E. Michael Saleski PPS and BCS Systems Manager

Slides:



Advertisements
Similar presentations
1 BROOKHAVEN SCIENCE ASSOCIATES NSLS-II Shielding Workshop S. Buda Personnel Protective Systems March 27, 2007.
Advertisements

1 BROOKHAVEN SCIENCE ASSOCIATES Presentation to ASAC R. Casey Radiation Shielding: Assumption and Design April 24, 2007.
FAC review, 10/27 D. Schultz 1 e-Beams System Update Injector System Installation has started. Linac System Preparing for ’06 installation. Controls System.
FAC, 10/12/06 D. Schultz 1 e-Beams Systems Update Linac Injector Undulator Production MMF commissioning ARR David Schultz.
FAC, 4/20/06 D. Schultz 1 e-Beams System Update Linac System Preparing for downtime installation. Injector System Installation has started. Undulator System.
Safety Oversight for SLAC Accelerator Department Operations
PROBLEM: Radiation Dose Rate in IR2 When IR1 is Operating (and Vice Versa) Muon Dose Rate > 1 mRem/hr for 0.1% Collimated Halo.
LCLS Linac System Management Linac Coherent Light Source Stanford Synchrotron Radiation Laboratory Stanford Linear Accelerator Center.
Hamid Shoaee LCLS FAC Controls June 17, LCLS Control System Personnel Linac & BC2 Controls progress LTU, Dump Controls.
Eric Bong LCLS FAC Injector-Linac System October 27, 2005 Injector –Linac System Overview E. Bong LCLS FAC October 27, 2005.
E. Michael Saleski PPS and April 20, 2006 LCLS Personnel Protection System and Beam Containment System E. Michael Saleski.
David H. Dowell Injector April 29-30, 2004 LCLS Injector Overview D. H. Dowell, SLAC FAC Review April 29-30, 2004 Injector.
PPS and BCS Requirements for LCLS-II (Baseline) Stan Mao 06/10/2015.
FAC, 10/12/06 D. Schultz 1 Readiness for 2007 Startup Linac Injector Controls ARR David Schultz.
Injector Accelerator Readiness Review, 10/31/06 Henrik Loos 1 Beam Losses During LCLS Injector Phase-1 Operation Scope of phase 1 operation Operating modes.
LCLS-II Linac LLRF Control System – L2, L3 Zheqiao Geng Preliminary Design Review May 7, 2012.
Stephen Schuh Vacuum Controls SCR and 16 November 2005 Vacuum Controls System Concept Review and Preliminary Design Review.
Global Design Effort Beam Delivery System => EDR LCWS07 June 2, 2007 at DESY Andrei Seryi for BDS Area leaders Deepa Angal-Kalinin, A.S., Hitoshi Yamamoto.
1 BROOKHAVEN SCIENCE ASSOCIATES Redundancy Requirements for Critical Devices R. Casey August 8, 2007.
D. Beavis (RSC) May 4, 2010 EBIS ARR Radiation Safety.
MINU GPP WBS 1. Main Injector Neutrino Upgrades - Infrastructure Project Dixon Bogert APD Department Report – March 7, 2007 Russ Alber - FESS Engineering.
ATF2 Commissioning Toshiyuki Okugi 2008 / 7 /9 ATF2 beam commissioning meeting, KEK.
Friday April 7, 2006 J. Anderson Jr. Page 1 ES&H Safety System Upgrades  Data Acquisition System 95% Complete 16 of 17 Linux Ethernet Port Replicator.
1 BROOKHAVEN SCIENCE ASSOCIATES Summary of Shielding Calculations for NSLS2 Accelerators P.K. Job Radiation Physicist Peer Review 2007 March
Thickness of the Kamaboko Tunnel Shield Wall under Different Assumptions Ewan Paterson ADI Meeting July 2, ADI Meeting Ewan Paterson 7/2/15.
1 Sector Test – Preparation Layout in LSS7 Jan Uythoven (AB/BT) Thanks to Mike Lamont and the other ‘sector testers’
August 12, Machine Status: 2013  Proton Source Commissioning and Studies RFQ Injector Line (RIL) Linac : Roof hatch installed Booster : Magnet.
31, LCLS Maintenance Personnel and Procedures Paul Bellomo.
PAL-XFEL Commissioning Plan ver. 1.1, August 2015 PAL-XFEL Beam Dynamics Group.
18/March/2008OP-days S.Mataguez / O.Hans1 Hardware Problems in the PS complex LINAC 2 BOOSTER PS AD Thanks to all that helped and provided information,
21 July 2006, Vancouver Global Design Effort 1 PPS - division into zones and shield wall locations - N. Terunuma KEK.
ALS-U Radiation Safety Systems
Shielding Design for LCLS Injector Operation – Phase one
G0 Backward Angle Accelerator Preparations
Maintain a single control room for all accelerator programs
Injector Performance Requirements Conventional Facilities Update
LCLS Injector: Introduction D. H
LCLS Linac Update Brief Overview L1 & BC1 Progress LTU & E-Dump Status Continuing Resolution Impact.
Injector –Linac Status & Schedule E. Bong LCLS FAC October 12, 2006
Interlocking of CNGS (and other high intensity beams) at the SPS
Diagnostics overview and FB for the XFEL bunch compressors
LTU/Undulator Installation Status
LCLS Injector Commissioning Dates ( )
Stanford Linear Accelerator Center
Machine Protection for LCLS Injector Commissioning (IMPS)
Thickness of the Kamaboko Tunnel Shield Wall under Different Assumptions and the Impact on Operations Ewan Paterson LCWS15 Meeting NOV 3, /24/2019.
FACET Accelerator Overview
Linac/BC1 Commissioning P
Electron Beam Systems ETC and Methodology
Injector / Linac Installation Current Status
LCLS Commissioning P. Emma, et al
INJECTOR (WBS 1.2.1) Jym Clendenin, SLAC April 23, 2002
FACET Accelerator Overview
Maximum Credible Beam Event Paul Emma et al
Breakout Session SC5 – Control Systems
Operational Experience with LCLS RF systems
LCLS Injector Configuration
LCLS Personnel Protection System and Beam Containment System
E-Beams Systems Manager
LCLS Injector System Overview D. H
Control System Overview Hamid Shoaee LCLS Control System Manager
SLAC Radiation Safety Work Control Form Process:
Injector/Linac Design Status C. E
LCLS Machine Protection System
LCLS e- Beams System Overview
CF Scope, Management & Organization
LINAC System Engineering / Design Status C.E. Rago
LCLS Control System Personnel Linac & BC2 Controls progress
LCLS e- Beams Systems Manager
Control System Overview Hamid Shoaee LCLS Control System Manager
Presentation transcript:

E. Michael Saleski PPS and BCS Systems Manager LCLS Personnel Protection System, Beam Containment System, (and misc. Safety Inspection Items) E. Michael Saleski PPS and BCS Systems Manager

LCLS: PPS-eye View

LCLS Injector Vault Layout

LCLS Injector WG Plumbing

Simplified PPS System Architecture

LCLS Injector Vault Under-Floor Searching

PPS Summary Diagnostic Panel has individual ‘A/B’ status for all items Allows for simpler micro-switch testing Equipment gate micro-switches are special safety switches – can only be actuated with special tabs on doors Ultimately will use similar to PEP-style BSOICs; stuck with SLAC Classic BSOICs for now Commissioning second or third week of January; much is invasive to PEP operations

BCS Definition and Project Scope Prevents radiation from ‘escaping’ the shielding enclosure Direct measurements of radiation or beam loss Protection of safety-critical collimators and stoppers Entirely ‘new’ LCLS BCS needed New gun = new shut-off mechanisms Support two simultaneous programs (LCLS & PEP) = new set of shut-off paths [Reduce mutual interference of programs as much as possible = desire targeted shut-offs if plausible –later]

BCS System Scope Original ‘Mode-switching’ BCS proposal has been sidelined for now Propose an ‘Interim BCS’ where conservatively “All BCS faults shut-off all Guns.” Mode-switching requirements are now better understood – move forward with second proposal for 2007 downtime implementation

LCLS Injector Shut-Off Mechanisms Laser Safety Stopper (LSS) Dedicated BCS LSS situated in Injector Vault, stops the production of primary beam Dark Current may persist Accelerator Sections move to Staggered Standby New injector sections L0A and L0B together will move to staggered standby with the rest of the Linac New Sub-Booster Interface needs to be developed, new high-stability Solid State Sub-booster is not compatible with old SBI Module Stops primary beam and dark current acceleration RF Gun moves to Staggered Standby RF Gun equivalent to removal of triggers at CID Staggered with respect to L0A and L0B Also uses new SBI

Interim BCS System Architecture

Configuration ‘Alpha’ CID beam to PEP, and A-Line or SABER; LCLS Beam to LCLS Linac Injector Spectrometer (SDMP) Power Supply for magnets BX01/BX02 will be locked off BSY BCS will be active as appropriate for parasitic program (common line, NARC/SARC, A-Line) and possible accidental LCLS beam delivery to BSY

Configuration ‘Beta’ CID beam to PEP; LCLS beam injected into Linac through TD11 or to the LCLS Linac Injector Spectrometer Dump TD11 will be disabled ‘IN’ Linac BAS II stoppers (BAS II Dump, ST950, ST960) administratively inserted 50B1 and B1/2 locked out; Common Line BSY BCS are active

Configuration ‘Beta-prime’ CID beam to PEP; LCLS beam injected into Linac past TD11 (or to the LCLS Injector Spectrometer) Dump TD11 will be allowed ‘OUT’ BAS II ‘inserted’ with air valve – not a safety item B1/2 remain locked out; Common Line and NARC/SARC BSY BCS are active

Safety Inspection Items (?) PPS: 3 BSOICs, 1 stopper (RST1) Locked Entry Module roof hatch BCS: 4 LIONs Spot Shielding: 21-1,-2,-4 have 24” of borax (also wider) SDMP has down-beam (4-inch thick Pb, 24”x26”) and aisle shielding (sliding 5-inch thick Fe, 43”x31”) TD11 has penetration shielding (1 ¾-inch thick Fe, 25”x40”) and aisle shielding (sliding 5-inch thick Fe, 43”x31”)