Earned Value Management

Slides:



Advertisements
Similar presentations
Connoizor Enabling Performance for Businesses through Software Website: Contact:
Advertisements

Presenter: Sohel Akhter, PMP, CCNA,ISMS
Budget Management. 57 Budget Management Budget Development Good scheduling skills and abilities Understanding of the project scope Well developed WBS.
 Costs are planned, measured, analyzed and controlled in terms of project activities.  Expenditure for any activity is incurred evenly over the duration.
Monitoring and Control Earned Value Management (EVM)
CSSE Oct.2008 Monitoring and reporting project status Chapter 10, pages
Chapter 10: Monitoring and Controlling Change
Monitoring and Controlling
Earned Value Project Management: a powerful tool for software projects
Project Monitoring and Control. Introduction Goal: ensuring that the project is on time and on budget and/or highlight any deviation from the plan Areas.
Project Management Process Project Description Team Mission/ Assignment Major Milestones Boundaries Team Identification Measures of Success Roles & Responsibilities.
EARNED VALUE MANAGEMENT SYSTEM A Project Performance Tool
PRO 3002 Pam Soderholm Welcome To Class!. In Earned Value Analysis, what does “AC” stand for? Actual Cost of Work Performed QUALITY.
Earned Value Analysis by John Cornman. Introduction “Earned Value Analysis” is an industry standard way to measure a project’s progress, forecast its.
This work is licensed under a Creative Commons Attribution 3.0 Unported LicenseCreative Commons Attribution 3.0 Unported License (CC-BY). Project Management.
Project Management Methodology Project monitoring and control.
1 ev14a Interactive Session 4 u Tuesday, July 17 7pm to 10pm u Build a sqa plan for the dental office software u Assume a 3-person, development team, a.
Understanding Earned Value Analysis
1. Earned Value Analysis (EVA) Earned value is a measure of progress enables us to assess the “percent of completeness” of a project using quantitative.
EARNED VALUE MANAGEMENT (EVM)
10/19/ :26 AM 1 Project Cost Control. 10/19/ :26 AM 2  Controlling involves making sure that the results achieved are in line with the planned.
Earned Value SOS section Sp8Jan24ev3. Earned Value Analysis One approach to measuring progress in a software project is to calculate how much.
PRO 3020 Pam Soderholm Welcome To Class!. In Earned Value Analysis, what does “AC” stand for? Actual Cost of Work Performed.
UU Master Class Earned Value 17 July Earned Value Contents What is Earned Value / Earned Value Analysis Why and where is it used A brief history.
Introduction To Earned Value November 14, Definition Earned Value is a method for measuring project performance. It compares the amount of work.
Earned Value Analysis Tracking Project Progress. Introduction | Components | Project Scenario | Values | Calculations | Forecasts | Summary l What Is.
1 Earned value analysis Planned value (PV) or Budgeted cost of work scheduled (BCWS) – original estimate of the effort/cost to complete a task (compare.
PMP Study Guide Chapter 11: Controlling Work Results.
EVM – Do You Really Know What the Numbers Mean? Booz | Allen |Hamilton Seth Huckabee EVP, PMP, PMI-SP.
Schedule Control (Earned Value)
Agenda ‒ Cost Management ‒ Cost Budgeting ‒ Cost Control Learning Goals 1.Cost Control 2.Earned Value Management.
Project Management 1 Project Control. Project Management 2 Topics Project Control Status Reporting Earned Value Analysis.
Earned Value Management
Measuring Progress HNC Project Management. Measuring Schedule Performance Break project tasks up into small work units. Work units that are too large.
Project Management Earned Value Management Demonstration
Performance Measurement Baseline Contract Price (Project Price)
Earned Value Analysis by Miles M. Hamby, PhD Copyright©2014 Miles M
Project Monitoring
“PMP® Exam Prep” Earned Value Management
TOPIC-8B- PROJECT COST CONTROL
PROJECT MANAGEMENT AND CONTROL
Budget Planning.
Project Management (x470)
CHAPTER:7 Project Cost Management
Project Management – PTM712S
Performance Measurement Baseline Contract Price (Project Price)
5. Cost resources & PLAN DURATION
Earned Value Management
Project Cost Management
Work Packages / Deliverables Completed
Contract Performance Charts
Progress and Performance Measurement and Evaluation
Earned Value - What is it
Understanding Earned Value Analysis
Understanding Earned Value Analysis
Earned Value Analysis It is a continuous comparison between the plan of the project data and the actual data. Budgeted and Committed Cost: Variance = Budgeted.
An Introduction to Earned Value Performance Measurement
Implementing EV in IT A Three Step Approach John Chapman Touchstone Ltd
PROJECT COST MANAGEMENT
Earned Value Measures Planned Value (PV) Earned Value (EV)
ENGINEERING MANAGEMENT (GE 404)
فرآيند كنترل پروژه.
Earned Value Management
5. Cost resources & PLAN DURATION
5. Project PLAN & cost estimation
Project Management Life Cycle
Monitoring and Controlling
Understanding Earned Value Analysis
Earned Value $$$.
Chapter 13: Software Project Management
Presentation transcript:

Earned Value Management A management technique to: Assess project status make the appropriate adjustments as needed Based on 3 key project elements: Planned Value (PV) or BCWS ( budgeted cost of work scheduled) Earned Value (EV) or BCWP (budgeted cost of work performed) Actual Cost or ACWP (actual cost of work performed)

Graphical View CV = EV - AC SV = EV – PV Note: both cost variance and schedule variance are measured by the same unit ---- cost this puts a “burden” on the manager to interpret schedule AC PV EV Cost Time

Example note 9 6 5 Date : 4/5/2004 Actual Effort spent so far in Pers-days Estimated Completion date Actual Completion date Estimated Effort in Pers-days Work Tasks 1 10 10 2/5/04 2/5/04 2 25 3/15/04 3/25/04 15 3 1 30 9 4/25/04 4 5/5/04 4/1/04 25 20 5 6 5/25/04 15 5 6/10/04 20 6 Each estimated effort is the BCW (e.g. for work task 3 it is 30 person days). BAC = 10+15+30+25+15+20 = 115 person-days BCWS (on 4/5/04 – tasks 1 and 2 were scheduled to be completed) = 10+15 = 25 person days BCWP (on 4/5/04 –tasks 1, 2, and 4 are completed) = 10 +15+25 = 50 person-days ACWP (on 4/5/04 – actual cost of tasks completed) = 10 + 25 + 20 = 55 person-days

Two important Variance Metrics Schedule Variance (SV): the difference between the estimated efforts of the tasks that have been completed by the specified time and the estimated efforts of the tasks that were scheduled to be completed by the specified time or BCWP - BCWS in our example on 4/5/2004 : SV = 50 – 25 = +25 person days ( we are 25 person-days ahead in schedule _ Cost Variance (CV): the difference between the estimated efforts of the tasks that have been completed by the specified time and the actual efforts expended for the tasks that have been completed at the specified time or BCWP - ACWP in our example on 4/5/04 : CV = 50 – 55 = -5 person days ( we have a 5 person-days of over-run in cost)

Graphical Representation Beating schedule on 4/5/2004 ACWP BCWP ∆ = Cost Variance = BCWP-ACWP BAC = (∑ BCW’s) Effort ∆ = Schedule Variance = BCWP - BCWS BCWS 4/5/2004 Time

Two important Index Metrics Schedule Performance Index (SPI): SPI = BCWP / BCWS If SPI is 1 then I am on schedule target If SPI > 1 then ahead; SPI < 1 then behind In our example on 4/5/02: SPI = 50/25 = 2 Cost Performance Index (CPI) : CPI = BCWP / ACWP If CPI is 1 then I am on cost target If CPI < 1 then cost over-run ; CPI > 1 then cost under-run In our example on 4/5/02: CPI = 50/55 = .90 Would CPI index be more intuitive if it were flipped ? (e.g. CPI = ACWP/BCWP)

Potential Areas of Research Improve the definition of BCWP Improve or change the definition of “Schedule Variance” Improve on the “forecasting” formula which is given as Estimate at Completion (EAC): EAC = ACWP + [(BAC-BCWP)/CPI] EAC = ACWP + [(BAC-BCWP)/(CPI x SPI)] EAC = ACWP + [(BAC-BCWP)/ (aCPI x bSPI)] where a and b are some constants