CPA A house is to have new carpets fitted throughout. The work involved has been divided into a number of tasks, as shown in the table.

Slides:



Advertisements
Similar presentations
Critical Path Analysis. Why Is CPA Important? CPA is arguably the piece of maths used most often, outside of basic arithmetic. Important not only in commerce.
Advertisements

Lecture Network Analysis
CP Chapter 4 Schedule Planning.
Richard Fisher 1 The University of Texas at Dallas Project Management BA 4320 Richard Fisher The University of Texas at Dallas.
Exemplar A. Introduction Proman is a company that specialises in managing building projects. It has been contracted to manage a project to build a new.
ES=32 EF=34 LS=33 LF=35 ES=10 EF=16 LS=10 LF=16 ES=4+6=10 EF=10 LS=4
Critical Path Analysis. There are no pre-requisites for this Achievement Standard so it can be placed in any course. No knowledge is pre-supposed.
Network Diagramming Network Analysis  The common term for network analysis is PERT  PERT stands for Program Evaluation and Review Technique  The word.
Project Scheduling Tools As part of CSA3040 © 2003, 2004 – Dr. Ernest Cachia.
Gantt Chart Graph or bar chart with a bar for each project activity that shows passage of time Provides visual display of project schedule Slack amount.
CSSE 372 Week 6 Day 2 Constructing and Analyzing the Project Network Diagram  PERT Chart PERT was invented for the Nautilus submarine project. Ok, maybe.
Tutorial 2 Project Management Activity Charts (PERT Charts)
PREPARED BY : NOR AZAH BINTI AZIZ KOLEJ MATRIKULASI TEKNIKAL KEDAH PROJECT NETWORK DIAGRAM.
Project Planning. Learning Objectives: By the end of this topic you should be able to:
CPA Setting up an ICT system. A consultancy company has divided the work into a number of activities. The table below shows the details. ActivityImmediate.
© Nuffield Foundation 2011 Nuffield Free-Standing Mathematics Activity Refurbishing a room © Nuffield Foundation 2011.
Activity networks – Example 1 TaskDuration (hours)Immediate predecessors A3- B4- C6- D5A E1B F6B G7C, D, E The table below shows the tasks involved in.
___________________________________________________________________________ Quantitative Methods of Management  Jan Fábry Project Management Example -
Critical Path Analysis Activity Duration mins Shower3 Dry hair8 Fetch car7 Iron clothes12 Dress and make-up10 Drive to interview20.
Module 5 – Networks and Decision Mathematics Chapter 24 – Directed Graphs.
Precedence Network Calculations the basic information that should be calculated in the precedence network are: 1) Early activity start (ES) 2) Early activity.
15C Backward scanning and crashing
Using MS Project To draw a Network diagram. Add tasks Add the 8 tasks listed for making a cup of tea. Add the duration of each –Note: MS Project doesn’t.
Projmgmt-1/14 DePaul University Project Management I - Realistic Scheduling Instructor: David A. Lash.
Copyright 2006 John Wiley & Sons, Inc. Beni Asllani University of Tennessee at Chattanooga Project Management Operations Management - 5 th Edition Chapter.
USING MS PROJECT Project management software programs such as Microsoft Project can be used for developing the project schedule We demonstrate the use.
Project Management Chapter 3 BUSI 2106 – Operations Management.
___________________________________________________________________________ Operations Research  Jan Fábry Project Management.
USING MS PROJECT 2010 Project management software programs such as Microsoft Project 2010 can be used for developing the project schedule and budget, and.
PROJECT MANAGEMENT Syllabus Outcomes : Construct and interpret a network, identify the critical path, and calculate the free and total float. Evaluate.
1 Project Management Chapter Lecture outline Project planning Project scheduling Project control CPM/PERT Project crashing and time-cost trade-off.
Chapter 17 Project Tracking. Objectives Identify, develop, and use project management tools to track project progress: Schedules Gantt Charts Toll Gate.
Unit 9.2_Lesson 2_CD Resource 2f_Plenary Gantt charts From the Gantt Chart answer the question.
CPA A group of workers is involved in a building project. The table shows the activities involved. Each worker can perform any of the given activities.
Activity- Jobs Time (hours) Preceding Activities-Jobs Decorating & furnishing a spare bedroom 1 Remove old furniture Remove carpet Take down curtains &
Activity Time (hours) Preceding Activities Decorating & furnishing a spare bedroom 1 Remove old furniture Remove carpet Take down curtains & rail Remove.
You are part of the sports committee in your school and so it is your responsibility to organise this year’s swimming gala. There are many tasks that.
1 Selected Topics on Project Management The Critical Path Dr Marc Conrad 1Marc Conrad.
Business Department Session 6 Exam Question –Draw Network diagram –Identify Critical path –Sketch Gantt Chart –‘Crash’ the project Reduce the project completion.
11/02/09 Chapter 7-Project Planning 1 Elements of Project Planning  Divide project into tasks, tasks into subtasks, subtasks into...  Estimate duration.
Chapter 12 Network Scheduling Techniques. Scheduling Techniques Gantt or bar charts Gantt or bar charts Milestone charts Milestone charts Line Balancing.
University of Sunderland CIFM02 Unit 2 COMM02 Activity Planning Unit 2.
Advanced Project Management Tools and Techniques of Project Planning Ms. Ghazala Amin Slides Courtesy: Dr. A Z. Khan.
Operational strategies Lean production. The adoption of techniques that help to reduce waste.
Quick 5 Quiz Are you ready …… ?!. Question 1 A ‘Critical’ Task is one which (could be more than 1) … A.Will be part of the Critical Path B.Any delay therein.
15B Critical path analysis. In a critical path analysis, edges represent activities. Nodes (vertices) represent the end of one activity and the start.
Scheduling and Budgeting Engineers Without Frontiers CEE 402.
IE 366 Chapter 6, Section 10 Project Planning and Scheduling.
Network Diagram Prob 1 Activity Predecessor Duration (days) A None 2 B
& Urban Planning Civil Engineering Department
Project Management: PERT/CPM
PERT & GANTT CHARTS An Introduction.
Activity networks – Example 1
Project Scheduling Lecture # 1.
Critical Path Analysis (CPA)
Unit 4 Project Design, implementation and evaluation
معرفي روش هاي برنامه ريزي شبكه و محاسبات زمان
Analysing the AoA network
SE Tasks for a Concept Development Project
Critical Path Analysis
Nuffield Free-Standing Mathematics Activity Refurbishing a room
Activity on Node Approach to CPM Scheduling
BEST VIEWED IN SLIDE SHOW MODE
Critical Path Analysis
Critical Path Analysis
Project Planning By Phaik San Liew.
Planning assignment in MS-Project
Exercise – A small building.
Critical Path Analysis
Presentation transcript:

CPA A house is to have new carpets fitted throughout. The work involved has been divided into a number of tasks, as shown in the table.

CPA A house is to have new carpets fitted throughout. The work involved has been divided into a number of tasks, as shown in the table. Construct an activity network for the project

CPA Construct an activity network for the project Find earliest start times (forward pass) Find latest finish time (reverse pass) BA F E CD GH I J K

CPA Construct an activity network for the project Find earliest start times (forward pass) Find latest finish time (reverse pass) BA F E CD GH I J K

CPA Construct an activity network for the project Find earliest start times (forward pass) Find latest finish time (reverse pass) BA F E CD GH I J K The Critical path is: C D F G H J K and the time to complete the task is 9.9 hours

CPA Construct a Cascade Diagram or Gantt Chart The Critical path is: C D F G H J K and the time to complete the task is 9.9 hours Floats: A – 0.8; B – 0.8; E – 0.8; I – 0.1 BA F E CD GH I J K

CPA BA F E CD GH I J K Time in hours Activity

CPA Construct an activity network for the project Find earliest start times (forward pass) Find latest finish time (reverse pass) BA F E CD GH I J K The Critical path is: C D F G H J K and the time to complete the task is 9.9 hours