Tender for EC-Units assembly Sylvie Dagoret-Campagne EC-Design Review, March 1st 2012, LAL1
The tender Phase 1 : mechanical prototype – At least 4 fake MAPMT – The mold design and production – Tools Phase 2 : electronical prototype Phase 3 : 9 FM EC-Units EC-Design Review, March 1st 2012, LAL2
Validation and corrections 15 days for LAL checking the proto 15 days to correct the proto EC-Design Review, March 1st 2012, LAL3
Cost Element MATRARESAAXINTECA Phase 1 proto-mécafaux PMT Outillage-Etude enrobage assemblage enrobage 450 Total Phase 2 proto- electronique Outillage-Etude enrobage2000 assemblage enrobage 450 total Phase 3 FMpar unité pour par rechange pour total TOTAL Toutes les phases EC-Design Review, March 1st 2012, LAL4
Time ElementMATRARESAAXINTECA Phase 1proto-méca10 weeks18 weeks4 weeks Phase 2proto-electronique2 weeks3 weeks2 days Phase 3EC-rate1/week1,5/week1 day 9-FM8 weeks13,5 week9 days 2-spares5 weeks3 weeks2 days TOTAL without spare20 weeks34,5 weeks6 weeks TOTAL with spare25 weeks37,5 weeks EC-Design Review, March 1st 2012, LAL5
Comment Very different propositions – AXINT, very fast and very cheap – RESA, very slow and very expensive Interactions – Deep technical discussions with RESA Need a carefull analysis of technical solutions with AXINT and MATRA EC-Design Review, March 1st 2012, LAL6