Annette Czerneski, ACM IT Support North Central Region Construction Conference March 10, 2015.

Similar presentations


Presentation on theme: "Annette Czerneski, ACM IT Support North Central Region Construction Conference March 10, 2015."— Presentation transcript:

1 Annette Czerneski, ACM IT Support North Central Region Construction Conference March 10, 2015

2  Construction and design software installation and support.  Notify staff about software updates.  Notify staff about application or server outages.  Distribute new construction contracts to project leaders and assign to project managers for estimate approvals. 2 Shoulder compaction and shaping on STH 54 Wood County Contractor – S&N Project Leader – Martin Alekna, MSA Professional Services, Inc. Project Manager – Jeff Stewart

3 .NET Framework 4.5 (FieldManager)  Office 2010 or 2013 (Pantry)  Internet Explorer 10 (FieldNet web)  Cisco AnyConnect client (PT, MTS, FIIPS, HOD) 3

4  FieldManager, V5.1a  Field Information Tracking (FIT) 2015  Materials Information Tracking (MIT) 2015  ACMApplications folder  Backup  Pantry 2015  WisDOTShortcuts 4 USH 51 Minocqua Oneida County Contractor – Advance Construction Project Leader – Pat Bailey, REI Engineering, Inc. Project Manager – Dan Erva

5  Mobile Inspector is an iPad app WisDOT is using in conjunction with FieldManager.  Field staff can enter item quantity entry, men, equipment and weather at the construction site and it auto syncs with FieldManager.  Staff can take photos and attach them to an IDR.  Standalone versions of the CMM and Standard Spec are available on the iPad.  In 2014, WisDOT piloted the Mobile Inspector app with 1-2 inspectors per region office participating. 5

6  The Mobile Inspector app is free but WisDOT pays an annual license fee for the “Bridge” communication software between the app and FieldManager.  In 2015, there will be more WisDOT inspectors using iPads in the NE and SE Region offices.  Due licensing restrictions, this app will not be provided to consultant staff but we hope to have this resolved by the 2016 season. 6

7  Utilities | System Management | Maintain Users  Add User  Add each inspector for all the contracts within this database.  Enter the inspector’s associated iPad Device ID on this screen. Multiple device IDs can be entered. This was setup for states who use iPads, iPhones, Android phones, etc. 7

8  Docu (Change Contract Documentation) | Users  New tab for the Mobile Inspector app.  This is where the Project Leader selects the Mobile Inspector(s) for this specific contract. All users are entered under the Maintain Users section.  This needs to be completed for each contract and database installed on each computer with mobile inspectors. 8

9  Inspector Daily Reports / General tab  Origin - FieldManager, FieldBook or External (refers to Mobile Inspector) 9

10  IDRs AND Daily Diaries | Attachments tab You can attach Files or URL links 10

11  Items | Documentation tab  Compare the authorized quantity to the quantity placed and quantity paid.  Select “Yes” for the Item Completed field.  In the notes field, enter an explanation for the quantities variation.  Close FieldManager  Open FIT and merge data. Print the Explanation of Variation report in FIT. 11

12  Estimates | General tab  Required Estimate Comments field Work on this estimate was performed from _Date_ to _Date_. 12

13  FN Mailbox | Send Outbox | Get Mail  These buttons appear on all FieldManager windows. 13

14  Upon exiting your FieldManager database for the 5 th time, a Warning window will appear prompting you to backup.  The backup window was shortened due to the number of crashed FieldManager databases reported to Kristen McDaniel in 2014.  The initial backup is stored at C:\ProgramData\FieldManager\database\Backup  An additional backup can be saved on an external USB drive too. 14

15  We recommend performing weekly backups.  How to setup WisDOT backup process:  Create folder on USB drive named \ACMApplications  Copy C:\ACMApplications\backup\*.* to USB drive \ACMApplications folder  Each week run backup from USB drive:  Run \ACMApplications\Backup\ACMBackup.bat  Copies FieldManager, FIT and/or MIT databases  Option to backup current user’s profile too.  Store the backup device offsite. 15 Woodruff – Lac du Flambeau Vilas County Contractor – Integrity Grading and Excavating Project Leader – Pete Dieckman, NWBE, Inc. Project Manager – Jim Volkmann

16 Requirements to send data:  When the ECIP is approved.  When contract time starts.  When a contract modification is created.  When a contract modification is approved.  When work is completed on the contract.  When a DQI report is completed.  When an estimate is submitted. Required data entry:  DQI information  Explanation of Variation report  Data entered in FieldManager  Acceptance information  ECIP information  Proving period information for paint and landscaping)  When the ECIP is approved.  Late paving and seeding dates.  Claim submission and punch list completion dates.  Structure(s) information  Staff / Field Office information  Warranty information 16

17  Bomgar (remote access tool) will be used again this year to install updates and resolve issues.  If a company has 5 or more computers requiring updates they can be brought to a DTSD office or an on-site visit can be arranged.  Local administrative rights required for software installs.  Appointments (based on contract status):  New contracts starting in March and April  Active and carryover contracts  Existing contracts that are not finaled  Contracts starting in May or later this season 17 Business 51, Grand Avenue (City of Wausau) Marathon County Contractor – American Asphalt Project Leader – Dave Julson, EMCS Project Manager – Jed Peters

18  FieldManager 5.1 is the last version of FieldManager for WisDOT.  In 2016, staff will continue to use FieldManager 5.1a as we move staff to the new AASHTOWare web interface.  We plan to migrate carryover projects from FieldManager to the new web interface.  New projects will probably be started using the new web interface.  FIT and Project Tracking will probably be incorporated into the new web interface.  WisDOT will continue to use MIT, MTS and Pantry. 18

19  Annette Czerneski (715) 421-7319 or (715) 459-4773 annette.czerneski@dot.wi.gov annette.czerneski@dot.wi.gov  WisDOT IT Service Desk (800) 362-3050  ACM Support Portal https://acmsupport.dot.state.wi.us/ https://acmsupport.dot.state.wi.us/  2015 Construction Season PC User Guide Pantry2015\RegionSpecific\ NorthCentralRegion\ 19 Construction of retaining wall, BUS 51 interchange project, Rothschild Marathon County Contractor – Lunda Construction Project Leader – Dave Katzner, MSA Professional Services, Inc. Project Manager – Wendy Arneson

20 20 Segment of the U/K Interchange project - County U bridge over USH 51 and the County U Urban Reconstruction Marathon County Contractor – Michels Inc. Project Leader – Michael Dombeck, Gremmer & Associates Project Manager – Dan Erva