Yakima Air Terminal.  Project Overview  Project Schedule  Impacts  Project Status  Questions.

Slides:



Advertisements
Similar presentations
Part 139 Training 1.
Advertisements

SILVER COMET FIELD AT PAULDING NORTHWEST ATLANTA AIRPORT FIVE YEAR CAPITAL IMPROVEMENT PROGRAM.
1.0 Item: Northside Development and Destination Lindberg Study Impacts: The possibility of acquiring Marine Corps Recruit Depot land and building terminal,
Airport considerations and airport solutions Session 5 Presentation 3.
Yakima Air Terminal.  Project Overview  Project Schedule  Impacts  Project Status  Questions.
Titusville to Edgewater Bike Loop PD&E Study
Presentation to SEC-AAAE Annual Conference Chicago Department of Aviation April 19, 2010.
Yakima Air Terminal/McAllister Field Master Plan Airport Board Briefing May 21, 2012 YAKIMA AIR TERMINAL | McALLISTER FIELD | Yakima, WA 1.
Lander Streets and Utilities 2015 Public Meeting No. 2 McDougall & Cliff Project Area.
Dillon and Christina Project Area Lander Streets and Utilities 2015 Public Meeting No. 2.
6 th Street Water Main And Street Reconstruction 2013.
Association of California Airports September 20, 2007.
Project Construction Update August 30, 2011 I-5 North Stockton Freeway Widening and Pavement Reconstruction Project Between Dr. Martin Luther King Jr.
Yakima Air Terminal.  Project Overview  Project Schedule  Impacts  Project Status  Questions.
August 18, 2011 State Route 99 Auxiliary Lanes Project Route 32 to East 1st Avenue.
75 Express Lanes Segment D Construction From South of Sheridan Street to North of Griffin Road Presentation to Ivanhoe Community August 27, 2014.
Millinocket Municipal Airport November 5, 2014 Meeting.
SR-528 (Beach Line)/ SR-3 (Courtenay Blvd) Emergency Bridge Repair January 21, 2011.
Recent Lighting and Marking Design Challenges/Trends
U.S. 31 at CR 400 South Roundabout Information Meeting December 18, 2013 Clifty Creek Elementary Columbus, Indiana.
The Months and The Seasons Prepared by Claudia Doria and Terra Myers.
2012 CALENDAR. JANUARY 2012 Sunday 日 Monday 月 Tuesday 火 Wednesday 水 Thursday 木 Friday 金 Saturday 土
January 2012 Monday Tuesday Wednesday Thursday Friday Sat/ Sun / /8 14/15 21/22 28/
FLASH CARDS The AOPA Air Safety Foundation (ASF)
Saturday May 02 PST 4 PM. Saturday May 02 PST 10:00 PM.
ISE Capstone Project by Michael Ferry University of Minnesota 2008.
Time Zones The World is divided up into 24 time zones. Each time zone is approximately 15 degrees of longitude wide. The time within each time zone has.
MONDAYTUESDAYWEDNESDAYTHURSDAYFRIDAYSATURDAYSUNDAY WEEK WEEK WEEK WEEK WEEK CALENDAR PROJECT.
1 Winter Operations Program Presented by Ken Greene October 10, 2011.
Talofa!! from American Samoa. American Samoa.
Penn Liberty Motors Automobile Dealerships. Location 20 North Broad Street Philadelphia, PA
Class Schedule Template SundayMondayTuesdayWednedayThursdayFridaySaturday 6 AM 7 AM 8 AM 9 AM 10 AM 11 AM 12 AM 1 PM 2 PM 3 PM 4 PM 5 PM 6 PM Title Classroom.
US 1 COLLEGE PARK – SEGMENT 1 FROM COLLEGE AVE/REGENTS DRIVE TO MD 193 (UNIVERSITY BLVD) Presentation to College Park City Council August 5,
What day is today? What`s the date?. Sunday Monday Tuesday Wednesday Thursday Friday Saturday What day is today?
34th Eastern Region Airports Division Annual Conference
Disclaimer – Any and all information contained herein is subject to change without notice 1 O’Hare Airfield Configuration EXISTING Airfield Configuration.
Dates to mark on your summer calendar August 23 – Annual Rummage Sale. Set up starts August 21 with take down through August 25 August 24 – Message and.
Presented to: By: Date: Federal Aviation Administration 2012 ACA Annual Conference David F. Cushing, Manager, LAX-ADO Wednesday, September 11, 2013 Construction.
MICRONESIA AIP PROJECT STATUS UPDATE
Pacific Aviation Directors Workshop March 13 – 15, 2012 Hosted by: A B Won Pat International Airport - Guam F ederal A viation A dministration DEPARTMENT.
Some things can’t wait for traffic Capital Beltway HOT Lanes Project New Travel Choices Ahead.
San Antonio Airport System Overview Presented to the Airport Ground Transportation Association September 13, 2010.
WELCOME! July 31, 2012 ODOT District July 31, 2012 PURPOSE OF TONIGHT’S MEETING Introduce the project –Reconstruct I-75.
2010 FAA Worldwide Airport Technology Conference Chicago Department of Aviation April 20, 2010.
1 Leon County Board of County Commissioners MICCOSUKEE ROAD RESURFACIING INTERMITTENT ROAD CLOSURE From North MERIDIAN STREET To DOCTORS DRIVE.
SHDH Perimeter Radiation Improvements Town Hall Meeting – June 23, 2015.
Design Manager: Chris Thomas CEAL July 17, Interstate 8 (I-8) to Interstate 5 (I-5) Connector Widening and Auxiliary Lane Project.
COUNTY ROAD 517 Improvements from State Highway 172 to Howe Drive DECEMBER 16, 2015 At Tribal Multipurpose Facility.
Important Dates SundayMondayTuesdayWednesdayThursdayFridaySaturday Temporary Exhibits Recognition 6pm-8pm, Southeast Atrium Session.
Junior Presentation. PSAT: What does it mean?  The PSAT is a practice test that measures the knowledge and skills you have developed in reading, writing,
Madison Avenue Reconstruction Department of Planning and Development.
Expense Report Total Miles MONDAY 5 5 TUESDAY WEDNESDAY 6 6 THURSDAY FRIDAY SATURDAY 0 SUNDAY0 TOTAL 23.
NHS Meetings Calendar All Meetings are at 2:20pm unless otherwise stated This logo denotes a General Meeting. This means that ALL MEMBERS must.
The Calendar.
Conestoga Valley High School Aviation Technology Airports The Lancaster Airport, located on Manheim Pike, was first opened in 1935 and is Lancaster’s only.
Griffin-Spalding County Airport LPA Group Project Update Presented to September 28, 2009.
PRESENTATION TO: CITRUS COUNTY BOARD OF COUNTY COMMISSIONERS 11 AUGUST 2015 INVERNESS AIRPORT MASTER PLAN UPDATE.
Airports of Montenegro. General informations  Airports of Montenegro is a public enterprise established by the Government of the Republic of Montenegro.
City Manager Report – May, 2016 Presented to: Minot City Council City Manager Report – May, 2016 Presented to: Minot City Council Lee Staab, City Manager.
HYLTON BRIEFING NO. 3. Reminder of Key Dates: Restaurant Closes 26/05/16 Exam Weeks GCSE & FS w/c 06/06/16 and 13/06/16 Stepping Up w/c 06/06/16 and 13/06/16.
Apalachicola Regional Airport
June 5, 2017.
Facilities Report to the Buffalo State College Senate May 6, 2016
Malibu Canyon Pole Replacement Project Information
SW Gage Blvd - Street Repair Project
Highest Activity Day: 694 Ops Wednesday May 10
PROJ. 566(17) LOR PID MAJOR WIDENING
projects update ATLANTA district
Contract 60X10 Informational Meeting Weber I-55
S.R. 26 Road Rehabilitation in Clinton County
Presentation transcript:

Yakima Air Terminal

 Project Overview  Project Schedule  Impacts  Project Status  Questions

 The Yakima Air Terminal has received an $11,000,000 grant. The grant is to:  Resurface and widen Alpha Taxiway, Taxiway Connectors A1-A5, and portions of Bravo and Charlie Taxiways;  Resurface airfield pavement between the north taxiway edge line to the non-movement line;  Replace the existing MITL system with LED MITL, including new conduit, fixtures, and regulator;  Replace all existing directional and hold short signs; and  Correct several markings not meeting FAA standards.

 Expected construction START DATE April 18, 2016:  Phase 1: April 18, 2016 – May 13, 2016  Phase 2: May 14, 2016 – June 3, 2016  Phase 3: June 4, 2016 – June 24, 2016  Phase 4: June 25, 2016 – July 15, 2016  Phase 5: July 16, 2016 – August 5, 2016  Phase 6/7: August 6, 2016 – September 7, 2016

 Runways 9/27 Closure  April 18, 2016 – August 5, 2016  Monday, Tuesday, Wednesday, Thursday, & Friday  6:50pm - 11:00pm  12:00am (midnight) – 5:45am  Saturday ONLY  6:10pm – 5:45am  The contractor doesn’t anticipate construction work on Sunday. However, if there’s a need to recoup construction days to meet the deadline of each phase, we’ll institute the same runway closure illustrated Monday-Friday.

 Phase 1: April 18, 2016 – May 13, 2016  Ramp Closures.  McCormick West, and Plath Hangar.  Partial Ramp Closures.  Fuel Tank/House and McCormick Air Center.  Temporary Runway 9/27 Closure for work within the Runway Safety Area.  On-going construction activities and vehicle traffic on service roads and ramps.

 Phase 2: May 14, 2016 – June 3, 2016  Ramp Closures.  Airlift Northwest, FedEx Air Cargo and Airport Maintenance Building.  Partial Ramp Closures.  McCormick Air Center and Private Hangars (formerly Noland-Decoto).  Temporary Runway 9/27 Closure for work within the Runway Safety Area.  On-going construction activities and vehicle traffic on service roads and ramps.

 Phase 3: June 4, 2016 – June 24, 2016  Ramp Closures.  GE Aviation, West Itinerant Ramp, Med Assets, and West Terminal Apron Ramp.  Partial Ramp Closures.  Private Hangars (formerly Noland-Decoto).  Temporary Runway 9/27 Closure for work within the Runway Safety Area.  On-going construction activities and vehicle traffic on service roads and ramps.

 Phase 4: June 25, 2016 – July 15, 2016  Ramp Closures.  East Terminal Apron Ramp.  Partial Ramp Closures.  East Itinerant Ramp.  Runway 4/22 and Bravo Taxiway Closed.  Temporary Runway 9/27 Closure for work within the Runway Safety Area.  On-going construction activities and vehicle traffic on service roads and ramps.

 Phase 5: July 16, 2016 – August 5, 2016  Ramp Closures.  No Ramps Closed.  Alternate routes required for: Cub Crafters, McAllister Museum, Advanced Medical Systems, and South Air Park.  Temporary Runway 9/27 Closure for work within the Runway Safety Area.  On-going construction activities and vehicle traffic on service roads and ramps.

 Phase 6: August 6, 2016 – September 7, 2016  Partial Ramp closures denoted by barricades.  Runway 4/22 closed intermittently.  On-going construction activity and vehicle traffic on service roads and taxiways.

 Phase 7: August 6, 2016 – September 7, 2016  Final application of airfield markings completed.  Not expecting any closures, however a schedule will be provided of the impacted areas to minimize air traffic and vehicle operations within the work areas.  On-going construction activities and vehicle traffic on service roads and ramps.

 If at all possible, avoid construction areas.  Please plan all operations around construction to the maximum extent possible.  If there are known operations that will be impacted by the proposed schedule, please let us know.  The Airport Management will provide NOTAMs.  Do not travel (plane or car) across barricades delineating closed pavement.  Do not provide direction to the contractor unless there is an emergency.

 Robert Peterson Office: (509) (#7) Cell: (509)  Kris Yalovich Office: (509) (#7)  Stephanie Ray, PE (509)  Michael Battle, PE (509)