St Johnsbury BF 7000(20) Bridge 6 on VT Route 2B over the Lamoille Valley Rail Trail Presenter: John Byatt, PE Consultant Project Manager.

Similar presentations


Presentation on theme: "St Johnsbury BF 7000(20) Bridge 6 on VT Route 2B over the Lamoille Valley Rail Trail Presenter: John Byatt, PE Consultant Project Manager."— Presentation transcript:

1 St Johnsbury BF 7000(20) Bridge 6 on VT Route 2B over the Lamoille Valley Rail Trail Presenter: John Byatt, PE Consultant Project Manager

2 PROJECT LOCATION

3 Purpose of Meeting Present the project background and existing conditions Present the replacement structure selected Discuss maintenance of traffic options Receive public input

4 Meeting Agenda Vtrans Project Development Process Project Background Existing Conditions Preferred Alternative Maintenance Of Traffic Schedule Questions

5 Phases of Development Project DefinitionProject DesignConstruction Project Funded Project Defined Contract Award Identify resources & constraints Evaluate alternatives Public Participation Quantify areas of impact Environmental permits Develop plans, estimate and specifications

6 Who are you representing? A.Municipal Official B.Resident C.Local Business D.Independent Organization E.Other

7 What is your reason for attending this meeting? A.Specific Concern B.General Interest C.Live in close vicinity D.Other

8 Which would you be most concerned about? A.Closure Duration B.Bridge Aesthetics C.Environmental Impacts D.LVRT Impacts E.Other F.Not really concerned

9 Description of Terms Used Beams (Superstructure) Deck Abutment (Substructure) Bridge Rail

10 More Terms Used Beam (Superstructure) Deck Abutment (Substructure) Span Pier (Substructure) Water Span Bridge Length Elevation View of Bridge

11 Project Background The structure is owned and maintained by the State Funding will be 80/20 Federal/State (no local funds) Functionally labeled as an Urban Minor Arterial Posted Speed = 35 mph (Design Speed) Existing bridge is a three-span steel beam w/ concrete deck Bridge length = 129 feet (42’ maximum span) Bridge Width = 25 feet (curb-curb with 5’ sidewalk) The bridge was built in 1936 (77 years old)

12 Traffic Data “Current Year” 2016 “Design Year” 2036 Average Annual Daily Traffic820860 Design Hourly Volume8590 Average Daily Truck Traffic2030 %Trucks1.62.2

13 EXISTING BRIDGE DEFICIENCIES Deficiencies Structurally Deficient The bridge and approaches are too narrow for the roadway classification and design speed The bridge railing is substandard On-going maintenance needed Inspection Rating Information (Based on a scale of 9) Bridge Deck Rating4 Poor Superstructure Rating4 Poor Substructure Rating4 Poor Rating Definitions 9 Excellent 8 Very Good 7 Good 6 Satisfactory 5 Fair 4 Poor 3 Serious 2 Critical 1 Imminent Failure

14 Special Concerns Railroad Clearance to be maintained Geotechnical Issues/Sensors Groundwater Issues Existing Water Main 4f Historic Requirements Impact to LVRT Retaining wall at driveway

15 Looking west over Bridge

16 Pier deterioration at beam support

17 Looking under the bridge at deck and beams

18 Rust and Leakage under Deck

19 Undermining of West Abutment

20 Temporary Repair at West Abutment

21 Project Goals Improve overall condition of the crossing Improve substandard bridge width Improve substandard rail Meet historic requirements Minimize impacts to rail trail, utilities, buildings, egress, right-of-way and cultural resources

22 Alternatives Discussion Considered closing the bridge permanently Considered an at-grade trail crossing Rehabilitation was ruled out due to the deteriorated condition of the existing bridge Full bridge replacement is preferred alternative Prefabricated Steel Plate Arch structure was selected as the bridge type

23 What will bridge look like?

24

25 Typical Bridge Section

26 Proposed Roadway Section

27

28 Ways to Maintain Traffic Road Closures – Main method - Traffic to use state signed detour route via Route 2. One-way Alternating Traffic – Temporary traffic signal would control traffic through construction site. Would be used before or after road closure Would not be used throughout construction Rail Trail would be closed during construction Abutter access will be maintained to property

29 State Detour Route Green Route: 3.4 Miles Purple Detour Route: 4.4 Miles Added Miles: 1.0 Miles End to End Distance: 7.8 Miles Major Factors Added Miles: 1.0 Traffic Volume: 820 vpd Duration

30 Mitigation Strategies for Bridge Closures Some ideas on how these impacts are often mitigated: Accelerated construction duration including: Allowance for working 24 hours per day and 7 days per week Incentive/Dis-incentive clause to encourage the contractor ($$) Noise limits included in contract for night time work Municipalities are compensated for bypass impacts Grant assistance from Agency of Commerce & Community Development

31 One-way Alternating Traffic

32 Accelerated Bridge Construction Driven steel piles with precast concrete cap for abutment

33 Accelerated Bridge Construction Precast Concrete Cap placed in two sections

34 Accelerated Bridge Construction Precast concrete Abutment in place

35 Options to Maintain Traffic 6 week road closure with 3 weeks of alternating one- way traffic –Standard construction methods –7 days per week –Extended (12+ hour) days 8 week road closure with no alternating one-way traffic –Standard construction methods –7 days per week –Extended (12+ hour) days

36 Options to Maintain Traffic 6 week road closure with no alternating one-way traffic – –Accelerated Bridge Construction (ABC) techniques –7 days per week –24 hour construction allowed –Increased Costs

37 How often do you use this segment of Route 2B? A.Daily B.Weekly C.Monthly D.Rarely E.Never

38 What is your preferred MOT option? A.6 week closure/3 week one-way alt B.8 week closure C.6 week closure with ABC

39 Schedule Dependent on Project Development time and ROW acquisition time Current construction is Summer 2017

40 Did you find this presentation to be? A.Too technical in nature B.Too simplified C.Just about right D.Not much use at all

41 Questions