1 10/1/2016 Cut-Over Milestones 01 September 2010Market Readiness Seminar.

Slides:



Advertisements
Similar presentations
Review of NPRR586 CMWG 1/7/2014. Existing Credit Lock Process ERCOT calculates a “preliminary allocated CRR transaction limit” based on “eligible” CRRAHs.
Advertisements

1 TSP Nodal Engagement Market Participant Call ERCOT August 04, 2010.
Congestion Revenue Rights Activity Calendar Update Donald House CMWG September 19, 2014.
Lead from the front Texas Nodal 1 Texas Nodal Market Implementation Program Implementation Scenarios September 6, 2006.
Market Trials - Friday call Credit and Treasury Weekly Update September 3, 2010.
1 Market Trials Outage Scheduling Weekly Update July 23, 2010.
1 Single Entry Model (SEM) Go-Live Update ROS Update July 16, 2009.
1 Nodal Market Readiness Cut-Over Activities Kick-Off Meeting May 25, 2010.
Lead from the front Texas Nodal 1 EDS 4 Release 9.1 DAM/RUC/SASM Market Call January 11, 2008.
1 Market Readiness Seminar 6 Remaining Market Trials and Cutover Activities Sept 01, 2010.
ROS Meeting – 12/06/071Texas Nodal Program - TPTF Update Texas Nodal Transition Plan Task Force ROS Meeting Stacy Bridges, ERCOT Thursday, 12/06/2007.
1 Market Readiness Seminar 9 Remaining Market Trials and Cutover Activities November 10, 2010.
1 Market Trials Outage Scheduling Weekly Update June 25, 2010.
Lead from the front Texas Nodal 1 Texas Nodal Congestion Revenue Rights (CRR) EDS 3 Release 7 - Overview EDS 3 Phase 2 MP Planning.
1 Market Trials Update NATF June 1, 2010.
April 2, 2008 CRR Team Update PCRRs CRR Team UpdateApril 2, 2008 Table of contents 1.What is a PCRR? 2.Which NOIEs are eligible for PCRRs? 3.What.
Lead from the front Texas Nodal 1 Integrated ERCOT Readiness and Transition (IRT) TPTF - November 6 th, 2006.
Nodal Program Update Technical Advisory Committee 4 November 2010.
October 20, 2010 WMS Credit Update. 2 Topics Nodal exposure – how much collateral CRR/TCR auctions – December 2010 Preliminary Credit Cutover Timeline.
1 Market Trials Congestion Revenue Rights Weekly Update May 6, 2010.
CRR Issues Transparency provided by CRR Reports CRR EDS handbook Business process NPRR TPTF November 27, 2007.
Lead from the front Texas Nodal 1 Texas Nodal Registration Kick-off Meeting Matt Mereness June 6 th, 2007.
January 21, 2008 TPTF 168 Hour Test Initial Approach Discussion.
1 TSP Nodal Engagement Market Participant Call ERCOT September 15, 2010.
1 Market Trials Congestion Revenue Rights Weekly Update September 3, 2010.
Lead from the front Texas Nodal 1 EDS 4 Outage Scheduler EDS Market Call May 30, 2008.
TCR to CRR Transition Plan Proposed method for TCR Auction Revenue refunds Contingency plans For TAC Nov 1st, 2007.
9/17/2012 CSWG CSWG – ERCOT Update ERCOT. 2 Settlements Project & Operational Updates February 27, 2012 NPRR 347: Combined Daily Invoice –Still on track.
Outage Scheduler Transition Plan Kenneth Ragsdale NATF.
February 5, 2008 TPTF 168 Hour Test Follow up discussion.
1 Market Trials Outage Scheduling Weekly Update August 20, 2010.
Congestion Revenue Rights Activity Calendar Update Donald House CMWG October 23, 2015.
Lead from the front Texas Nodal 1 Texas Nodal Market Implementation Program Implementation Scenarios September 6, 2006.
Market Readiness Seminar Update Nodal Cutover Update July 28, 2010 Market Readiness Seminar #5.
1 Market Trials Outage Scheduling Weekly Update August 13, 2010.
1 Cutover Market Call November 27, 2010.
Cutover Update NATF 2 November Today’s Agenda Reminders Program Status 24 Hour LFC Test Update Cutover Update Soft Launch 2 November 2010NATF.
Market Readiness Seminar #5 July 28, 2010 Market Readiness Seminar #5.
July 28, 2010 Market Readiness Seminar Credit Transition to Nodal (Preliminary)
Lead from the front Texas Nodal 1 EDS 4 Outage Scheduler EDS Market Call April 25, 2008.
1 Market Trials DAM/RUC/SASM Weekly Update March 19, 2010.
Congestion Revenue Rights Market Trials Kickoff. Agenda Topics: I.Overview of CRR Market Trials Phase 3.0 II.Entry Criteria (including System Requirements)
Congestion Revenue Rights 1 TCR to CRR Transition Plan NOIE Workshop Nodal CRR registration process for NOIEs (REVISED) Beth Garza.
Lead from the front Texas Nodal 1 Integrated ERCOT Readiness and Transition (IRT) TPTF – December 4 th, 2006 ERCOT Qualification.
1 Market Trials Open Market Participant Call Weekly Kick Off Aug 09, 2010.
1 Market Trials Open Market Participant Call Weekly Kick Off May 10, 2010.
Transition Plan Network Operations Model Change Requests 5/26/2010.
Retail Workshop ERCOT Nodal Update October 06, 2010.
Network Operations Model Go-Live Decision Kenneth Ragsdale TAC July 1, 2010.
1 Market Readiness Seminar 7 Remaining Market Trials and Cutover Activities October 01, 2010.
Lead from the front Texas Nodal 1 MP10 / MP11 Registration Data Update Oct 14, 2008 TPTF.
1 Weekly Market Call Weekly Update November 05, 2010.
1Texas Nodal NATF Readiness Update Vikki Gates May 4, 2010.
1 Market Trials Update NATF January 5, 2010.
1 Single Entry Model (SEM) Go-Live TAC Update May 7, 2009.
Lead from the front Texas Nodal 1 Texas Nodal EDS4 - Approach 11/28/2007.
1 Market Readiness Seminar 6 Remaining Market Trials and Cutover Activities Sept 01, 2010.
1 Single Entry Model (SEM) Go-Live Update TAC Update August 6, 2009.
1 Readiness Scorecard – Market Readiness Series Brandon McElfresh Nodal Readiness and Transition January 28, 2010.
August 11, 2008 TPTF EDS Sequence and Durations Discussion Daryl Cote.
Market Trials Update NATF March 2,
CRR MUI Upgrade Requalification Demonstration WebEx
Market Trials Congestion Revenue Rights
Market Trials Open Market Participant Call
Market Readiness Seminar 8
ERCOT CRR Update to CMWG
CRR Activity Calendar Carrie Bivens Manager, Forward Markets
PR CRR Framework Upgrade
Market Trials Open Market Participant Call
Market Trials Open Market Participant Call
Presentation transcript:

1 10/1/2016 Cut-Over Milestones 01 September 2010Market Readiness Seminar

2 01 September 2010 Cutover Tasks Complete (08/13) Registration Deadline for CRRAH to participate in December CRR Monthly Auction (Protocol ) (08/16) ERCOT releases Outage Scheduler to Market  TSPs/QSEs can enter outages in Outage Scheduler via Web Service or UI  TSPs/QSEs are responsible for verifying outages imported to Nodal Systems and correcting any missed/incorrect outages by 09/17/2010 (09/01) Network Model Go-Live (Protocol 3.10 ) (09/02) Begin interim update process for Network Model Changes  From 09/02 forward until Go-Live any Model changes submitted to ERCOT prior to Go-Live will leverage the interim update process. (09/01) CRR Activity Calendar to MIS  MPs can retrieve the CRR Activity Calendar from MIS public with a valid Digital Certificate Cutover Update

3 Market Readiness Seminar01 September 2010 Next 2 Weeks (09/08) Deadline for PCRR NOIE Contract Eligibility (09/17) Outages are synched between Zonal and Nodal.  Market Participants maintain synch of outages between Zonal and Nodal systems thru 12/02 (dual entry) Next Month Summary (CREDIT) ERCOT assesses each CPs credit worthiness for the Dec CRR Auction ERCOT posts ACLs daily for CRR December monthly auction to CRR  CRRAH able to retrieve ACLs from CRR system each business day.  MPs can post additional collateral until 11/08/2010 for Dec 2010 CRR Auction (CRR) ERCOT begins accepting PCRR Nominations for December Monthly Auction ERCOT shall allocate PCRRs to NOIEs for the 2010 December Monthly Auction and publish to MIS ERCOT shall post CRR Network Model for the 2010 December Monthly Auction to MIS ERCOT to post December 2010 Monthly Auction Notice to MIS Cutover Update – Upcoming Activities

4 Market Readiness Seminar01 September 2010 Next Month Summary Cont’d (OUTAGES) December Outages pulled for CRR Network Model (for PCRR Allocation) (NETWORK MODEL) Network Model built for CRR Allocation and Auction Network Operations Model posted to TSP Citrix location and TSPs begin validation process (ERCOT) ERCOT begins test data clean up from Market Trials  CRR Test Data ERCOT performs MIS backend reconfigurations (10/03/2010 – 10/11/2010)  Market Participants will not have access to the MIS UI and EWS Get Reports functionality.  Market Participants will need to use the direct links (listed on next slide) or Citrix to access system applications.  All other EWS will be left on and from 10/1 up until the First Run Date as defined in EMIL of the CDR report, the EWS will return ‘no reports found’ during that time. MIS UI and EWS Get Report Go-Live (10/12/2010)  Postings will be made available based on the EMIL posting date going forward  Postings live prior to 10/12/2010 will continue to be made available at this time.  Market Participants will only have access to go-live posting data. Data from Market Trials activities is no longer available for download. Cutover Update – Upcoming Activities

5 URLs to be used during cutover activities in October: – Network Model via Citrix: – – Market Manager User Interface: – – Outage Scheduler Application: – – CRR Application (MUI): – - direct link for CRRAHshttps://mis.ercot.com/crr/mui/ListAllUserMessage.do – - direct link for CPshttps://mis.ercot.com/crr/mui/editSMPCreditLimit.do –Web Services Endpoint URL: – Cut-Over – MIS UI and EWS Get Report Reconfiguration Details 01 September 2010Market Readiness Seminar