Integration of CLIC TBM in CLEX Electronics allocation and cables tracing Wilfrid Farabolini (CEA/IRFU) 16 October 2013.

Slides:



Advertisements
Similar presentations
André Augustinus 16 June 2003 DCS Workshop Safety.
Advertisements

Andrea Paoli AdV 1 st Project Review Cascina, November 3 rd, 2008 IME – infrastructure modifications for environmental noise reduction.
MODULE TRANSPORT CLIC Module Working Group 27 September 2010 Keith Kershaw CERN EN-HE.
Chinese International School Laboratory Refurbishment A case Study of laboratory design.
CERN TS Department / Civil Engineering Group 8 February 2008 Civil Engineering Layouts & Tunnel Cross Section 1 CLIC/ILC Collaboration Meeting 8 Feb 2008.
MICE: Hall Infrastructure Chris Nelson CEng CM16 8 th Oct 2006.
R. Corsini, CLIC Project Meeting - 24 th May 2013 CTF3 1 CTF3: Highlights of the 1 st run R. Corsini for the CTF3 Team 1.
LHCb Upgrade Optical Fibers from Cavern to the Surface - what has been done ? - prototypes status and next coming steps - what is missing for final installation.
ZTF Interconnecting Scheme Stephen Kaye
June 2004 Andrea Gaddi, PH-CMI USC Installation Commissioning Task Force 1st Run Meeting, June 3rd, 2004.
K. Alam, CLIC workshop, October 16-18, CLIC workshop, October 2007 Working group “ Two beam hardware and integration” Test module in the two.
TS Department / Civil Engineering Group 17 October 2007 Civil Engineering Layouts & Tunnel Cross Section 1 CLIC workshop – Working group: Two beam hardware.
1 5 December 2012 Laurent Roy Infrastructure / Electronics Upgrade -Cabling (long distance) -Rack and Crate (space, electrical distribution, cooling) -Detector.
Magnetic Shielding Issues Roy Preece STFC - RAL. Overview Issues Items in harms way – Step IV Step IV mitigation plan –Racks –Compressors Current / Future.
IMPACTS OF INSTALLING THE REFERENCE MAGNET PLACEMENT IN B december 2014 Fulvio Boattini & Natacha Lopez Hernandez.
Magnetic Shielding Roy Preece. Issues Cooling channel initially designed without return yolks. Current North and South shielding walls designed to encapsulate.
Undulator Orientation & Electron Beam Spacing Should the undulator frames be toward the central aisle or the tunnel walls? What is the optimum spacing.
1 Status of the CLIC two-beam module program A. Samochkine, G. Riddone Acknowledgements to the Module WG members 4 February 2014 CLIC Workshop 2014 (3-7.
Integration, Installation & Infrastructure Ans Pardons, with input from the WP4 members September 2014.
Magnetic Mitigation - Contents l Magnetic Mitigation General l West Wall Compressors l Rack Room 2 l Magnetic Shielding Yoke Jason Tarrant – Integration.
LHC Insertions Upgrade Working Group (LIUWG) Space available in tunnel Y. Muttoni.
CLEX TBM T0 Cooling system Progress Report 1 V. Soldatov, A. Vamvakas, BE-RF
Discussion points TBM meeting 23/09/2015. Updates Global 3D assembly updated, no severe problems/clashes T1 RF network dimensions updated WPS arms machined.
John Osborne : GS-SEM Civil Engineering 19 May 2009 Report on behalf of CLIC Civil Engineering and Services (CES) WG CTC 19 May 2009 Tunnel Cross Section.
GIF in EHN1- layout, construction and schedule Adrian Fabich, EN-MEF-LE GIF users meeting, 12 th February 2014.
Doug, here are some slides. FGT Electrical Integration ethernet trig/clk DDL fiber Wiener MPOD controller ISEG 8 ch HV -4 2 mA ARC module (APV Readout.
Dmitry Gudkov BE-RF-PM CLIC Module Working Group Engineering design of the adjustable supporting system for DBQ.
AD/ELENA (B193) Hall Extension F. Butin. Status The need of a new building for AD was already discussed in 2010, First pre-study shown to GTPE 1st Sept.
1 Thermal tests planning for mock-up TM0 Thermal tests planning for CLIC prototype module type 0 May 30th,
Update on the Laser Beam Line
EAR2 Beam Line Report on the Status C. Weiss EAR2 Beam Line - Report on the Status1.
Integration studies – Part 1 Inner triplet Y. Muttoni TS-ICC-LI 31 July 2008.
Overview of the main events related to TS equipment during 2007 Definition Number and category of the events Events and measures taken for each machine.
CLIC module Experimental program for module array Module review, June 22 nd 2015Elena Daskalaki, BE-RF-MK.
1 13 Octobre 2011 Laurent Roy ATCA Crate / Infrastructure in place -Rack in D3: dimension -Electrical power availability -Tell1 racks running in D3 (air.
V. Bobillier1 Cable installation status.
TBTS Test Program & Schedule G. Riddone
PS/SPS Days Roberto Losito/Oliver Aberle 13th January 2004
Radiation Protection studies for the Linac4 / Linac2 interface Joachim Vollaire, DGS-RP 28/09/2015 Linac4 Coordination Meeting.
R2E Point 5 mini safe room cooling / ventilation A. L. Perrot, 30 th April 2013.
Contents Jason Tarrant STFC Aim of Presentation to show: l Problem of compressors located at south shield wall l Description of compressor layout and services.
1 CTF3 CLEX day July 2006 CLEX day 2006 Introduction G.Geschonke CERN.
CLEX TBM T0 Cooling system Design strategy 1 V. Soldatov, A. Vamvakas, BE-RF
1 st LTEX meeting Protecting the experimental caverns and personnel from a "sector 34 like" incident: work planned in the LHC tunnel Prepared by M GASTAL.
Power, Cooling, Cables, Simulations of Heat Dissipation Short overview of ongoing work on these points Technical Coordination (Rolf Lindner et al.) Cooling.
Xbox and Structure testing news N. Catalan Lasheras, R. DeGiovanni, J. Giner-Navarro, G. Mcmonagle, I. Syratchev, B. Wooley, X. Wu
Dmitry Gudkov Phase correction of the CLIC TBM in CLEX Dmitry Gudkov Wilfrid Farabolini.
CTF3 Brief Summary W. Farabolini on behalf of the CTF3 team W. Farabolini - CLIC Project Meeting #19119 Dec
Baby MIND Module Cabling Options 27 th January 2016 F. Cadoux, Y. Favre, L. Nicola, E. Noah.
Decommissioning of CTF3 Nothing has been studied on the cost, manpower needed, environmental impact (RP) etc. This is just to raise some points that may.
ELENA installation progress F. Butin / ELENA collaboration.
S A Griffiths CM42 June 2015 Electrical & Control.
Scintillator testing in Prague (update from Aussois)
Update of MVD services and requests
CLEX Building Layout, Conventional Facilities, TL2, TL2’,
Tunnel Cross Section Studies
CLEX* Status and Plans CTF3 complex CLEX
Ideas for medium and long term facility upgrade Roberto Corsini for the CLIC Accelerator Collaboration.
TZ32 tunnel H. MAINAUD DURAND, BE-ABP/SU CTC 07/07/2009.
List of changes and improvements for the next generation CLIC module
ALICE Muon Tracking Upgrade EDR Answers
N-TOF EAR2 - Vertical beam design & construction - Irradiation facility proposal S. Girod EN-EA.
ATLAS ITk CO₂ Cooling pipe routing CO₂ Meeting, 28 June 2016
ATLAS ITk CO₂ Cooling pipe routing Common Mechanics meeting
The 11T cryo-assembly: summary of design and integration aspects
Radiation-safe area for electronics, or laser or
FCI and FCX Range FCI and FCX Range.
Extract from today’s talk given to DCB
STUB configuration Mats Pålsson
Review Bloc 4 and SM18 facilities and upgrade
Presentation transcript:

Integration of CLIC TBM in CLEX Electronics allocation and cables tracing Wilfrid Farabolini (CEA/IRFU) 16 October 2013

Cables and racks request TBM Cabling Summary System Racks for electronics Cable Type Quanti ty Ø (mm) Starting (S) and End (E) Points A Shielded bunkerCTF3 galleryTBMShielded bunkerOutside Shelter Pre- alignment Sensor conditioning crates (19"x 3U x 380mm) 3 x 43 U (3 racks) Rad-hard Muller MULRAD2404 S E 640 x Rad-hard Muller MULRAD264 S E 96 x MCA S E x MCA867.7 S E x MCA S E x NG S E 3267 x RF LDF x ethernet15 25 command for stepping motors control and Limit switch BI 1 rack 210 S E 200 x Vacuum 6 rows NG4 (4 conducteurs de 1mm2)28.7 S E x TCA3 (triaxial haute tension)27 S E 98 x DIODE: SVA3 (triaxial haute tension + 2 conducteurs 0.25mm2 basse tension)69.7 S E x NEG: PH3SJ (3x1.5mm2) 6A/10V max612.5 S E Magnet Cooling 2 x 43 U (2 racks) Temperature sensors305 E S 750 Supply pipe - SAS#1115 E S 225 Supply pipe - SAS#2115 E S 225 Supply pipe - PETS115 E S 225 Supply pipe - DBQ#1115E S 225 Supply pipe - DBQ#21 15 E S 225 Return pipe - SAS#1115 S E 225 Return pipe - SAS#2115 S E 225 Return pipe - PETS115 S E 225 Return pipe - DBQ#1115S E 225 Return pipe - DBQ#2115S E 225 Collected by Alexander Summarized by Dmitry mm 2 6 racks + 1 spare 5 holes + 1 spare Cables separation due to EMC constraints

1 st idea: additional drills on the ceiling Pros: - Minimum changes to the building Cons:- Delicate drilling (present cable tray and TBL line to be removed, dust inside) - Cables length > 20 m if to follow present cable trays - Problem to install new racks in the gallery - Staff in the gallery during operations CLIC Module TBL CALIFES

Shortest path from Module to Gallery Drill only on same rows as the present pits - building structure to be preserved – drilling the ceiling is problematic (GS/SE)

Problem to install the drilling machine Cable tray to be removed TBL equipments to be removed Protection from dust and water to be installed

Even more problems for cable path Cable trenches are full on this side Nothing authorized below air ducts level (transport vehicles) Any other path is very long (40 m for last installed RF cables)

Lack of space in the above gallery 2.5 crates available in the vacuum alley (to be negotiated) 3 crates available in the signals acquisition alley (after some rearrangement) Pits positions

2 nd solution: drill the wall towards CTF2 Pros: Simple drilling (Clear area, enough space for dust confinement) Possibility to install racks where are the disused 30 GHz racks Operations from a safer gallery (but still close to the X-Box1) Cons:Long cable length (>> 20 m, inside CLEX electronics required) Radioprotection of the CTF2 area to be investigated CLIC Module TBL CALIFES

Cables path towards CTF2 Possible drills More clearance but iron wall to be moved Possibility to add a cable tray under the ceiling but long path to reach the module (13 m to the wall) Only 3 crates available in the gallery above CTF2 if disused 30 GHz electronics is removed

Best choice: dedicated shelter on the car park Pros: Easiest drilling solution (from outside, minimum dust, clear area inside) Shortest possible cables length (< 20 m) Sufficient place to host the new racks Safe and comfortable operations inside the shelter (outside of the controlled area) Cons:New construction (Algeco 1 kCHF/m 2 ) with all services (air conditioning ?) Radioprotection of the car park to be investigated by RP CLIC Module TBL CALIFES Shelter 3 x 5 m

From Module to car park wall - Easy drilling of 6 holes (diam. 160 mm) with slope for RP - Still 2 m of trench to be cut to reach the wall x m fully available trench m to the wall (2.8 m thick) Alternatively use of the ventilation window chicane instead of drilling new holes (to be investigated)

A shelter on car park side 5 x 3 m available Example of a present shelter (high voltage electronics for TL2 tail clipper) Ventilation window

Possible shelter arrangements Dmitry Gudkov 4 x 3 m shelter

Conclusion The shelter on car park solution allows: -Minimal cable length and easy cables pulling (also a cost issue for “good” RF cables) -Easy crates installation and safe operations (outside controlled area) -Easy drilling of the holes (less building structure concern, drill from outside) -Alternatively possible use of the ventilation window (under investigation by Y. Body – EN-CV) -Possibility to displace some electronics cabinet inside for Rad- Hard tests -Requires cable trench extension (feasibility checked with (GS/SE) ) -RP to give the green light (G. Dumont contacted) -Decision to be taken by March 2014