Presentation is loading. Please wait.

Presentation is loading. Please wait.

VELO Module Mid-Term Review T. Bowcock 11 October, 2006.

Similar presentations


Presentation on theme: "VELO Module Mid-Term Review T. Bowcock 11 October, 2006."— Presentation transcript:

1 VELO Module Mid-Term Review T. Bowcock 11 October, 2006

2 Themis Bowcock - MTR Overview Introduction Why? Terms of reference Timeline Project Summary

3 Themis Bowcock - MTR Introduction Why? Consolidate and review production STOP before we go too far Produce a revised baseline procedures Larger statistics from PRR Identify new problems (fix!) Public record Refereed (Tim Jones) Input of experience from other experiments

4 Themis Bowcock - MTR Introduction: Terms of reference Review documentation checklists, and idiot guides Review data to identify problems Compile list of issues that need to be addressed Identify priority items that must be addressed before production restarted Produce short written report to the Technical Board of LHCb

5 Themis Bowcock - MTR Introduction Timeline 11 th Oct: MTR at Liverpool – Full day 12 th Oct: Summary of MTR with CERN VELO management 16 th Oct: Written Report of MTR to TB … Restart production (if possible)

6 Themis Bowcock - MTR Project: Resources PPARC (1998-2006) ~1.1MChf hardware including R&D 42 Si Modules and cables (no large number spares) Note PPARC not paying for FE Chips R&D ~250kChf or 50kCHf/yr to 2005 Limited ability to produce early prototypes and modules Liverpool/HEFCE and JIF Liverpool Semiconductor Detector Centre infrastrure Limited funding from Department ~50kChf

7 Themis Bowcock - MTR Project: Staff NameResponsibilityActivity Themis Bowcock Group Leader John CarrollProject EngineerAssembly Testing Metrology Torkjell Huse AssemblyQualification Gianluigi Casse Qualification Rolf Oldeman Qualification Mark Tobin SoftwareCERN Peter Cooke Production Workshop Staff Production Hybrids/Bonding Phil Turner Testing Tara Shears Testing Lisa Dwyer TestingCERN Anthony Affolder Testing Peter Sutcliffe Testing/Metrology NameResponsibilityActivity David HutchcroftSoftware CoordinatorSoftwareTesting David Jones SoftwareTesting Kurt Rinnert SoftwareTesting Tony Smith Production Coordinator Hybrids Ashley Greenall Hybrids Geoff Southern Hybrids Dave Muskett Testing/Metrology Assembly Mike Wormald Hybrids/Bonding Assembly Mark Whitley Hybrids/Bonding Girish PatelQuality Assurance QA Karol Hennessy*Software Qualification Mike LockwoodOperations Assembly * University College Dublin

8 Themis Bowcock - MTR Project: Staff

9 Themis Bowcock - MTR Project: Oversight

10 Themis Bowcock - MTR Project: Management Gantt Has been replaced as we move into quasi DC operation Replaced by detailed time/worksheet optimized for throughput Areas of competance Weekly and Daily Meetings e-log (well used) Risk Register

11 Themis Bowcock - MTR Geometry (42 modules R&Phi) R sensors must be positioned within 20 um (gauss sigma) in X and Y of the nominal position relative to the base. R sensors must be positioned within 100 um (gauss sigma) in Z of the nominal position relative to the base. Phi sensors must fit within tolerances given by RF foil. The positioning has no further requirements, but the actual position must be known to an accuracy of about 10 um relative to the R sensor. Addition of constraint system See metrology discussion Project: Modules

12 Themis Bowcock - MTR Project: Module Specification Temperature The sensors operate at a nominal operational temperature of ~ -5° C.

13 Themis Bowcock - MTR Project: Module Specification Outgassing outgas_one_module < 1e-4 mbar liter / s after approx 4 hours in vacuum.

14 Themis Bowcock - MTR Project: Module Specification Electrical The module should be designed to sustain up to 600 V in vacuum @ < 1e-4mbar. Channels lost Sensors (20) Final module max 25/side

15 Themis Bowcock - MTR Summary Project approximately at mid-point Are we doing the right things? What more can we do to improve? Are we meeting our goals? Today…

16 Themis Bowcock - MTR Summary: Today Session I: QA & documentation Session II: Data Summaries Session III: Logistics,Infrastructure… Session IV: Discussion


Download ppt "VELO Module Mid-Term Review T. Bowcock 11 October, 2006."

Similar presentations


Ads by Google