INDEPENDENT COST ESTIMATES AND COST REVIEWS Michael Peek, PE CCE CFM Office of Engineering and Construction Management.

Slides:



Advertisements
Similar presentations
The Department of Energy Enterprise Risk Management Model
Advertisements

Contract and Project Management: A Field Perspective Moderator Michael Peek, PE CCE CFM Office of Engineering and Construction Management.
Roadmap for Sourcing Decision Review Board (DRB)
Ensure Vendor/Engineer of Choice Product Quality
DOT Office of Inspector General Audit of DOT’s Office of the Secretary’s Acquisition Function Federal Audit Executive Council Procurement Training Conference.
COST CONTROLS OF CAPITAL COSTS THROUGHOUT THE DESIGN PHASE Presented by Planning & Management Services, Inc Federal Way, WA (near Seattle) Western Winter.
TITLE OF PROJECT PROPOSAL NUMBER Principal Investigator PI’s Organization ESTCP Selection Meeting DATE.
TEHRAN 4-5 MARCH 2012 IDB-ECO PROJECT RISK MANAGEMENT WORKSHOP 5/4/2015 Shehzad Akram 1.
TITLE OF PROJECT PROPOSAL NUMBER Principal Investigator PI’s Organization ESTCP Selection Meeting DATE.
© 2015 Cengage Learning. All Rights Reserved. May not be scanned, copied or duplicated, or posted to a publicly accessible website, in whole or in part.
NEES Project Management Workshop June 16 June 18 1 Segment 2.
Overarching Roles of Critical Partners In A Project 9:30 – 10:00 Rob Curlee, FMO Joseph Dominque, OCISO Mike Perry, EA.
Presentation By: Chris Wade, P Eng. Finally … a best practice for selecting an engineering firm.
Project Management Process Project Description Team Mission/ Assignment Major Milestones Boundaries Team Identification Measures of Success Roles & Responsibilities.
Course Technology Chapter 3: Project Integration Management.
Iterative development and The Unified process
Certified Business Process Professional (CBPP®) Exam Overview
Pre-Project Planning Lessons from the Construction Industry Institute Construction Industry Institute Michael Davis, P. Eng, PMP Ontario Power Generation.
PRESENTED BY TRUST THOMAS EROMOSELE STUDENT NO:
Auditing Standards IFTA\IRP Audit Guidance Government Auditing Standards (GAO) Generally Accepted Auditing Standards (GAAS) International Standards on.
What is Business Analysis Planning & Monitoring?
Challenges Faced in Developing Audit Plans and Programs 21 st March, 2013.
S/W Project Management
1 Module 4: Designing Performance Indicators for Environmental Compliance and Enforcement Programs.
System Planning- Preliminary investigation
Lori Smith Vice President Business Intelligence Universal Technical Institute Chosen by Industry. Ready to Work.™
U.S. Department of Energy Project Management: Communicating Progress – Celebrating Success Paul Bosco, PE, PMP, CFM, LEED-AP Director, Office of Procurement.
NIST Special Publication Revision 1
The Challenge of IT-Business Alignment
© Grant Thornton | | | | | Guidance on Monitoring Internal Control Systems COSO Monitoring Project Update FEI - CFIT Meeting September 25, 2008.
PPMT CE-408T Engr. Faisal ur Rehman CED N-W.F.P UET P.
Department of the Interior CPIC Forum Department of the Interior CPIC Forum Capital Planning and Investment Control (CPIC) Revisions to the Construction.
Quality Management.  Quality management is becoming increasingly important to the leadership and management of all organisations. I  t is necessary.
GBA IT Project Management Final Project - Establishment of a Project Management Management Office 10 July, 2003.
Centro de Estudos e Sistemas Avançados do Recife PMBOK - Chapter 4 Project Integration Management.
Introduction- Project Management By Ctrl+C & Ctrl+V 1.
1.  Describe an overall framework for project integration management ◦ RelatIion to the other project management knowledge areas and the project life.
Basic of Project and Project Management Presentation.
Strong9 Consulting Services, LLC 1 PMI - SVC I-80 Breakfast Roundtable Monthly Meeting Thursday, October 12, :00 am – 9:00 am.
ISM 5316 Week 3 Learning Objectives You should be able to: u Define and list issues and steps in Project Integration u List and describe the components.
Executive Session Director’s CD-3b Review of the MicroBooNE Project January 18, 2012 Dean Hoffer.
CHECKPOINTS OF THE PROCESS Three sequences of project checkpoints are used to synchronize stakeholder expectations throughout the lifecycle: 1)Major milestones,
0 Office of Performance Assessments and Root Cause Analyses (PARCA) PARCA EVM Update Presenter: Phone:
DOE Order 413.3A Program and Project Management for the Acquisition of Capital Assets Catherine Santana Deputy Director, Project Management Systems, OECM.
Earned Value Management Presented By: Steve Krivokopich May , 2006.
Chapter 3 Strategic Information Systems Planning.
DOE ASSET MANAGEMENT PLAN
Consultant Advance Research Team. Outline UNDERSTANDING M&E DATA NEEDS PEOPLE, PARTNERSHIP AND PLANNING 1.Organizational structures with HIV M&E functions.
1 Global Design Effort: Controls & LLRF Controls & LLRF Working Group: Tuesday Session (29 May 07) John Carwardine Kay Rehlich.
The Project Plan Plan Your Work, then Work Your Plan
SCOPE DEFINITION,VERIFICATION AND CONTROL Ashima Wadhwa.
| 1 Weapon System Acquisition Reform- Product Support Assessment DAU SYMPOSIUM 13 April 2010 Presented by: Basil Gray Where Innovation.
Continual Service Improvement Methods & Techniques.
Company LOGO. Company LOGO PE, PMP, PgMP, PME, MCT, PRINCE2 Practitioner.
Project Management Career Development Program (PMCDP) development-program Linda Ott.
ICAJ/PAB - Improving Compliance with International Standards on Auditing Planning an audit of financial statements 19 July 2014.
GAO’s Cost and Schedule Assessment Guides U.S. Government Accountability Office Applied Research and Methods Cost Engineering Sciences Jason T Lee, Assistant.
Project Delivery Working Group FY2016 EFCOG Annual Meeting Robert P. Miklos Idaho National Laboratory Battelle Energy Alliance Working Group Chair June.
IV&V Facility 7/28/20041 IV&V in NASA Pre-Solicitation Conference/ Industry Day NASA IV&V FACILITY July 28, 2004.
AUDIT STAFF TRAINING WORKSHOP 13 TH – 14 TH NOVEMBER 2014, HILTON HOTEL NAIROBI AUDIT PLANNING 1.
Principal Investigator ESTCP Selection Meeting
Project Cost Management
12.2 Conduct Procurements The process of obtaining seller responses, selecting a seller and awarding the contract The team applies selection criteria.
Principal Investigator ESTCP Selection Meeting
Identify the Risk of Not Doing BA
Capital Asset Projects executed by the
Mumtaz Ali Rajput +92 – SOFTWARE PROJECTMANAGMENT– WEEK 4 Mumtaz Ali Rajput +92 – 301-
Principal Investigator ESTCP Selection Meeting
Cost Estimating Best Practices
Principal Investigator ESTCP Selection Meeting
Presentation transcript:

INDEPENDENT COST ESTIMATES AND COST REVIEWS Michael Peek, PE CCE CFM Office of Engineering and Construction Management

Click to LOOK INSIDE! EINSTEIN’s Abbreviated Guide To INDEPENDENT COST ESTIMATES AND COST REVIEWS Michael Peek, PE CCE CFM But what should it really cost? E = Mc 2 = TPC =

Why Independent Cost Estimates and Cost Reviews? Support Secretarial/Acquisition Executive decision making Logical “next step”… increase focus on front-end planning Address External Stakeholder Concerns – Consistent with GAO Best Practices Guidelines (GAO-09-3SP) – Adopt Industry Standards Requirements addressed in DOE O 413.3B Statutory requirement … mandated in FY2012 Consolidated Appropriations Act (P.L ) We cannot solve our problems with the same thinking we used when we created them. Albert Einstein

With the implementation of DOE Order 413.3B, Program and Project Management for the Acquisition of Capital Assets, the Office of Engineering and Construction Management is required to conduct an Independent Cost Review (ICR) and/or develop an Independent Cost Estimate (ICE) to support the Secretarial Acquisition Executive’s (SAE)/Acquisition Executive’s (AE) decision at various Critical Decision (CD) milestones … RequirementDOE O 413.3B Cost Reviews (App C, Sec 18.) For projects > $750M, OECM must conduct ICR prior to CD-0 For projects > $100M, OECM must conduct: Prior to CD-1, ICE and/or ICR Prior to CD-2, ICE Prior to CD-3, ICE (if warranted) DOE O 413.3B Requirements If you can't explain it simply, you don't understand it well enough. Albert Einstein

FY2012 Consolidated Appropriations Act Requirements (P.L ) Sec 308: None of the funds made available in this title may be used to approve critical decision-2 or critical decision-3 under Department of Energy Order 413.3B, or any successive departmental guidance, for construction projects where the total project cost exceeds $100,000,000, until a separate independent cost estimate has been developed for the project for that critical decision. A perfection of means, and confusion of aims, seems to be our main problem. Albert Einstein

Best Practices GAO Cost Estimating and Assessment Guide: Best Practices for Developing and Managing Capital Program Costs, March 2009 (GAO-09-3SP) Association for the Advancement of Cost Engineering International (AACEI) – Recommended Practices – Professional Practice Guides Society of Cost Estimating and Analysis (SCEA) – Cost Estimating Body of Knowledge (CEBok) DOE G Cost Estimating Guide, May 2011 The only source of knowledge is experience. Albert Einstein

High Quality Cost Estimate Characteristics: – Comprehensive … addresses all known costs appropriate for the level of project definition – Well-documented... basis of estimate allows for independent replication and updating – Accurate … is free from errors and omissions – Credible … is well structured and presented in an industry accepted format Any intelligent fool can make things bigger and more complex... It takes a touch of genius - and a lot of courage to move in the opposite direction. Albert Einstein

Basis of Estimate A well prepared Basis of Estimate (BOE): – Documents overall project scope … – Facilitates review and validation of the cost estimate … – Alerts project team to potential cost risks and opportunities … – Record of key communications made during estimate preparation … – Establishes initial baseline for scope, quantities and cost for use in cost trending … – Source of support during dispute resolutions … – Provides historical relationships between estimates … Everything should be made as simple as possible, but not simpler. Albert Einstein

Everything that can be counted does not necessarily count; everything that counts cannot necessarily be counted. Albert Einstein Identify/Focus on Cost Drivers – Cost drivers require a detailed independent estimate – Early technical, cost and schedule risk identification Methodology – Bottom-up – Parametric Cost Models & Cost Estimating Relationships – Engineering judgment – Vendor quotes/vendor proposals Updated throughout the project cycle … – Trend should cost versus will cost The Cost Estimate

Historical Cost Data – Identify useful Cost Estimating Relationships … focusing on 10 selected projects Percent of TPC devoted to specific project phases Evaluation of Program Cost Estimates Start-up & Commissioning CERs of special interest WBS Best Practices Handbook – Product oriented … collaborate on standardization by project type… – Common element structure to capture cost data for common scope across projects … Other Initiatives I have no special talent. I am only passionately curious Albert Einstein

Evaluating existing data sources and estimating tools across DOE … – Oak Ridge; EM CBC – PARS II & ACDB OECM Promote cost estimating consistency … – Common framework within each Program – Increased sharing of existing cost data Address inflation indices … Program Office/PMSO and EFCOG support critical for success … Other Initiatives The only thing that interferes with my learning is my education. Albert Einstein

Bottom Line A cost estimate is only as good as the project’s components … Upfront planning - design maturity and technology readiness … Risk identification and management … Stable funding commitments … Properly resourced staffing - numbers and skill sets … Credible and consistent contract management and alignment … Optimized oversight and reporting … Anyone who doesn't take truth seriously in small matters cannot be trusted in large ones either. Albert Einstein

Take Aways Independent Cost Estimates and Independent Cost Reviews should: Enable Risk Informed Cost Effective Decisions Support Mission, Program and Project Execution  Emphasis on Program and Project Accountability  Should Cost vs. Will Cost Be based on industry accepted standards and processes Strive not to be a success, but rather to be of value. Albert Einstein

Questions? OECM I Unthinking respect for authority is the greatest enemy of the truth. Albert Einstein