Earned Value Measures Planned Value (PV) Earned Value (EV)

Slides:



Advertisements
Similar presentations
Connoizor Enabling Performance for Businesses through Software Website: Contact:
Advertisements

Presenter: Sohel Akhter, PMP, CCNA,ISMS
Budget Management. 57 Budget Management Budget Development Good scheduling skills and abilities Understanding of the project scope Well developed WBS.
 Costs are planned, measured, analyzed and controlled in terms of project activities.  Expenditure for any activity is incurred evenly over the duration.
Formula Memorization Trick CV=EV-AC SV=EV-PV CPI=EV/AC SPI=EV/PV EAC=BAC/CPI ETC=EAC-AC VAC=BAC-EAC When memorizing the formulas I have found it best to.
CSSE Oct.2008 Monitoring and reporting project status Chapter 10, pages
Microsoft Project 2002 Sessions 5-6. Entering Tasks During this first session we will enter a set of tasks that comprise building a shed – data sheet.
Chapter 10: Monitoring and Controlling Change
Project Monitoring and Control. Introduction Goal: ensuring that the project is on time and on budget and/or highlight any deviation from the plan Areas.
Project Management 6e..
EARNED VALUE MANAGEMENT SYSTEM A Project Performance Tool
Earned Value Analysis by John Cornman. Introduction “Earned Value Analysis” is an industry standard way to measure a project’s progress, forecast its.
Project Management Methodology Project monitoring and control.
1 ev14a Interactive Session 4 u Tuesday, July 17 7pm to 10pm u Build a sqa plan for the dental office software u Assume a 3-person, development team, a.
Understanding Earned Value Analysis
1. Earned Value Analysis (EVA) Earned value is a measure of progress enables us to assess the “percent of completeness” of a project using quantitative.
© SYBEX Inc All Rights Reserved. Session 10 Project Control.
Conducted By: Dr. Madhu Fernando, PMP, DBA, MEng. MGT PROJECT MANAGEMENT LESSON 5 AND 6: PROJECT PLANNING – TIME AND COST PLANNING AND MANAGEMENT.
9-1 Project Management from Simple to Complex. 9-2 This work is licensed under the Creative Commons Attribution-Noncommercial-Share Alike 3.0 Unported.
EARNED VALUE MANAGEMENT (EVM)
10/19/ :26 AM 1 Project Cost Control. 10/19/ :26 AM 2  Controlling involves making sure that the results achieved are in line with the planned.
Earned Value SOS section Sp8Jan24ev3. Earned Value Analysis One approach to measuring progress in a software project is to calculate how much.
Project Management Part 6 Project Control. Part 6 - Project Control2 Topic Outline: Project Control Project control steps Measuring and monitoring system.
1 Project Management – Unit 4 – Part 1 Cost Model ACWP: Actual cost of work performed: Actual costs in performing the work so far. BCWP: Budgeted cost.
Presented by Tim Pyron Author: Que’s Special Edition Using Microsoft Project 2002 Que’s Special Edition Using Microsoft Project 2000 SAMS Teach Yourself.
Introduction To Earned Value November 14, Definition Earned Value is a method for measuring project performance. It compares the amount of work.
Earned Value Analysis Tracking Project Progress. Introduction | Components | Project Scenario | Values | Calculations | Forecasts | Summary l What Is.
1 Earned value analysis Planned value (PV) or Budgeted cost of work scheduled (BCWS) – original estimate of the effort/cost to complete a task (compare.
PMP Study Guide Chapter 11: Controlling Work Results.
EARNED VALUE MANAGEMENT & ORACLE PRIMAVERA P6 TREY MILLER, MBA, PMP ORACLE PRIMAVERA P6 EPPM CERTIFIED IMPLEMENTATION SPECIALIST GLOBAL PROJECT MANAGEMENT,
EVM – Do You Really Know What the Numbers Mean? Booz | Allen |Hamilton Seth Huckabee EVP, PMP, PMI-SP.
1 Understanding Earned Value in Under an Hour Breakout Session # A11 Name: Wayne Brantley, MS Ed, PMP, ITIL Senior Director of Professional Education.
Schedule Control (Earned Value)
Project Cost Con trol. 1.To identify those work types having excessive costs and to give an indication of how serious those overruns are. 2.To forecast.
Agenda ‒ Cost Management ‒ Cost Budgeting ‒ Cost Control Learning Goals 1.Cost Control 2.Earned Value Management.
Project Management 1 Project Control. Project Management 2 Topics Project Control Status Reporting Earned Value Analysis.
Earned Value Management
Measuring Progress HNC Project Management. Measuring Schedule Performance Break project tasks up into small work units. Work units that are too large.
Earned Value Management EVM. 03/06/2013 Earned Value Management Planned Value (PV): –Budget of the planned work.
Project Management Earned Value Management Demonstration
Performance Measurement Baseline Contract Price (Project Price)
Earned Value Analysis by Miles M. Hamby, PhD Copyright©2014 Miles M
Project Monitoring
“PMP® Exam Prep” Earned Value Management
TOPIC-8B- PROJECT COST CONTROL
PROJECT MANAGEMENT AND CONTROL
Budget Planning.
CHAPTER:7 Project Cost Management
Earned Value Management
Performance Measurement Baseline Contract Price (Project Price)
5. Cost resources & PLAN DURATION
Earned Value Management
Project Cost Management
Work Packages / Deliverables Completed
Earned Value Management & Oracle Primavera P6
Progress and Performance Measurement and Evaluation
Earned Value - What is it
Earned Value Analysis It is a continuous comparison between the plan of the project data and the actual data. Budgeted and Committed Cost: Variance = Budgeted.
Project Scope Management
An Introduction to Earned Value Performance Measurement
Implementing EV in IT A Three Step Approach John Chapman Touchstone Ltd
PROJECT COST MANAGEMENT
ENGINEERING MANAGEMENT (GE 404)
فرآيند كنترل پروژه.
Earned Value Management
5. Cost resources & PLAN DURATION
Schedule and Cost Variance Problem
5. Project PLAN & cost estimation
Monitoring and Controlling
Earned Value $$$.
Presentation transcript:

Earned Value Measures Planned Value (PV) Earned Value (EV) Baseline cost of work scheduled BCWS Earned Value (EV) Baseline cost of work completed BCWP Actual Value (AC) Actual cost of work completed ACWP

BCWS BCWP ACWP Baseline cost of work scheduled Baseline cost of work performed ACWP Actual cost of work performed

EAC BAC VAC Estimate at Completion Budget at Completion Variance at Completion

SV CV Scheduled Variance BCWP-BCWS How much done vs how much planned SV is positive = Ahead of schedule CV Cost Variance BCWP-ACWP Baseline cost vs Actual cost CV is positive = Under budget

SPI CPI Scheduled Performance Index BCWP/BCWS SPI< 1 = Project behind schedule CPI Cost Performance Index BCWP/ACWP CPI> 1 = Project is under budget

TCPI To Complete Performance Index Ratio of Remaining work vs Remaining budget TCPI> 1 = Over budget TCPI< 1 = Under budget

Earned value > Planned Value = More work done than we planned

Earned value > Actual Cost = Baseline cost higher than actual, we are under budget