Ladder Assembly All tools and jigs produced Glue dispensing works

Slides:



Advertisements
Similar presentations
GATHER THE FOLLOWING SUPPLIES:
Advertisements

A Low Mass On-chip Readout Scheme for Double-sided Silicon Strip Detectors 13th February 2013 C. Irmler, T. Bergauer, A. Frankenberger, M. Friedl, I. Gfall,
Stave Vacuum Tool Tim WP4 Face to Face Liverpool, 13/11/14.
1 Short update Itzhak Tserruya HBD meeting BNL, April 11, 2006.
Prepared by: Barry Sparrow and Sal Ienco Civil/Construction Sault College.
Hybrid assembly at Glasgow. Placing ASICs Arrange 20 ASICs in ASIC tray with strip bond pads facing outwards – ASICs to be used in ‘Cat A’ sample boxes.
Assembly Procedure ALICE Outer Barrel Stave 14 Module 2 Cold Plates 1 Stave.
1 © 2011 Profile Recorder for ProtoFlow S Installation Instruction.
V. Carassiti - Princeton (USA) 9-13/01/ BABAR IFR UPGRADE DETECTOR ASSEMBLING AND MOUNTING.
AMS-02 tracker mechanics status of assembly and integration at UniGe Outer planes: - Tests of evaporator (cooling loop) integration - Tools to develop.
AMS-02 tracker mechanics status of assembly and integration Inner tracker integration completion: - Assembly and cabling - Temperature and magnetic field.
Stator Plan & Schedule Chris Booth 2 nd March stators to construct for mid-April. One complete coil assembly recovered from ISIS drive. Coils recoverable.
The AMS-02 detector is based on a large acceptance (~0.5 m²sr) and high sensitivity spectrometer composed by a super-conducting magnet (0.8 T), cooled.
MM mechanical prototype Work progress at CERN MicroMegas General Meeting, CERN, 5-6 November
Mantle Clock. Beginning Steps Cut 2 piece 20 x 5 to make the 2 sides and top/bottom Cut 1 10 ¾ and 1- 9 from each 20 piece. This will make a side and.
IBL Mock Up IBL Mock Up MANUFACTURING 2011/04/29 François-Xavier NUIRY Maxence CURDY Andrea CATINACCIO CERN PH/DT/PO 1.
SVD Mechanics 21th B2GM Florian Buchsteiner (HEPHY Vienna)
Hybrid Integrated Circuit
Slide 1Susanne KyreTracker week, October 2005 TEC/TOB bias bonds Susanne Kyre University of California, Santa Barbara.
Update on Alignment kit and Stave 250 frame and thoughts for Stave 130 M.Gibson (RAL) 2/5/13 1 Status of the frame for stave 250 Status of infrastructure.
Marc Anduze – 09/09/2008 Report on EUDET Mechanics - Global Design and composite structures: Marc Anduze - Integration Slab and thermal measurements: Aboud.
Silicon Meeting July 10, 2003 Module and Stave Production Status James Fast Fermilab.
M. Gilchriese Module Assembly and Attachment at LBNL M. Gilchriese for F. Goozen April 2000.
Silicon /pcb assembly R Thompson, J Freestone LAL 3 June 08.
16/04/20031PNPI / LHCb Muon EDR Wire Pad Chambers PNPI design for regions R4 in Stations M2,M3,M4  4 gas gaps of 5mm±70µm;  Active area: 1224x252.8 mm².
Assembly Procedure ALICE Outer Barrel Stave 14 Module 2 Cold Plates 1 StaveMarco Kraan Paul Kuijer.
Strip Stave cores Stephanie Yang ATLAS upgrade Oxford activities, January 2015.
Thermo-mechanical petal status Sergio Díez Cornell 23Jan 2015.
Hybrid Mechanical/Thermal Design Ray Thompson / Manchester FP420 meeting Torino 11/12 July 06.
SVD Mechanics Markus Friedl (HEPHY Vienna) BPAC, 26 October 2015.
MFT WG5: ladder disk and global assembly Stéphane BOUVIER & Sébastian HERLANT MFT WG7: Mechanics and Thermal studies Jean-Michel BUHOUR & Emili SCHIBLER.
Focusing Lighting Instruments THE107. Focusing Lights This presentation will walk you through the basic steps of focusing a theatrical lighting instrument.
David Bailey Gluing. Silicon /pcb assembly Previously Using Sony Robot and precision dispenser Have established acceptable glue dot parameters Dot electrical.
Stave C channel side closeout gluing jig S Yang WP4 monthly meeting at Liverpool University 26 th March 2014.
Strasbourg status Ring 7 pilot run François Didierjean.
Gluing, measuring and shearing Heated plate curing Is the process feasible? Tests with 130nm hybrids Measure resulting glue thickness Determine the shear.
ATHENA - Module Construction P. Riedler, J. Rochet.
A.Cheremukhin (JINR, Dubna) CMS Preshower PRR, July 5-6, 2001, CERN1 Micro-module assembly -  -module elements - alignment of the silicon sensors to the.
Stave #12 This stave core was built together with William Emmet, Tom Hurteau, and Jeffery Ashenfelter from Yale University in the week of November.
Hybrid and Module Status 1. Hybrid Delivery First hybrids over-etched and shrunk due to changes in design and mistakes in manufacturing – Shrinkage for.
375, 375XL 1¼” -2”. Modification Overview  Production of the 1¼” -2” 375 began in 2004 and is current.  The lead free version 375XL was introduced in.
DOE CD-2/3a Review of the BTeV Project – December 14-16, BTeV Pixel Detector Pixel Module Assembly and Half-Plane Assembly Guilherme Cardoso James.
News on Mechanical Design Dirk Wiedner July /4/20121Dirk Wiedner Mu3e meeting Zurich.
Rapid Change Technology The following is a presentation to aid Technicians in the replacement of the Rapid Change Technology Block.
25th April 2013 C. Irmler (HEPHY), Y. Onuki (IPMU) Ladder Assembly Procedure Belle II – New Collaborators Meeting.
Sentek Technologies Joining EnviroSCAN Probes. Probe Components 20-way probe cable connector (special order) Cable spacer (Part No 80015) Probe rods Probe.
B2GM, Nov 2014 Laci Andricek, MPG Halbleiterlabor 1 PXD Ladder Assembly - Conceptual design of jigs -
Thoughts about PS module assembly Ulrich Heintz, Meenakshi Narain, Bill Patterson, Eric Spencer, Juan Trenado Brown University, Providence 4/16/2015Heintz,
Mechanical robustness & associated tension at the DSSD slant part connection Mar-5 th 2013 B2GM KEK S. Uozumi (KNU), T. Tsuboyama, N. Sato (KEK)
Marc Anduze – EUDET Meeting – PARIS 08/10/07 Mechanical R&D for EUDET module.
INSTALLATION MANUAL FATL Machine Installing: ACTIVITY CHECK POINT 1. Minimum two persons required for opening the Machine. 2. Cut the straps & tape. 3.
BM&N STS ladders assembly in VLHEP
Stator Plan & Schedule Chris Booth 2nd March 2009
RE 4/3 RPC Pre-assembly manual 1. HCP case preparation
SVD Electronics Constraints
ATLAS pixel module assembly flow
Update on Pavia MM mechanical prototype
Ladder Assembly All tools and jigs produced Glue dispensing works
Gluing jigs for Demonstrator
Open Issues Modification of Cactus Arm bending tool required
TIDVG-4 TIDVG-4 Dump assembly, welding and installation Process sector BA1 February 2017 J. Humbert, (EN/MME) 06/02/2017 J. Humbert, EN-MME.
Studies of Quad Pixel Module assembly using paper laminate
Step-by-step assembly instructions
Louisiana Tech University
Decide which length you plan to use on the Bandaid. Then check to be sure your bandaids are all the same length. These small Band aids have 2.
Module/Ladder Assembly
Module Production in Brussels
Module Production in Brussels
Making a simple steady hand game
Possible types of Si-sensor: SILICON CALORIMETRY FOR A LINEAR COLLIDER G.Bashindzhagyan, Il Park August Silicon sensor.
Presentation transcript:

Ladder Assembly All tools and jigs produced Glue dispensing works Pull tests ok 9 dummy ladders assembled

Transfer on vacuum jig Modules arrive with kapton attached (tested) Vacuum jig for turning and ladder gluing Fits on top side (cut outs for switcher) Mode from microporous plate (gentle vacuum on sensor top side) Vacuum jig on sensor Screw kapton jig to vacuum jig Unscrew kapton jig from base jig

Accident Made 18 transfers without problems….. Demonstration to tech, coordinator: module cracked! Reason: due to stiffness and misalignment of the dummy kapton modules lifted upwards from base jig When the vacuum jig was lowered it did not push the module back, but broke it Real kapton much softer and better aligned: this situation should not occure Anyway: check and counteract if this happnes nevertheless Base Jig Vacuum Jig

Remove base jig Turn around and take off base jig

Prepare for glue dispensing Add protective cover to be sure: module is securely held by Vacuum…

Mount on glue dispenser 2nd module is prepared the same way Glue is automatically dispensed on both modules in one step

Place modules on alignment jig bwd module 1st fwd module 2nd

Align and glue together Precision achieved: 10 µm over full length of ladder Modules are pushed together to 30µm to ensure good contact and distribution of the glue. Then they are driven apart to the nominal gap of 50µm

Add ceramic stiffeners Stiffeners are handled with a vacuum tool Glue is applied with a needle (works better than with a dispenser)

48h later…. For curing the ladder is covered and put apart After curing ladder base jig is added

Remove vacuum jigs Fix kapton jigs to ladder base jig Unscrew vacuum jig Remove ladder and turn over

Protect and store Add cover for sensors Put in transport/storage box

Gluing Tests Line dispensing dots Musashi dispensor Araldite 2011 200 Pa 5 mm/s (line) Needle: 0.2 mm Best results: Line, broken at v-grooves for stiffeners First tests with manual alignment (no control of gap) Some (very marginal) spill over (~100 µm width) Second test series: no spill over

Pull Tests Strip pattern: breaks at > 3 kg Dot pattern weaker (~2 kg) 3 kg is considered sufficient (silicon breaks at ~3 kg) Confirmed by pull test of 1st glued dummy ladder => 3.9 kg =>

Protocol Glue gap Delta z Delta x Delta h

Statistics Delta h Glue gap Ok after additional clamp All in µm

Summary Module/Ladder assembly procedure defined. Tooling is designed and produced. All jigs are produced (for 80 modules & 40 ladders). Gluing with automatic dispenser tested. Pull strength ok. 9 dummy ladders assembled plain thinned silicon, plastic ‘kapton’ thinned silicon with copper, real kapton Including ASIC dummies Available: 5 outer ladders, 1 inner ladder Assemble more realistic dummy ladders W31OF1, W30 OF1, xxxxxx (partial) electronic test possible