Earned Value Analysis It is a continuous comparison between the plan of the project data and the actual data. Budgeted and Committed Cost: Variance = Budgeted.

Slides:



Advertisements
Similar presentations
Connoizor Enabling Performance for Businesses through Software Website: Contact:
Advertisements

©2003 Rolls-Royce plc The information in this document is the property of Rolls-Royce plc and may not be copied or communicated to a third party, or used.
Budget Management. 57 Budget Management Budget Development Good scheduling skills and abilities Understanding of the project scope Well developed WBS.
 Costs are planned, measured, analyzed and controlled in terms of project activities.  Expenditure for any activity is incurred evenly over the duration.
Monitoring and Control Earned Value Management (EVM)
CSSE Oct.2008 Monitoring and reporting project status Chapter 10, pages
Microsoft Project 2002 Sessions 5-6. Entering Tasks During this first session we will enter a set of tasks that comprise building a shed – data sheet.
Chapter 10: Monitoring and Controlling Change
HIT241 - COST MANAGEMENT Introduction
Chapter 10 Project Monitoring and Control
Earned Value Analysis by John Cornman. Introduction “Earned Value Analysis” is an industry standard way to measure a project’s progress, forecast its.
Project Monitoring and Control. Monitoring – collecting, recording, and reporting information concerning project performance that project manger and others.
Project Management Methodology Project monitoring and control.
Controlling cost ( lecture + seminar ). Why control cost? To satisfy financial auditors and support data for the government (obligatory). To satisfy the.
1 ev14a Interactive Session 4 u Tuesday, July 17 7pm to 10pm u Build a sqa plan for the dental office software u Assume a 3-person, development team, a.
1. Earned Value Analysis (EVA) Earned value is a measure of progress enables us to assess the “percent of completeness” of a project using quantitative.
Cost Estimation and Budgeting. Cost management Data collection & cost estimation Cost accounting Cost controll Copyright © 2010 Pearson Education, Inc.
EARNED VALUE MANAGEMENT (EVM)
Controlling cost 2 ( seminar ). Budget preparation Data collection WBS Cost centres Indirect expenses & the use of hammocks –direct –overhead (indirect)
Earned Value Management System (EVMS). Given: –total budget of $100,000 –12 month effort –produce 20 units Status: –spent to date: $64,000 –time elapsed:
10/19/ :26 AM 1 Project Cost Control. 10/19/ :26 AM 2  Controlling involves making sure that the results achieved are in line with the planned.
Earned Value SOS section Sp8Jan24ev3. Earned Value Analysis One approach to measuring progress in a software project is to calculate how much.
1 Project Management – Unit 4 – Part 1 Cost Model ACWP: Actual cost of work performed: Actual costs in performing the work so far. BCWP: Budgeted cost.
EARNED VALUE MANAGEMENT (EVM) TUTORIALS
Ev3 1 In House Software Development:… Verner, etal IEEE Software, Jan?feb 2005.
Introduction To Earned Value November 14, Definition Earned Value is a method for measuring project performance. It compares the amount of work.
Earned Value Analysis Tracking Project Progress. Introduction | Components | Project Scenario | Values | Calculations | Forecasts | Summary l What Is.
Project Management Information System What?? Objective: –Record & report relevant information and status of various components of project –Highlight the.
1 Earned value analysis Planned value (PV) or Budgeted cost of work scheduled (BCWS) – original estimate of the effort/cost to complete a task (compare.
EVM – Do You Really Know What the Numbers Mean? Booz | Allen |Hamilton Seth Huckabee EVP, PMP, PMI-SP.
Schedule Control (Earned Value)
Agenda ‒ Cost Management ‒ Cost Budgeting ‒ Cost Control Learning Goals 1.Cost Control 2.Earned Value Management.
Project Management 1 Project Control. Project Management 2 Topics Project Control Status Reporting Earned Value Analysis.
Earned Value Management
Measuring Progress HNC Project Management. Measuring Schedule Performance Break project tasks up into small work units. Work units that are too large.
Performance Measurement Baseline Contract Price (Project Price)
Earned Value Analysis by Miles M. Hamby, PhD Copyright©2014 Miles M
Project Monitoring
TOPIC-8B- PROJECT COST CONTROL
PROJECT MANAGEMENT AND CONTROL
Budget Planning.
CHAPTER:7 Project Cost Management
Earned Value Management
Chapter 7: Project Cost Management
Project Management Basic Concepts
Project Communication, Tracking, and Reporting
Performance Measurement Baseline Contract Price (Project Price)
5. Cost resources & PLAN DURATION
Earned Value Management
Project Cost Management
Work Packages / Deliverables Completed
Contract Performance Charts
Progress and Performance Measurement and Evaluation
Earned Value - What is it
An Introduction to Earned Value Performance Measurement
Implementing EV in IT A Three Step Approach John Chapman Touchstone Ltd
PROJECT COST MANAGEMENT
Problem solving.
Financial Principles and Project Cost Management
Earned Value Measures Planned Value (PV) Earned Value (EV)
ENGINEERING MANAGEMENT (GE 404)
فرآيند كنترل پروژه.
Controlling cost.
Earned Value Management
5. Cost resources & PLAN DURATION
Schedule and Cost Variance Problem
5. Project PLAN & cost estimation
Project Management Life Cycle
Chapter 27 Project Scheduling
Chapter 7: Project Cost Management
Presentation transcript:

Earned Value Analysis It is a continuous comparison between the plan of the project data and the actual data. Budgeted and Committed Cost: Variance = Budgeted cost – committed cost Variance (+ve ) = Unconsumed Cost Variance ( -ve ) = Over spend activities

Cost and Schedule Variances

Cost and Schedule Variances

BCWS Budgeted Cost of Work Schedule A B C D E F G H I J X1 X2 X3 X4 X5 X6 X7 X8 X9 X10 NOW BCWS = X1 + X2 + X3 + X4 + X5 $ This is the sum of all the costs up to the specific activity that is stated in budget plan.

BCWP Budgeted Cost of Work Performed A B C D E 100% X1 X2 X3 80% X4 50% X5 BCWP = X1 + X2 + X3 + 0.8 X4 + 0.5 X5 $ This is the sum of all the costs up to the specific activity in relation with its completion percentage.

ACWP Actual Cost of Work Performed ACWP = Actual cost of work done. This is the total costs of the work done on reality provided by project manager on the financial monitor.

If BCWP > BCWS ( over spend ) If BCWP < BCWS ( time is late -ve ) If BCWP > BCWS ( +ve time is more than sufficient )

Forecasting Benefits of forecasting: It is the process of prediction of the future events. Benefits of forecasting: To estimate the cost of remaining parts of a project ( forecasted value ). To identify the source and places of certain problems in the budget plan. It is a tool for corrective actions.

Forecasting Mathematical Expressions The Cost Performance Index ( CPI ): CPI = BCWP / ACWP It gives a good indication whether the project is performing financially well or not. CPI > 1 : Good performance. CPI < 1 : Bad performance ( shortages Overspend ).

Forecasting Mathematical Expressions The Schedule Performance Index ( SPI ): SPI = BCWP / BCWS It is a good indicator for the project timing. SPI > 1 : Good performance. SPI < 1 : Bad performance (Poor ).

Forecasting Mathematical Expressions Budgeting Cost to Completion ( BCC ): The Amount of money needed to completion. BCC = BAC – BCWP It is defined as the amount of money required to complete a project where it is partially completed ( remaining money ).

Forecasting Mathematical Expressions Estimated Cost to Completion ( ECC ): Its more realistic value than budgeted. ECC = BCC / CPI It depends on CPI which is a by product of the actual cost of work performed. Forecasted Cost to Completion ( FCC ): FCC = ACWP + ECC

Example The R&D department of a company has been developing a new product line, the project manager is concerned whether the following provided data is exhibiting a good project performance, calculate the following and comment on the project status to convince the project manager. CPI,BCC, ECC, SPI, FCC.

Work Package Budgeted Cost Completion Time month Actual Cost % Complete B49 20000 1 23500 100% B50 2 20500 B51 37000 3 23000 70% B52 27000 4 B53 12000 5 4500 60% B54 28000 6 18500 75% B55 40000 7 ---- 184000

Solution BCWS = 20000 + 20000 + 37000 + 27000 + 12000 + 28000 = 144000 $ ACWP = 23500+20500+23000+27000+4500+18500 = 117000 $ BCWP = 20000 + 20000 + ( 37000 x 0.7 ) + 27000 + ( 12000 x 0.6 ) + ( 28000 x 0.75 ) = 119900 $ CPI = BCWP / ACWP = 119900 / 117000 = 1.02 good performance.

BAC = Budget at Completion = 184000 BCC = BAC – BCWP = 184000 – 119900 = 64100$ ECC = BCC / CPI = 64100/1.02 = 62843.14 $ SPI = BCWP / BCWS = 119900 / 144000 = 0.832 < 1 Poor performance according to time. FCC = ACWP + ECC = 117000 + 62843.14 = 179843.14 $

Comments We do not have any financial problem i.e the budgeted cost (money resources) is larger than the forecasted values, we conclude that the money is available , it is more than sufficient as the indicators were positive, the only problem we have is the time.

Comparing Projects Project SPI CPI A 0.78 (2) 0.68 (2) B 0.96 (1) 0.78 (2) 0.68 (2) B 0.96 (1) 0.98 (1) C 0.46 (3) 0.51 (4) D 0.46 (4) 0.64 (3)

Problem : Compare between the following projects according to the time and cost consumed: Project A Project B WP budget actual %comp A 435 395 100% B 320 409 90% C 125 - d 570 WP budget actual %comp A 820 800 100% B 750 920 90% C 1000 730 65% D E 700 850 -- ---