The Central Avenue Connector Trail

Slides:



Advertisements
Similar presentations
January 23, 2006 FAIRFAX COUNTY PEDESTRIAN TASK FORCE FAIRFAX COUNTY PEDESTRIAN TASK FORCE FINAL REPORT.
Advertisements

From – A Report of the Connecticut Regional Institute for the 21 st Century by Michael Gallis & Associates, 1999 (known as the “Gallis Report”) Knowledge.
South Side Red River Bridge Corridor Study Phase III Preliminary Geotechnical Study Phase IV New Alignment Alternatives Evaluation.
Spokane Transportation Planning Partnerships August 23, 2013.
Transportation Alternatives Program FY 2015 Proposed Projects for Funding in Northern Virginia Transportation Planning Board May 21, 2014 Sarah Crawford.
STATE ROAD 100 CORRIDOR COMMUNITY REDEVELOPMENT AGENCY Bulldog Drive Improvements Right-of-Way and Design September 21, 2010 Presentation for SR 100 CRA.
Feasibility Study FOREST GLEN PASSAGEWAY April 10, Isiah Leggett Montgomery County Executive Arthur Holmes, Jr. Director Department of Transportation.
County Wide Active Transportation Study (CWATS) Master Plan Active Communities Summit – October 3, 2011.
County of Fairfax, Virginia Department of Transportation Update on Transportation Activities in Fairfax County Transportation Roundtable Dulles Area Transportation.
Schools Jobs Revenues Services Recreation Environment Transportation Transportation Connectivity Housing Public Safety Pontiac’s.
Multimodal Corridor Plan BCC Discussion Item Transportation Planning Division August 19, 2014.
1 Matadero Creek Trail Midtown Resident Association April 16, 2013.
US 1 COLLEGE PARK – SEGMENT 1 FROM COLLEGE AVE/REGENTS DRIVE TO MD 193 (UNIVERSITY BLVD) Presentation to College Park City Council August 5,
Barrington Road at Jane Addams Memorial Tollway (Interstate 90) Interchange Improvement Study Hoffman Estates Village Hall June 27, 2012.
Project Briefing Metropolitan Washington Council of Governments Transportation Policy Board Project Briefing Metropolitan Washington Council of Governments.
FY 2011 TPB TIGER Grant Application TPB Technical Committee Eric Randall September 9, 2011.
From Planning to Pouring: The Evolution of Safe Routes to School Julie Walcoff, Ohio DOT, Columbus, OH Alex Smith, Columbus Public Health, Columbus, OH.
1 Item 11: Review of Draft Bicycle and Pedestrian Plan for the National Capital Region Michael Farrell TPB Staff Presentation to the Transportation Planning.
Capital Improvement Program. During the Annual Strategic Action Plan (SAP) evaluation, long-term needs and priorities are identified by City Council Capital.
National Capital Region Climate Change Report OVERVIEW Joan Rohlfs, Chief, Air Quality Planning Metropolitan Washington Council of Governments October.
Metrobus 30s Line Study Improving Your Customer’s Transit Experience Virginia Transit Association May 20,
Council Policy Forum Feb. 23, 2015 CAPITAL PLANNING & INFRASTRUCTURE.
Board of County Commissioners September 25, 2012.
1 Item 12: Report on Draft Bicycle and Pedestrian Plan for the National Capital Region Michael Farrell TPB Staff Presentation to the Transportation Planning.
Tom Norton, Executive Director Colorado Department of Transportation American Association of State Highway and Transportation Officials September 9, 2003.
Advancing bicycling through unified state and local advocacy organizations Thunderhead Alliance 50 States/50 Cities Project Complete Streets Pro Walk/Pro.
County of Fairfax, Virginia Department of Transportation VDRPT Route 1 Multimodal Alternatives Analysis: Recommendations for Next Steps Board Transportation.
August 19, 2015 Port Bienville Rail EIS Scoping Meeting Presented by: Rhea Vincent Mike McGuire.
South/West Corridor Transit Improvements ZARZAMORA AND MILITARY PRIMO BRT PROJECTS ENVIRONMENTAL AND PRELIMINARY DESIGN PHASE September 9, 2014 VIA Community.
City of Belmont Comprehensive Bicycle and Pedestrian Plan Parks and Recreation Commission Meeting 11/4/2015.
Public Input Meeting April 16, Meeting Schedule Housekeeping Meeting Schedule – Open House – 6:00-6:30 pm – Presentation – 6:30-7:00 pm – Q&A –
Mobility for all Modes Update to the Transportation Chapter of the City’s Comprehensive Plan City Council May 27,
Transportation Master Plan Update Warden’s Forum May 7, 2015.
County of Fairfax, Virginia Department of Transportation Update on Transportation Activities in Fairfax County Transportation Roundtable Dulles Area Transportation.
Complete Streets Training Module 4b – Designing for All Users.
County Road 19(Manning Road) & County Road 22 Improvements Environmental Study/ Preliminary Design Report November 2008.
Arizona Forward Update
Urban Street Design Standards Overview of Project and Details
Transportation Improvement Plan (TIP) Project Solicitation
Potomac Yard Metrorail Station
Connecting the City: Building the Dallas Trail Network
Finance Committee & City Council October 10, 2016
Four Winds Condominium Association August 2, 2017
City Council Meeting November 7, 2016
Downtown Valdosta Truck Traffic Mitigation Study
Regional Roads Committee
Complete Streets Award Program
Plan Goals: Improve walkability and pedestrian safety Preserve and celebrate neighborhood character and sense of place Address code violations Improve.
Capital Metro Downtown Station Improvements
Cycling infrastructure spending 2017
Mobility Choice Blueprint
The Oakton Condominium Association September 12, 2017
FY 2012 Status Report on the North Mainland (Ormond Crossings CRA)
Draft Transportation Element September 6, 2017
I-66 Outside the Beltway Design Public Hearing Meetings November 13, 14 & Susan Shaw, P.E., Megaprojects Director Virginia Department of.
Loddon Campaspe Integrated Transport Strategy
FHWA Bicycle and Pedestrian Program
San Mateo Countywide Transportation Plan update
Transportation Alternatives (TA) Set-aside
Update on Route 1 Efforts Transportation Advisory Committee October 20, 2015 Leonard Wolfenstein, FCDOT Jane Rosenbaum, FCDOT Doug Miller, FCDOT Department.
Florida Transportation Commission FY 2009
City of Wilmington Bike Plan Update
Loddon Campaspe Integrated Transport Strategy
Endorsement of the Recommended Design Concept (Preferred Alternative) for Transforming I-66 Outside the Beltway Board Transportation Committee October.
Hillsborough County Initiatives to Address School Safety
Status Report on Rochester’s DMC Transportation Plan
Meadow Lake Boulevard Street Extension Project
URBAN TRAIL PROJECT UPDATES
Magnolia Grove Civic Club
What follows after approval of Active Transportation
Presentation transcript:

The Central Avenue Connector Trail Project Briefing For: The Central Avenue Connector Trail Prince George’s County Planning Board June 9, 2016 Agenda Item: 3C THE MARYLAND-NATIONAL CAPITAL PARK AND PLANNING COMMISSION PRINCE GEORGE’S COUNTY PLANNING DEPARTMENT

Project Background Project designed to complement the ongoing planning and revitalization efforts in the Central Avenue-Metro Blue Line Corridor. The Central Avenue Connector Trail (CACT) is an outgrowth of multiple planning and implementation efforts led by the Prince George’s County Planning Department. The CACT was one of the top implementation priorities identified in the Central Avenue-Metro Blue Line Corridor TOD Implementation Project Mobility Study completed in 2014. In 2014, the Metropolitan Washington Council of Governments (MWCOG) provided funding to the Planning Department to develop the Central Avenue Connector Trail Feasibility Study and Implementation Plan to determine how to move the project forward.

Project Background The Central Avenue Connector Trail Feasibility Study and Implementation Plan was completed in the Spring of 2016. Engaged community and key stakeholders to establish preferred trail alignment and key recommendations. Outlined design considerations and identified next steps. Provided necessary implementation analysis to leverage grant funding. Recently awarded two grants for preliminary engineering (30% design). Transportation/Land Use Connections (TLC) Program (MWCOG) - $80,000 Maryland Bikeways Program (Maryland Department of Transportation) - $362,000 Maryland Department of Transportation

Project Considerations The CACT is envisioned as a multi-use facility that provides safe and comfortable connections to the four Metrorail stations, neighborhoods, employment locations, shopping and entertainment venues, and to existing or planned trails. The trail will help to improve the overall public well-being and economy of the Central Avenue-Metro Blue Line Corridor while promoting active lifestyles within it. This project will leverage existing infrastructure and available Right-Of-Way to significantly upgrade available pedestrian facilities on and near Central Avenue. Trail designed to take advantage of publicly owned land and WMATA owned land to minimize conflict with individual property owners. Safety and access have been identified by the community as the key drivers for this project’s success and necessity.

Community Engagement Community and Stakeholder engagement has been an essential element in the overall planning process. In addition to two large community meetings, the CACT Project Team held two stakeholder meetings with representatives from key State and County agencies. Additional meetings with individual property owners, WMATA, MDSHA, DDOT, DPW&T, DPR, elected officials and municipalities were held. Through the process of community and stakeholder engagement significant contributions to the trail were achieved. Residents expressed concerns relating to safety and recommendations for design and programming. Coordination with WMATA resulted in a complete change in strategy which saw the trail alignment shift from a more circuitous route utilizing local streets and off-road trails to a more direct route which takes advantage of WMATA land connecting the four metro stations along the existing metrorail alignment.

Trail Alignment

Trail Design Portions of the CACT will follow the existing WMATA R-O-W and function as a park trail, while other segments will parallel roadways and function as a shared use sidepath, cycle track, or designated bike lanes. Trail programming will include signage, interpretive elements, trail furniture, fitness stations, and safety features such as lighting, call boxes and ADA accommodations. The following four facility types are used along the corridor: 12’ multi-use trail with 2’ buffer on each side 10-12’ sidewalk with buffer where possible 6’ sidewalks with parallel, on-street bicycle facilities (shared lane markings, wide bike lanes or bike lanes) 12’ to 16’ multiuse trail bridge, used where needed to bridge stream valleys and wetlands. 12’ boardwalks with railings may also be used in or near these areas

Connections

Case Study: Potomac Yard Park Trail

Implementation Phases

Ongoing Work: Phase I Design Draft 30% design plans have been completed for Phase 1 near the Addison Road Metro. Phase 1 runs from Addison Plaza to Peppermill Road (below). Community and agency stakeholder meetings will be used to get feedback and further refine the plans.

Ongoing Work: Phase II Design Funding from the Maryland Bikeways Program is being utilized to initiate Phase II Design. Phase II includes the Capitol Heights “trail loop” on the western end of the overall alignment and includes the segment from Peppermill Road to Brightseat Road. Design will also include the short-term (alternative) beltway crossing of Brightseat Rd. to Arena Drive. Project proposals have been received and reviewed by the project team and procurement staff, with project scheduled to commence in July, 2016.

Status of Current Work Feasibility Study and Implementation Plan completed in the Spring of 2016. Phase 1 of the CACT 30% design work is underway. Draft plans have been completed. Future stakeholder and community meetings have been scheduled. The RFP for 30% design work is out for Phase II (Implementation Phases 2-5). Selection of the consultant and contracts will be finalized by June 30, 2016. With support from the County Executive, County Council, county agencies, and local and regional advocacy groups, a Transportation Alternatives Program (TAP) Application was submitted in May, 2016 for the 30% design of a pedestrian bridge to cross over I- 495/Capital Beltway (Phase III). An informational brochure for the Connector Trail has been completed. The CACT Project has been included as a trail priority in the 2016 Joint Signature Letter. Money has been placed in the CIP (FY2018) for the Central Avenue Connector Trail to be used as a match for future grant applications for design and construction.

Next Steps Complete the 30% design work; Continue extensive community outreach and engagement; Resolve maintenance and operational responsibilities; Once the 30% design plans are complete, apply for funding for construction; Evaluate opportunities for spinoff economic and community development activities in and around the project area.

Questions?