Project Management: A Managerial Approach

Slides:



Advertisements
Similar presentations
Prepared by Scott M. Shafer, Updated by William E. Matthews and Thomas G. Roberts, William Patterson University Copyright 2007 John Wiley & Sons, Inc.5-1.
Advertisements

Project Management in Practice, Fourth Edition Prepared by Scott M. Shafer, Updated by William E. Matthews and Thomas G. Roberts, William Paterson University.
Scheduling the Project
Project Scheduling: Gantt/Pert Charts
MEM 612 Project Management Chapter 5 Scheduling the Project.
Gantt Chart Graph or bar chart with a bar for each project activity that shows passage of time Provides visual display of project schedule Slack amount.
Project Management in Practice Fifth Edition Copyright © 2014 John Wiley & Sons, Inc. Chapter 5 Scheduling the Project.
MGMT 483 Week 8 Scheduling.
Project Management: A Managerial Approach 4/e
Project Management: A Managerial Approach
Chapter 9 Project Management.
Project Management A Managerial Approach
Operations and Supply Chain Management, 8th Edition
Copyright 2012 John Wiley & Sons, Inc. Chapter 8 Scheduling.
Information Technology Project Management
OM480 Defining the Project Parameters – Scheduling 101 (With Material from the Text Authors)
OPERATIONS MANAGEMENT for MBAs Fourth Edition
Chapter 171 Stabilizing the Quality System Chapter 17 Achieving Quality Through Continual Improvement Claude W. Burrill / Johannes Ledolter Published by.
Project Management © Wiley 2007.
Information Technology Project Management
Time Management Week 7 - Learning Objectives You should be able to: n List and describe the processes, activities, inputs, and outputs in time management.
THE MANAGERIAL PROCESS Clifford F. Gray Eric W. Larson Developing a Project Plan Chapter 6.
1-1 Information Technology Project Management by Jack T. Marchewka Power Point Slides by Richard Erickson, Northern Illinois University Copyright 2003.
Project Management: A Managerial Approach
Project Management: A Managerial Approach
Chapter 8 Scheduling © 2012 John Wiley & Sons Inc.
Project Scheduling Project Management 517 Chapter 8 Prof. M. Anvari
Reid & Sanders, Operations Management © Wiley 2002 Project Management 17 C H A P T E R.
© Wiley 2010 Chapter 16 – PERT, CPM and Critical Chain Operations Management by R. Dan Reid & Nada R. Sanders 4th Edition © Wiley 2010.
Chapter 7 The Project Schedule and Budget Copyright 2012 John Wiley & Sons, Inc. 7-1.
Network Analysis Terminology
Copyright © 2000 John Wiley & Sons, Inc. All rights reserved
Chapter 8 Scheduling © 2012 John Wiley & Sons Inc.
Chapter 16 – Project Management Operations Management by R. Dan Reid & Nada R. Sanders 2nd Edition © Wiley 2005 PowerPoint Presentation by R.B. Clough.
MEM 612 Project Management Chapter 6 Allocating Resources to the Project.
INDE 6332 ENGINEERING PROJECT MANAGEMENT SCHEDULING LECTURE 1 University of Houston Dept. of Industrial Engineering Houston, TX (713)
Project Management in Practice
MEM 612 Project Management Chapter 5 Scheduling the Project.
Prepared by Scott M. Shafer, Updated by William E. Matthews and Thomas G. Roberts, William Patterson University Copyright 2007 John Wiley & Sons, Inc.5-1.
© 2006 John Wiley and Sons, Inc. Project Management: A Managerial Approach Chapter 8 – Scheduling.
CHAPTER :5 SCHEDULING. Things to Learn – Precedence analysis – Gantt Charts – PERT / CPA.
Project Management Planning and Scheduling. “Failing to plan is planning to fail” by J. Hinze, Construction Planning and Scheduling Planning: “what” is.
Beni Asllani University of Tennessee at Chattanooga
PROJECT MANAGEMENT.
Chapter 17 Project Management McGraw-Hill/Irwin
Project Planning & Scheduling
Project Scheduling
The Project Schedule and Budget
deterministic Fixed and known in advance, representing a
& Urban Planning Civil Engineering Department
The Project Schedule and Budget
forward scheduling or backward scheduling
Impacts on Individuals, Organizations & Society
Prepared by Debby Bloom-Hill CMA, CFM
Project Management for Business
Project Management and scheduling
Evaluating and Terminating the Project
Information Technology Project Management
CHAPTER 6 PROJECT TIME MANAGEMENT
liquidation of a partnership.
Transportation and Transshipment Models
PLANNING ENGINEERING AND PROJECT MANAGEMENT
The Production Process
Information Technology Project Management
Project Management CPM/PERT Professor Ahmadi.
Copyright © 2000 John Wiley & Sons, Inc. All rights reserved
AOA A style of project network diagram in which arrows
Importance of Project Schedules
CHAPTER 6 PROJECT TIME MANAGEMENT
Scheduling.
Presentation transcript:

Project Management: A Managerial Approach Chapter 8 – Scheduling © 2006 John Wiley and Sons, Inc.

© 2006 John Wiley and Sons, Inc. Overview WBS to Schedule Process PERT Schedule Types CPM © 2006 John Wiley and Sons, Inc.

© 2006 John Wiley and Sons, Inc. Scheduling A schedule is the conversion of a project action plan into an operating timetable It serves as the basis for monitoring and controlling project activity Taken together with the plan and budget, it is probably the major tool for the management of projects © 2006 John Wiley and Sons, Inc. Chapter 8-1

Simple Schedule – Gantt Chart © 2006 John Wiley and Sons, Inc.

Network Techniques: PERT and CPM With the exception of Gantt charts, the most common approach to scheduling is the use of network techniques such as PERT and CPM The Program Evaluation and Review Technique (PERT) was developed by the U.S. Navy in 1958 The Critical Path Method (CPM) was developed by DuPont, Inc during the same time period © 2006 John Wiley and Sons, Inc. Chapter 8-7

Scheduling Terminology Activity - A specific task or set of tasks that are required by the project, use up resources, and take time to complete Event - The result of completing one or more activities. An identifiable end state occurring at a particular time. Events use no resources. Network - The combination of all activities and events define the project and the activity precedence relationships © 2006 John Wiley and Sons, Inc. Chapter 8-9

Scheduling Terminology Path - The series of connected activities (or intermediate events) between any two events in a network Critical - Activities, events, or paths which, if delayed, will delay the completion of the project. A project’s critical path is understood to mean that sequence of critical activities that connect the project’s start event to its finish event © 2006 John Wiley and Sons, Inc. Chapter 8-10

Scheduling Terminology An activity can be in any of these conditions: It may have a successor(s) but no predecessor(s) - starts a network It may have a predecessor(s) but no successor(s) - ends a network It may have both predecessor(s) and successor(s) - in the middle of a network Interconnections from horizontal links in vertical WBS © 2006 John Wiley and Sons, Inc.

© 2006 John Wiley and Sons, Inc. Hypothetical Network 2 5 6 1 4 3 16 20 13 30 TE=64 Calculate t(e) and Z for this network…… © 2006 John Wiley and Sons, Inc.

Activity and Project Frequency Distributions m b TE (A) (B) © 2006 John Wiley and Sons, Inc.

PERT Activity Calculation t(e) = a + 4m + b a = Most Optimistic (MO) 6 m = Most Likely (ML) b = Most Pessimistic (MP) t(e) = Activity Duration When a single estimate for activity time is not sufficient! © 2006 John Wiley and Sons, Inc.

PERT Schedule Probability Z = T(S) – T(E) Z = Probability of SSD(T[E])2 Meeting Schedule T(S) = Scheduled Duration T(E) = Critical Path Duration Z is derived from a table of predetermined probabilities © 2006 John Wiley and Sons, Inc.

PERT Activity Times & Variances b t(e) 1-2 17 29 47 2-3 6 12 24 2-4 16 19 28 3-5 13 4-5 2 5 14 5-6 8 © 2006 John Wiley and Sons, Inc.

Variance of Activity Estimates b t(e) [(b-a)/6]2 Var 1-2 17 29 47 30 2-3 6 12 24 13 2-4 16 19 28 20 3-5 4-5 2 5 14 5-6 8 © 2006 John Wiley and Sons, Inc.

Possible Project Durations TE=64 TS=67 © 2006 John Wiley and Sons, Inc.

© 2006 John Wiley and Sons, Inc. Z Table Z Value Probability -2.0 0.02 +2.0 0.98 -1.5 0.07 +1.5 0.93 -1.0 0.16 +1.0 0.84 -0.7 0.24 +0.7 0.76 -0.5 0.31 +0.5 0.69 -0.3 0.38 +0.3 0.62 -0.1 0.36 +0.1 0.54 © 2006 John Wiley and Sons, Inc.

© 2006 John Wiley and Sons, Inc. Gantt Charts The Gantt chart shows planned and actual progress for a number of tasks displayed against a horizontal time scale It is an effective and easy-to-read method of indicating the actual current status for each set of tasks compared to the planned progress for each item of the set It can be helpful in expediting, sequencing, and reallocating resources among tasks Gantt charts usually do not show technical dependencies © 2006 John Wiley and Sons, Inc. Chapter 8-14

© 2006 John Wiley and Sons, Inc. Drawing Networks Activity-on-Arrow (AOA) networks use arrows to represent activities while nodes stand for events Activity-on-Node (AON) networks use nodes to represent activities with arrows to show precedence relationships The choice between AOA and AON representation is largely a matter of personal preference © 2006 John Wiley and Sons, Inc. Chapter 8-12

© 2006 John Wiley and Sons, Inc. Hypothetical Network 3 1 2 5 6 4 © 2006 John Wiley and Sons, Inc.

AOA Network Building Blocks 80 79 Install software Event Activity © 2006 John Wiley and Sons, Inc.

Partial Koll Business Center - AOA 4 5 1 3 2 A Application approval D Service availability check C Traffic study B Construction plans © 2006 John Wiley and Sons, Inc.

© 2006 John Wiley and Sons, Inc. Partial AOA Network 2 3 1 4 A X C B E (A) (B) (C) © 2006 John Wiley and Sons, Inc.

© 2006 John Wiley and Sons, Inc. Partial AOA Network 2 3 1 4 A B C X E (D) 5 D 2 3 1 4 A B C X E (E) 5 D F ? © 2006 John Wiley and Sons, Inc.

KOLL BUSINESS CENTER County Engineers Design Department Full AOA Network 2 3 1 4 A 5 B C 10 X 5 15 6 7 8 Y F 10 G 170 H 35 E 15 D 5 Legend KOLL BUSINESS CENTER County Engineers Design Department Activity Duration © 2006 John Wiley and Sons, Inc.

Activity-on-Node Network Fundamentals X Y Z Y and Z are preceded by X Y and Z can begin at the same time, if you wish (B) A B C A is preceded by nothing B is preceded by A C is preceded by B (A) J K L M J, K, & L can all begin at the same time, if you wish (they need not occur simultaneously) All (J, K, L) must be completed before M can begin but AA (C) (D) Z is preceded by X and Y AA is preceded by X and Y © 2006 John Wiley and Sons, Inc.

© 2006 John Wiley and Sons, Inc. Copyright 2006 John Wiley & Sons, Inc. All rights reserved. Reproduction or translation of this work beyond that permitted in section 117 of the 1976 United States Copyright Act without express permission of the copyright owner is unlawful. Request for further information should be addressed to the Permissions Department, John Wiley & Sons, Inc. The Publisher assumes no responsibility for errors, omissions, or damages caused by the use of these programs or from the use of the information herein. © 2006 John Wiley and Sons, Inc.