activity-on-node concept appeared around.
THE MANAGERIAL PROCESS Clifford F. Gray Eric W. Larson Developing a Project Plan Chapter 6.
Amin Salari, CCM, PMP, LEED AP – Lundgren Management
Copyright 2006 John Wiley & Sons, Inc. Beni Asllani University of Tennessee at Chattanooga Project Management Operations Management - 5 th Edition Chapter.
EGNR 300 Project Management Planning & Scheduling ENGR 300 Dept. of Computer Science and Engineering University of Bridgeport,
© Construction Management Association of America. Do Not Duplicate or Reproduce. Standards of Practice Course CPM Scheduling Lab.
PROJECT SCHEDULING By Deepika chaudhary. Project Scheduling Scheduling means estimation of time and resources required to complete activities and organise.
1 Project Planning, Scheduling and Control Project – a set of partially ordered, interrelated activities that must be completed to achieve a goal.
PMP, CAPM, PgMP, PMI-SP, PMI-RMP, OPM3 and PMBOK are registered marks of Project Management Institute, Inc Inov8Solutions Inc – Quality Educational Services.
Project Management Part 5 Project Scheduling. Topic Outline: Project Scheduling Identifying relationships among activities Project network diagrams Identifying.
Richard Fisher 1 The University of Texas at Dallas Project Management Richard Fisher The University of Texas at Dallas.
CE 366 PROJECT MANAGEMENT AND ECONOMICS Robert G. Batson, Ph.D., P.E. Professor of Construction Engineering The University of Alabama
Copyright 2006 John Wiley & Sons, Inc. Beni Asllani University of Tennessee at Chattanooga Project Management Operations Management - 5 th Edition Chapter.
Richard Fisher 1 The University of Texas at Dallas Project Management Richard Fisher The University of Texas at Dallas.
Copyright 2012 John Wiley & Sons, Inc. Chapter 8 Scheduling.
1 EASTERN MEDITERRANEAN UNIVERSITY FACULTY OF ENGINEERING DEPARTMENT OF CIVIL ENGINEERING CIVL 493 Construction Management Assoc. Prof. Dr. Ibrahim YITMEN.
CON 2001 Construction Methods Tool #1 - Construction Scheduling Presented by Elia Twigg, P.E. (Prof. Ralph V. Locurcio, P.E.)
Dr. Hany Abd Elshakour 2/18/ :27 PM 1. Dr. Hany Abd Elshakour 2/18/ :27 PM 2 Time Planning and Control Activity on Arrow (Arrow Diagramming.
Project Management – Part 1. Overview What is a project? Project management techniques Activity lists Network diagrams Critical path analysis Gant charts.
Project Planning & Scheduling What is a “project”? Objectives and tradeoffs Planning and Control in Projects Scheduling Methods Constant-Time Networks.
PROJECT MANAGEMENT ENCE-7323 TO 763-N CLASS 3 September 17, 2001 Carl E. Edlund
Project Management Fundamentals - Planning Tools 1.
Copyright 2006 John Wiley & Sons, Inc. Beni Asllani University of Tennessee at Chattanooga Project Management Operations Management - 5 th Edition Chapter.
Project Planning, Scheduling and Control Planning: –defines objectives, tasks and preceeding relationships; estimates time and resources Scheduling: –identifies.
Project Management MGT 30725
PROJECT MANAGEMENT.
Project Management: PERT/CPM
Project Management (PERT/CPM) PREPARED BY CH. AVINASH
Time Planning and Control Activity on Node Network (AON)
Most commonly used methods for project management.
Project Planning & Scheduling
Project Management for Business
Project Planning and Scheduling
Project Scheduling Chapter 14.
Chapter 6: Project Time Management
CHAPTER 6 PROJECT TIME MANAGEMENT
PROJECT MANAGEMENT WITH CPM/PERT.
Time Planning and Control Precedence Diagram
Project Scheduling Basics Activity on Node Precedence Diagrams
Project Scheduling: Lagging, Crashing and Activity Networks
Time Planning and Control Activity on Node Network (AON)
Lecture 5: Project Time Planning (Precedence Diagramming Technique)
Exercise – A small building.
Time Planning and Control Precedence Diagram
CHAPTER 6 PROJECT TIME MANAGEMENT
Presentation transcript:

AMERICAN SPORTS BUILDERS ASSOCIATION CRITICAL PATH METHOD SCHEDULING FOR SUCCESS December 6-8, 2008 New Orleans, Louisiana Presented By: Bill Pronevitch

SCHEDULING- Is It Necessary? Effective Project Management involves coordinating activities such as: –Planning –Organizing –Controlling Time (scheduling) –Cost The “Scheduling” process forces people to: –Quantify their effort in discrete terms –Place tasks in proper relationships

SCHEDULING- Methodologies Two of the most common methodologies: –Bar Charts –Critical Path ADM: Arrow Diagramming Method PDM: Precedence Diagramming Method Both scheduling methods are widely used for: –Controlling –Making optimal use of project time

SCHEDULING- Bar Charts Bar Charts (also called “Gantt Charts”) are primarily for controlling Time elements: –Analyze/ specify the basic approach to be used –Segment the work into a reasonable number of activities that can be scheduled –Estimate the time required to perform each activity (i.e.- activity duration) –Place activities in “time-order” (logic) –Adjust the chart until the specified completion date, if one exists, is satisfied.

SCHEDULING- Bar Chart ABCDEFABCDEF Gantt Chart (Bar Chart) shows: All Activities and Status on a Single Chart

SCHEDULING- Bar Charts Benefits: –Plan, Schedule, and Progress on a single chart –A simple, understandable way to schedule small projects or undertakings Disadvantages: –Activity-limited, can’t handle complex projects –Doesn’t show logic ties (activity relationships) –Insufficient detail to enable timely detection of schedule slippages on long duration activities

SCHEDULING: Critical Path The Critical Path Method (CPM) was designed for and is useful on projects where the duration of each activity can be with reasonable certainty - it predicts project overall completion - it identifies the (critical) activities that control the overall length of the project CPM is widely used in: process industries construction and plant outages/ shutdowns.

SCHEDULING: Critical Path Benefits: –Determines shortest project completion time –Identifies “critical” activities – that can not be slipped or delayed (i.e.- “TOTAL FLOAT”) –Shows allowable slippage for “non-critical” activities (i.e.- “FREE FLOAT”) Disadvantages: –Large number of activities required –Difficult to read, understand, and maintain.

SCHEDULING: CPM/ADM ADM (Arrow Diagramming Method): –Arrow (line): represents an Activity –Tail (of arrow): shows an Activity’s start –Head (of arrow): shows an Activity’s finish –Node (or event): shown at each end The “Activity Number” consists of Head and Tail numbers, commonly referred to as I-J nodes (i.e.- “I-J Method” of CPM)

SCHEDULING: CPM/ADM ADM: Arrow Diagramming Method Process Work Order Requisition Material Install Pump Assign Crew (Dummy Activity – shows relationship, zero duration)

SCHEDULING: CPM/ADM Benefits: –Allows use of “Dummy Activities” which: Have a “ZERO” time duration Can be used to show additional relationships Disadvantages: –An Activity’s “Predecessor” must be complete before the Activity can start! –Neither the Activity’s “arrow length” or “arrow direction” have any meaning

SCHEDULING: CPM/PDM PDM (Precedence Diagramming Method): –Box/ Node: represents an Activity –Line/ Arrow: represents a Precedence – with time and direction properties Precedence consist of two parts: –“Relationship”: a Predecessor or Successor –“Lag”: the (positive or negative) number of work periods by which a specified Activity will be delayed (assumed to be “0” if not specified)

SCHEDULING: CPM/PDM PDM: Precedence Diagramming Method AC D E Process Work Order B Requisition Material Install Pump Assign Crew Pump Installation Completed

SCHEDULING: CPM/PDM Types of Relationships, Lags (aa,n): –FS, 0: Finish-to-Start, With “0 units” of delay –FF, 7: Finish-to-Finish, with “7 units” of delay –SS, 5: Start-to-Start, with “5 units” of delay –SF, 0: Start-to-Finish, with “0 units” of delay

SCHEDULING – PDM/ LOGIC Relationships (Logic Ties, Lags A B A B A B A B Start –to- Finish Finish -to- Finish Finish –to- Start Start –to- Start (FS,0) (FF,5) (SS,4) (SF,0)

SCHEDULING: CPM/PDM “6” Major Types of Constraints –Start On: a mandatory date –Start No Earlier Than*: can start “later” –Start No Later Than*: can start “earlier” – Finish On: a mandatory date –Finish No Earlier Than*: can finish “later” –Finish No Later Than*: can finish “earlier” * NOTE: Schedule logic drives “earlier” and “later” start and finish dates

SCHEDULING- PDM/ OTHER Hammock Activity –Spans many activities to show an “overall” performance period (i.e.- a summary activity) Logic Loop –One of the most common “scheduling errors” –Occurs when a set of activities precede each other in a “circular” fashion, (a group of activities can never begin nor end) –Must be eliminated prior to calculating the schedule (i.e.- running a time analysis)

SCHEDULING- Hammock PDM: Hammock (Summary) Activity A BC E D

SCHEDULING – PMD/LOOP LOOP: No beginning or end (a circular path) LOOP A BCD E F

SCHEDULING – PDM/ CALC’S Once a network has been created and the durations estimated for each activity, both the “Total Time” to reach project completion and each activity’s “individual” start and finish times, can be calculated –Manual computation is easy and logical (but tedious & time-consuming on large projects) Forward Pass: calculates early start/finish, (ES/EF) Backward Pass: calculates late start/finish, (LS/LF)

SCHEDULING – CALC’S FORWARD PASS: –Calculates “Earliest Start” and “Earliest Finish” times, observing the following rules: Assign an “ES” time to the first activity Other activities start as soon as their “predecessor” relationships have been satisfied Equations: –ES = EF (Pred.) + 1 –EF = ES + Duration - 1

SCHEDULING – CALC’S BACKWARD PASS: –Calculates “Latest Start” and “Latest Finish” times, observing the following rules: Assign an “EF” time to the last activity. All activities finish as soon as their “Successor” relationships have been satisfied. Equations: –LF = LS (Succ.) – 1 –LS = LF – Duration + 1

SCHEDULING – CALC’S PDM ACTIVITY NOTATION: –Activity Number: unique number to an activity –Duration: number of “work periods” assigned –ES & EF: calculated in Forward Pass –LS & LF: calculated in Backward Pass ACTIVITY NUMBER ES EF LSLF DURATION 1A5 357

Legend Activity ID ES Duration EF LS LF START FINISH FORWARD & BACKWARD PASS

Legend Activity ID ES Duration EF LS LF START FINISH FORWARD & BACKWARD PASS Early Dates: ESs = EFp + 1 EFs = ESs + Ds - 1

Legend Activity ID ES Duration EF LS LF START FINISH FORWARD & BACKWARD PASS Late Dates: LFp = LSs -1 LSp = LFp – D +1

Legend Activity ID ES Duration EF LS LF START FINISH FORWARD & BACKWARD PASS Late Dates: LFp = LSs -1 LSp = LFp – D +1

What is the Scheduling Process? Report/ Status Scheduling Planning

IDENTIFY MILESTONES Project Start Project Phase Start and Finishes Equipment and/ or Long Lead Item Delivery Project Finish

DEVELOP ACTIVITY LIST (EXAMPLE: HOUSE CONSTURCTION) Select Lot Clear and Grub Lot Install Utilities Construct House Select Contractors Arrange Financing Close Financing Landscape Purchase Appliance and Lighting Fixtures Install Flooring Paint

ASSIGN DURATION TO ACTIVITES (EXAMPLE: HOUSE CONSTRUCTION) Select Lot3 days Clear and Grub Lot10 days Install Utilities3 days Construct House60 days Select Contractors5 days Arrange Financing5 days Close Financing 1 day Landscape5 days Purchase Appliance/Lighting Fixtures1 day Install Flooring 5 days Paint5 days

SEQUENCE ACTIVITIES ASK THREE QUESTIONS! What activity must come before this one? What activity must come after this one? What activities can I perform at the same time?

REVIEW AND FINALIZE Review Relationships Review and Finalize Durations Review Resource Usage Review and Finalize Project End Date –Does this achieve the desired date? –If it does not…. What is the plan NOW?!?

SCHEDULING- CONCLUSION Planning and scheduling functions are usually performed iteratively in order to provide for accomplishing all required tasks within the specified time frames Both Critical Path Methods (ADM & PDM) create networks showing activity durations and total time for project completion “Failing to Plan is Planning to Fail”, hence “Plan the Work, Work the Plan”