D.Macina TS/LEATOTEM Meeting25/02/2004 Roman Pot test at the SPS Test of the Roman Pot prototype in the SPS proposed in December 2003 (CERN/LHCC 2003-061):

Slides:



Advertisements
Similar presentations
“LHC Controls for Sector Test” Planning SPS Extraction Kicker and Septa LHC Injection Kicker and other equipment (beam stoppers, dumps,...) Etienne CARLIER.
Advertisements

André Augustinus 16 June 2003 DCS Workshop Safety.
Beam commissioning strategy Global machine checkout Essential 450 GeV commissioning System/beam commissioning Machine protection commissioning.
MONALISA installation at the ATF2 ATF2 weekly meeting.
The LHCf experiment Measurement of Photons and Neutral Pions in the Very Forward Region of LHC Letter Of Intent: May 2004 Technical report: September 2005.
Saverio MINUTOLITIG meeting, 10 February Report on T1 installation activities and achievements made during this shutdown.
Strategy for SPS 200 MHz LLRF upgrade (1)  Each of the four cavities (2x 5 sections, 2x 4 sections):  1-T Feedback (loop around cavity and amplifier)
May Exp-Area meeting1 Safety Systems Installation status Flammable Gas Detection System Fire Detection System in SG8 ODH Detection System CO2 Detection.
P. 1Mario Deile – TOTEMino: Infrastructure Status and Schedule Mario Deile Zone 2.Gas system 3.Cabling 4.Cooling water 5.Counting-Room 6.Safety.
Gueorgui ANTCHEVNEC’2013 – Varna, Bulgaria 1 The TOTEM Experiment Consolidation and Upgrade G. Antchev * On behalf of the TOTEM Collaboration * INRNE-BAS,
The First 1 ½ Years of TOTEM Roman Pot Operation at the LHC M. Deile, G. Antchev, I. Atanassov, V. Avati, J. Baechler, K. Eggert, J. Kašpar, F. Lucas Rodriguez,
January 2006Beam dump and injection inhibits / J.Wenninger1 Beam Dump and Injection Inhibits J. Wenninger AB-OP & D. Macina TS-LEA LHC experiments signals.
Running at Low  * and High Lumi Test insertion on 13 October 2011:
Status of the Roman Pot Movement System and the Interlocks Mario Deile
Proposal for Decisions 2007 Work Baseline M.Jonker for the Cocost* * Collimation Controls Steering Team.
Construction and Installation Readiness of TOTEM Roman Pots Detectors Federico Ravotti (PH/TOT) Gennaro Ruggiero (PH/TOT) LHCC minireview – 06 May 2009.
07-JUL-2003LEADE / JW1 Satellite bunches in the LHC Satellite “definition” Satellite luminosity Satellite detection & tolerances J. Wenninger AB/OP.
ATLAS Forward Detector Trigger ATLAS is presently planning to install forward detectors (Roman Pot system) in the LHC tunnel with prime goal to measure.
Experimental equipment interacting with beam operation D. Macina TS/LEA Many thanks to my colleagues both from the experiments and the machine for their.
LS2 Other LHC Experiments Mike Lamont Thanks to: Michael Rijssenbeek (AFP) Joachim Baechler (TOTEM) Karl-Heinz Hiller (ALFA)
Plan for start-up with beam Friday  19:00 Machine closed. Ramp for powering tests & pre-cycle  22:00 Pilots through nominal cycle up to collisions. Measure.
Roman Pot Engineering Design Review CERN, 14 February 2006 M.Oriunno, CERN PH-TOT Installation, Commissioning and Schedule.
 A brief history of time  In the years BC.  My years at CERN  Current position  What is a Technical Coordinator?  The different type of intervention.
Test beam setup: status report 02/03/2009 M. Alfonsi (CERN)
Post Mortem Collimators and Movable Objects Michel Jonker Post Mortem Workshop Cern, 16 & 17 January 2007.
R. Assmann - LHCCWG Two Beam Operation R.W. Aßmann LHCCWG Acknowledgements to W. Herr, V. Previtali, A. Butterworth, P. Baudrenghien, J. Uythoven,
STATUS REPORT: ALIGNMENT OF COLLIMATORS P. BESTMANN /O. ABERLE Collimation Working Group 26/09/2011.
CMS Muon detectors for the GIF++ DRAFT Needs discussion within CMS Muon community A. Sharma.
The Stripping Foil Test Stand in the Linac4 Transfer Line
Saturday 7ish – refill for RP set-up 9:15 Going for Roman pot alignment. Stefano is coming. 12:10 TOTEM: Alignment of horizontal RPs B2 finished, short.
HiRadMat – Users Meeting 6/2/2015 Adrian Fabich EuCARD-2 is co-funded by the partners and the European Commission under Capacities 7th Framework Programme,
17 th November, 2008 LCWS08/ILC08 1 BDS optics and minimal machine study Deepa Angal-Kalinin ASTeC & The Cockcroft Institute Daresbury Laboratory.
00:15: Stable beams fill 1883, 1.1E33 cm-2s-1.  Seems the 144 bunches beam 1 doe not fit properly on the injection kicker waveform. Systematically the.
P. 1Mario Deile – Meeting on Experiment Protection from Beam Failures Protecting TOTEM Mario Deile PH-TOT
Activities related to Experiments during TS3 and YETS th November, 2015 M. Bernardini, M. Barberan With the support of S. Chemli and Experiments.
Activation around dump shielding, and design of beam line mask Mathieu Baudin, RP Genevieve Steele, EN-STI Helmut Vincke, RP.
Real time performance estimates of the LHC BPM and BLM system SL/BI.
J. MEKKI (1/8) 06/03/12 – RadWG meeting CNRAD plan Beam schedule – 1 st Slot Overall beam schedule for 2012 Equipments to be installed o Higher flux locations.
ATLAS-ALFA as a beam instrument Sune Jakobsen (BE-BI-PM and PH-ADO) on behave of the ATLAS-ALFA community LS1 LBOC meeting
● Morning: Physics fill with 25 bunches: – 07:00: Injection; – 07:25: Start ramp; – 09:00: End of squeeze and stable beams; – Emittances:  x1 = 3.0 
1 Sector Test – Preparation Layout in LSS7 Jan Uythoven (AB/BT) Thanks to Mike Lamont and the other ‘sector testers’
HiRadMat – Users Meeting 29/5/2015 Adrian Fabich EuCARD-2 is co-funded by the partners and the European Commission under Capacities 7th Framework Programme,
Status and organization of the H8c area Mirko Berretti 08/07/2015 (with M.Bozzo, N.Minafra, E.Oliveri, X. Pons…)
LHCf Detectors Sampling Calorimeter W 44 r.l, 1.6λ I Scintilator x 16 Layers Position Detector Scifi x 4 (Arm#1) Scilicon Tracker x 4(Arm#2) Detector size.
Transfer Line Test preparation meeting V. Kain, R. Alemany.
The integration of 420 m detectors into the LHC
Interface of FP420 to LHC FP420 meeting 28-Sep-2006.
06:00 – Ongoing injection problems on beam 2  07:42 – Start of injection investigations  11:11 – Injection problem fixed. Resteering of transfer line.
Accelerator Tunnel Layout (G01) Nick Gazis Senior Mechanical Engineer Review of ESS Accelerator Conventional Facility Design.
ATLAS Forward Proton Detectors ATLAS Forward Proton Detectors Michael Rijssenbeek for the ATLAS Collaboration Physics summary: Physics withSingle and Double.
LHC Status Sat Morning 30-June Bernhard Holzer, Jan Uythoven Status Friday Late: preparing restart some issues... LHCb dipole tripped / router problem.
Integration of forward physics detectors into the LSS of the LHC D. Macina (TS/LEA) Technical Support 2004 Workshop.
Fire and Oxygen Deficiency Detection Systems Risk Analysis S. Grau GS-ASE-Alarm Systems R2E Workshop, Tuesday Session 2: Equipment inventory,
ELENA installation progress F. Butin / ELENA collaboration.
Detector Safety System overview DSS is a PLC based system designed to protect ATLAS detector from damages. Front end (hardware) 2 redundant PLC ~700 input.
Testbeam Planning Common to all testbeams:
Collimation Activities during EYETS
Status of the ATLAS Forward Proton Detectors Michael Rijssenbeek for the ATLAS AFP group 25FEB2016.
Introduction Status before the 2009 run Results from the 2009 run
High Radiation to Materials 16th Project Team Meeting – May 20, 2010
LS2 LHC forward experiments
CNRAD dosimetry and Summary of the TS
Thursday morning – optics correction
Tuesday 22nd January - morning
Equipment of experiments directly interfering with the beam operation
2003 test beam with 25 ns bunched muons
Beam Dump and Injection Inhibits
Friday 14th September 03:15 Beta* at 1 km. Optics measurements, see yesterday. 07:00 Dump. 08:00 Refill with 3 nominal bunches for high beta. 11:15 Beams.
UITF Conduct of Operations Review
LS 1 start date 12th June Schedule Extension 2012 run Extension of 2012 run approved by the DG on 3rd July 2012.
Presentation transcript:

D.Macina TS/LEATOTEM Meeting25/02/2004 Roman Pot test at the SPS Test of the Roman Pot prototype in the SPS proposed in December 2003 (CERN/LHCC ): Recommended by the LHCC (28-29/01/04) Accepted by the SPSC (03/02/04) Accepted by the ATC (23/10/03) Formal approval will take place in the Research Board on February 26

D.Macina TS/LEATOTEM Meeting25/02/2004 Roman Pot Prototype The Roman Pot consists of: 2 pots (vertical plane) fully equipped Final cooling system Motors from LEP collimators and the associated remote control In addition we will get signals from: Nearby BPM (~1.5 m downstream) for triggering purposes (pseudo" intensity signal, i.e. the sum signal from each plane of measurement. Its amplitude would be intensity dependent) 3 BLM to study their response as the RP approaches the beam (to be used later in the LHC for protection purposes)

D.Macina TS/LEATOTEM Meeting25/02/2004 Locations Position of the RP in the tunnel Upstream the QD51910 quadrupole (near the ECX5) : The RP is not an aperture restriction for the wide Fixed Target Beam Low radiation area (< 1 Gy per week at ~20 cm from beam pipe) Enough space for the installation Racks and control room: Some space in the BB5 building (ATLAS storage) to minimize the cable length The bottom of ECA5 not possible for radiation safety reasons 3 racks allocated (to be installed at the level -1) in BB5 Control room location under discussion

D.Macina TS/LEATOTEM Meeting25/02/2004 Location in the SPS ring

D.Macina TS/LEATOTEM Meeting25/02/2004 Plan of the site at the SPS Point 5

D.Macina TS/LEATOTEM Meeting25/02/2004 The underground installation ECA and ECX5 racks RP 27.6 m beam

D.Macina TS/LEATOTEM Meeting25/02/2004

D.Macina TS/LEATOTEM Meeting25/02/2004

D.Macina TS/LEATOTEM Meeting25/02/2004

D.Macina TS/LEATOTEM Meeting25/02/2004

D.Macina TS/LEATOTEM Meeting25/02/2004 Horizontal cut at the beam height [cm] RP

D.Macina TS/LEATOTEM Meeting25/02/2004

D.Macina TS/LEATOTEM Meeting25/02/2004

D.Macina TS/LEATOTEM Meeting25/02/2004

D.Macina TS/LEATOTEM Meeting25/02/2004 RP integration in the SPS

D.Macina TS/LEATOTEM Meeting25/02/2004 Work (to be) done during shutdown Cables installation Already installed: 2 cables for the motors and their remote control 3 cables for detectors HV, LV(DOH)/temperature and pressure reading 8 cables for cooling and its control 1 for the BPM reading To be installed (in the following two weeks) Optical fibers CMS multiservice cables To be installed (in the following three weeks) Ethernet cable (from BB5 to the tunnel) RS MHz (from BA5 to BB5)

D.Macina TS/LEATOTEM Meeting25/02/2004 Work (to be) done during the shutdown Infrastructure installation: Dummy beam pipe (next week) Roman Pot Support (next week) Cooling (offers undergoing): Connection to the General water system Valves to reduce and regulate pressure Safety valves Flow meters Electricity (to be checked): 220 V and 380 V in the tunnel 220 V at the racks

D.Macina TS/LEATOTEM Meeting25/02/2004 RP support in the SPS Standard SPS support 450 mm

D.Macina TS/LEATOTEM Meeting25/02/2004 RP operation First discussion with the AB/OP group: During the NON-TOTEM runs: The SPS Control Room needs to know if the RP is in or out (we have to provide a signal based on our switches or ….) The Roman Pot will be software interlocked (beam dumped if RP in). The BLM may help to detect accidental movements (to be checked) We have to think about an inhibit signal, either hardware or software, to avoid accidental RP movements During the TOTEM runs: RP can be controlled either from BB5 or from SPS CR If access required, it takes ~ 30 minutes to start up the beam again

D.Macina TS/LEATOTEM Meeting25/02/2004 SPS schedule If we require <= 8 bunches in the machine : The machine set-up is similar to the one required for the LHC collimator test If the RP test follows the MDs dedicated to the LHC collimator tests => no additional set-up time Proposal : 2 eight-hours periods (from 8:00-16:00) following the LHC collimators MDs

D.Macina TS/LEATOTEM Meeting25/02/2004

D.Macina TS/LEATOTEM Meeting25/02/2004 RP installation Si det. installation 8-hours TOTEM runs Cooling installation