Getting a Grid Connection to Export Power Energy in Agriculture 2016 23 rd August 2016.

Slides:



Advertisements
Similar presentations
Financing your Renewable Energy Technology Jos Mister Energy Saving Trust.
Advertisements

Electricity distribution and embedded renewable energy generators Martin Scheepers ECN Policy Studies Florence School of Regulation, Workshop,
Distributed Generation (DG)
East West Interconnector Background Security Of Supply Promote Competition in The Electricity Sector Accommodate Growth Of Renewable Energy Reduce Dependence.
Managing Director, HVPD Ltd
SolarCurrents TM Rebuild Ypsilanti Julie Londo August 26, 2010.
Grid Connections: Now and the Future Patrick Smart Head of Commercial and Regulatory 10 th November 2010.
Retail Energy Forum Andrew Neves Central Networks - CMG Chair 2 March | Energy Networks Association.
Community Energy Opportunities Jon Bell Business Development Manager Mosscliff Environmental Ltd.
GENFLEX TARIFF AND INCOPORATION OF THE MEC INTO THE NMD RULES
Interconnection of Distributed Generation
Marek Kras. A combined cycle gas turbine power plant, frequently identified by CCGT shortcut, is essentially an electrical power plant in which a gas.
You currently have no control over ever rising electricity prices Electricity costs have doubled over the last 10 years* What will your electricity bill.
Biogas Workshop 10 th March 2009 ANF Energy Solutions Inc Power Purchase & Connection Power Purchase and Grid Connection Procedures Aidan Foss ANF Energy.
Topics to Cover Interconnection Process Overview
Review of progress and future work SQSS Sub Group 2 August 2006 DTI / OFGEM OFFSHORE TRANSMISSION EXPERTS GROUP.
Distributed Generation Programs, Incentives and Interconnections Ian Loughran, P.Eng. DSM Program Leader Renewable Energy Programs
Grid Access Unit Small and Micro Generator frame-work key focus areas Date : 18 April 2013.
JSC “Moscow United Electric Grid Company” (JSC “MOESK”) Operating activity’s results for the first half year of 2010.
Contributions In-Aid and Development of Fees Utility Financial Solutions Mark Beauchamp, CPA, CMA, MBA President
Estimados Expositores del II Seminario de Electricidad Consequences of increasing penetration of distributed generation on transmission and distribution.
How to deliver a Renewable Energy Project Jemma Benson CO2Sense Yorkshire.
AFREPREN/FWD Cogen Centre Training Workshop on Cogeneration in Africa
CIRED 2011RT 5b TSO-DSO co-ordination of planning for wind connections Tony Hearne Manager, Renewable Planning ESB Networks.
Net Metering and Embedded Generation NB Climate Action Change Hub Advisory Committee Meeting – October 1, 2008 Saint John, NB Linda Berthelot.
Rick Allison – Chief Engineer, Enercon Engineering Presented by Lawrence Tangel V.P. Enercon Engineering Chairman of USCHPA NON TRADITIONAL METERING flkjsflkfjl.
Grid Connection Issues Micro Hydro Projects Rachel Hodges.
1 Distributive Generation Wind Landfill Solar Fuel CellMicro-Turbine.
Contractual framework YOU LandlordInstallerPlannersDNO FiT licensee.
Electrical Engineering
1 SYMPOSIUM: U G A N D A A F T E R I D I A M I N A N D M I L T O N O B O T E Hamburg, Germany 29 th September 2008 INVESTMENT OPPORTUNITIES IN POWER GENERATION.
Connecting Low Carbon Generation Clive Goodman Primary System Design Engineer.
BIDDER’S CONFERENCE: Eskom Grid Connection Process and related matters Date: 16 August 2012.
Interconnected Generation Preliminary Engineering Work Related to Fees.
PPU TERANG HATI PROJECT POWER DISTRIBUTION ENGINEERING (EPEB453)
Pre-Grid Commissioning for Renewables Alf Scambler Renewables Sector Development Manager.
GRID INTEGRATION COST OF PHOTOVOLTAIC POWER GENERATION G. Strbac, D. Pudjianto, P. Djapic, J. Dragovic Energy Futures Lab.
Contestability in Connections Contestability Working Group Meeting NIE/SONI Joint Presentation 9 September
Tipperary County Council ‘Energy in Agriculture 2016’ Gurteen Agricultural College, Tuesday 23 rd August Renewable Energy - Planning Issues Nuala O’Connell,
Stray Current Mitigation & Cathodic Protection Regulation Pipeline Corrosion Management seminar Melbourne 29 June 2017 Peter Wade Manager Electrolysis.
Évora demonstrator site
Interconnecting Wind & Solar Energy in Texas
Planning and Realisation of Wind Farms
YEL WIND POWER PROJECT. YEL WIND POWER PROJECT.
Progress Briefing - Energy Initiative
Are Solar Panels right for Danescourt Primary School?
Electricity is produced at the power station.
DS3 and Qualifier Trials Update
Alternative Energy Promotion Center (AEPC)
Electrical Energy How is it generated and distributed?
Évora Demonstrator Site
Euan Norris SPEN Gavin Stewart SSEN
Electrical Energy How is it generated and distributed?
Interconnection Practice, Policies, Procedures ComEd Illinois
Electricity Distribution Network Design Training & Courses
Transmission and Sub-Transmission Network India – Present and Future Rajesh Suri GE (T&D) India Ltd 8 November 2018.
Renewable Energy In Egypt
The Joint Accounting Conference 2018
Pacific Power Seismic Preparedness Update
City Council April 30, 2018 Item 13
Sami Repo Tampere University of Technology FINLAND
DIMAN Solar Rooftop Solutions Grid Connected
Progress on the Renewable Energy IPP Procurement Programme
Microgeneration 26th August 2010 ESB Networks
UK typical power transmission and distribution costs
Puerto Rico Electric System Challenges Ahead
Solar Opportunities in Ontario
ILO Industrial Opportunities Days, 6-7 June 2019
Opportunities for Local Energy
Typical power transmission and distribution costs
Presentation transcript:

Getting a Grid Connection to Export Power Energy in Agriculture rd August 2016

Mullan Grid Consulting Electrical engineering consultancy specialising in grid connections for renewable generator installations Ongoing projects in Ireland & Northern Ireland Technical Advisor for approx 1500 MW of wind generation projects and multiple Solar, biomass, marine and hydro projects Experience of Gate 1, 2 & 3 and Non-GPA Represented on IWEA Council, IWEA & NIRIG Grid Committees & Gate 3 liaison group PPA Solutions established in 2012 to advise on PPAs

The Electricity System and its Operation 400 kV 220 kV 38 kV 110 kV 20/10 kV (Medium Voltage/MV) 400/230 V (Low Voltage/LV)

Distribution Network – 20/10 kV

High Voltage Network

Connection Offer Process - CER/09/099

Application form – NC5 and associated documents to be submitted to ESBN along with ESB Networks Fee Connection Offer Processed- Non GPA applications are processed one node at a time based on deemed complete date order. Estimated timelines for processing a connection offer by ESB Networks is currently estimated at 6-9 months. Execute offer – 3 months Connection works begin Connection Offer Process- Export

Micro-generation is classed as the connection of a generator with an MEC of less than 6kW (Single phase) or 11kW (three phase) Examples of micro-generator technology include Wind Turbines, Solar PV, Hydro and CHP There is currently no charge to apply or connect a micro-generator to the ESB network provided it is compliant. Complete Micro-Generation Application form – NC6 and return to ESB Networks. The applicant must confirm if an import/export meter is required on the application. ESB Networks will provide a quote for the installation of a meter if required, the cost of the meter is approx. €350. Proceed with installation of the Micro-Generator by a registered electrical contractor- The generator must comply with ESB Standards EN50438 and a compliance certification must be provided to ESB Networks. Do not proceed if notified by ESB Networks to not do so. ESB Networks will install the meters once the Micro-Generator has been installed, the relevant electrical certificates have been provided and payment for the meters has been received. The Micro-Generator can contact an electricity supplier to arrange purchasing/supplying of electricity once a meter has been installed. Connection Offer Process- Micro Generation

Generators with no export capacity are generally referred to as Paralleled Generators Apply to ESB Networks using the NC5 application, an OS Map and a detailed Site Plan. There is currently no charge to apply to connect a zero export generator to the ESB network, ESB Networks have suggested this may change in the future. A quote and connection agreement will be issued by ESB Networks within 30 days. It is likely these timescales will be increased at present due to the unprecedented volume of Non GPA applications. ESB Networks will liaise with the customer to ensure protection requirements are met and a connection agreement will be issued including the Maximum Import Capacity (MIC) and Maximum Export Capacity (MEC) of the site (this will be zero). The installation must comply with ESB Network protection requires, the testing of this connection must be witnessed by ESB Networks. Connection Offer Process- Parallel Generation

For Export, The connection method will depend on Proposed maximum export capacity (MEC) 2.Distance from local 38/MV substations 3.Distance from local 10kV or 20kV network 4.Existing and planned generation on the network 5.Existing infrastructure i.e. size of existing conductors, and transformers 6.Existing transformer capacity 7.Location i.e. urban or rural area 110kV substation with limited or no transformer capacity (pre solar)

Case Study 1 – 500kW Generator Connection Method A connection onto the existing MV Network, suitable for a 500kW Generator. Connection Timeline It is estimated that it will take ESB Networks approx. 6-9 months to process a connection offer. Delays may occur due to other Non GPA applications in the area. Estimated timelines to construct this connection method are 9-12 months from execution of a connection agreement assuming that no upgrades are required on the existing MV Network. Point of Connection (POC) MV/LV Site Existing 3 phase 10/20kV network ~ MV Line CB/ Ring main unit MV CT/VT’s Generator (500kW) T-Connection to MV OHL MV/LV 630kVA transformer Ownership – ESB Networks Ownership – Developer 0.5km MV OHL from compound to existing MV network meter G10 protection LV Line CB

Case Study 1 – 500kW Generator

Estimated Connection Costs Estimated Connection cost for Case Study 1 is €140, 832

Case Study 2 – 500kW Generator Connection Method A dedicated MV aconnection to the local 38kV/MV Substation. Connection Timeline It is estimated that it will take ESB Networks approx. 6-9 months to process a connection offer. Delays may occur due to other Non GPA applications in the area. Estimated timelines to construct this connection method are months from execution of a connection agreement. Higher risk connection compared to Cast Study 1 due to longer distance of new build MV OHL required. Generator (499kW) MV/LV Site ~ MV Line CB/ ring main unit MV CT/VT’s MV/LV 630kVA transformer 2km MV overhead line from compound to 38kV substation Typical 38/MV Substation: 2 x 38/MV 5MVA transformers MV Busbar 38 kV Busbar 38kV Trafo CB MV Line CB To 38kV network Point of connection meter Loads 38kV substation

Case Study 2 – 500kW Generator

Estimated Connection Costs Estimated Connection cost for Case Study 2 is €286,620 Potential to increase the amount of MW’s to reduce the cost per MW price

System Upgrade Costs Uprate MV overhead line per km €52,260* New 10MVA 38/MV transformer 100% Uprate 38kV overhead line per km €88,070-€110,310* €455,910* Connection Asset As existing and planned generation uses up spare capacity, upgrading overhead line, underground cable or transformers could be required Generators are allocated the full cost of distribution deep reinforcements However these reinforcements will not be required for all connections These reinforcements only identified when ESBN complete power system studies ESBN Standard Prices Uprate 2 * 110/38kV 31.5MVA transformer to 2 * 110/38kV 63MVA 100% €2,903,070* *ESB Standard Prices for Generators 2015

Rory Mullan Tel: Mob: